HomeMy WebLinkAbout20090902_TIBInspector's Daily Report
Project Name Date Shift
Sheet 1 of 2 day
Weather
AM PM
Inspector IDR Report #
No.
Photos/Videos taken today? Yes x No File:
Inspector's Shift Hours
From:
To:Inspector's Signature
Reviewed By
yes
Signs Barricades
no
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
Traffic Control
Yes
Reviewed
Subcontractor Number & Classification
Plan SheetItem Quanity
IDR Sheet
Item Number Material / Item Description
Major Equipment on Project
CDB Number & Classification
Tim Bergstrom 20090902 TB
Bid Items Inspected Today/Field Note
Flaggers
Location Structure#/Station
Acceptable
Date
8:15am
Date
Yesno
10:15am
TR (9/4/2009)
September 2, 2009
September 2, 2009
Tim Bergstrom
Inspector's Daily Report
Project Number
Sheet 2 of 2
Inspector IDR Report #
20090902 TB
September 2, 2009
DateIDR Sheet
Tim Bergstrom
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
Inspector's Notes
T09082 Todays activities:
Lab work was done including feild density test gradations and data entry. Processing and distribution of test results from
WSDOT Mats lab was also done.
TImothy I. Bergstrom,
Mayes Testing Engineers, Inc.
tbergstrom@mayestesting.com
253-223-5360
Inspector's Daily Report
Project Number
Sheet 3 of 3
Inspector IDR Report #
IDR Sheet Date
20090902 TB
Inspector's Notes
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project September 2, 2009
Tim Bergstrom