IDR Sheet of Sheets
Final Record Book Page
Contract 7624
Day Tuesday Date 9/8/09
WSDOT Exchange Property
City Transfer crew continued to use the conveyor belt to move native soils from the
Rolling Hills excavation. Material was placed by a track hoe to the area above the
conveyor belt and a dozer spread soil along this bench. A roller compacted the material.
Because of heavy rain over the week-end, no layers were placed on the soil reinforced
slope this morning. Some discussion occurred among City transfer and Merlino crew
about whether to proceed with today’s embankment work or come back tomorrow when
the grade is drier. They decided continue work and scrape ponded water from the surface
grade at Elev 183 between Sta. 11+75 to 13+00.
Some erosion on the side slopes was observed. Silt in the drainage ditch and and rock
lined ditch to the I- 405 shoulder below.
9:00 – Dan Quehl, Mayes Inspector on site. Dan said City Transfer crew worked
Saturday and placed two geogrid layers.
9:30 – Ken Viren, WSDOT not on site, today.
11:00 – Dan Lonsdale on site.
Benson Hill Road
Gary Merlino crew continued excavation of the hillside east of the roadway and dumping
it on the west side. Two flaggers were used for traffic control. Traffic, on both north and
southbound lanes, was stopped for several minutes to place material. After noon, this
material was transported to the conveyor belt.
2:00 - Traffic control was removed from Benson Road.
Rolling Hills
A dozer and track hoe continued to excavate to hillside north of the Benson Hill Bridge
and along the northbound lanes. Native soils were loaded onto a conveyor belt to the
WSDOT Exchange Property.
DOT Form 422-004A EF Inspector