HomeMy WebLinkAbout20090915_TIBInspector's Daily Report
Project Name Date Shift
Sheet 1 of 2 day
Weather
AM PM
Inspector IDR Report #
No.
Foreman
Traffic Control Supervisor
Apprentices / Trainees
Cat 962H Dozer
1
1
1
1
Photos/Videos taken today? Yes X No File:
Inspector's Shift Hours
From:
To:Inspector's Signature
Reviewed By
Locator - " " "
September 15, 2009
September 15, 2009
Tim Bergstrom
3:30 PM
(TR 9.17.2009)
Yesno
Acceptable
Date
11:00 AM
Date
Hitachi EX450 Excavator
Location Structure#/Station
Chevrolet Silverado Sevice Truck
Bid Items Inspected Today/Field Note
Flaggers
Sunny and Clear 70F to 77F
Tim Bergstrom 20090915 TB
Takeuchi TB016 backhoe
Operators
Flaggers
Laborers
Carpenters
Superintendent Superintendent - Trenchless Construction Services
Operator - " " "
John Deere Dozer 650J
Dynapac 16 Ton Vibratory Roller Flat bed trailer 1669 -- NI
Johnston 650 Water Truck
Vactron TruckMix Truck w/ 2- ST500 mixer pumps
Hitachi 270LC Pac Hoe
IDR Sheet
Item Number Material / Item Description
Major Equipment on Project
CDB Number & Classification
Cat Dozer D6
Cat D5GXL Dozer
John Deere Offroad Dump Trucks
Ford Flat Bed Truck
Subcontractor Number & Classification
Case Series 2 580 Super M+ excavator/hoepack
Kubota Super Series excavoator KX 161-3
Plan SheetItem Quanity
Vermeer D24x40 series II Boring Machine w/50 10' Rods
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
Traffic Control
Yes
Reviewed
yes
Signs Barricades
no
Inspector's Daily Report
Project Number
Sheet 2 of 2
Inspector IDR Report #
IDR Sheet
Tim Bergstrom
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
Inspector's Notes
September 15, 2009
Date
20090915 TB
Personel Used on Project this day;
1)Steve Pollard -- Foreman Elcon
2) Matt Andresen -- Apprentice Elcon
3) Scott Schulz -- Apprentice/Laborer Elcon
4) Scott Pederson -- Operator
T09082 Todays activities listed for Elcon at Talbot Onramp;
Contractor excavated a 3 foot deep trench for conduit containg fiberoptics. Conduit containing fiberoptics were
placed at the bottom of the trench and CDF was placed on top filling the trench approx. 6" below grade. The
CDF exceeded the minimum depth of 24" over the conduit. The trench extends from station 1214+00 parallel to
I-405 going north bound to station 1215+20.
One two inch diameter conduit piping contains wiring for temporary lighting. There are also (2) 4 inch conduit
pipings. One is for future use while the other contains interduct fiberoptic and twp (twisted wire pair).
See attached Stoneway ticket detailing cement truck CDF load.
A sample was obtained from the Defoor site for proctor analysis.
Time also includes maintenance and sample storage.
TImothy I. Bergstrom,
Mayes Testing Engineers, Inc.
tbergstrom@mayestesting.com
253-223-5360