HomeMy WebLinkAbout20091001_DQInspector's Daily Report
Project Name Date Shift
Sheet 1 of 3 day
Weather
AM PM
Inspector IDR Report #
No. No.
11
4 Laborers with CDB 7
12
2
1
1 650J John Deere Dozer
1
1
1
1
1
1
Photos/Videos taken today?x Yes No File:
Inspector's Shift Hours
From:
To:Inspector's Signature
Reviewed By
Laborers with CTI
10/01/009
October 1, 2009
Daniel Quehl
7:00 PM
TR (10.1.09)
Acceptable
Date
6:00 AM
Date
EX 450 Hitachi excavators
Location Structure#/Station
Bid Items Inspected Today/Field Note
Flaggers
light rain, hi 62 low 61
Daniel Quehl 20091001 DQ
Operator with CDB
General Foreman with CDB Foreman with CTI
Operators with CTI
TC-9 Komatsu small dump crawler(idle)
350P John Deere offroad dump truck
D6 Cat dozer
Dynapac 16 ton vibratory roller
IDR Sheet
Item Number Material / Item Description
Major Equipment on Project
CDB Number & Classification
EX 270LC Hitachi excavator with hoepack
water truck
312C Cat Excavator(idle)
Subcontractor Number & Classification
Plan SheetItem Quanity
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
cloudy, hi 61 low 51
Traffic Control
ReviewedSigns Barricades
Inspector's Daily Report
Project Number
Sheet 2 of 3
Inspector IDR Report #
IDR Sheet
Daniel Quehl
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
Inspector's Notes
October 1, 2009
Date
20091001 DQ
T oday' s activities listed for CDB at the Defoor site:
Attended the CDB weekly saftey meeting.
Performed observation and soil density testing on fill using common borrow over Miragrid 3XT and SF-55 /Miragrid 3XT
Geogrid reinforcing(remainder of used rolls being used in place of SF-20 Secondary Geogrid
reinforcing) from stations 10+35 to 14+00.
Performed soil density testing at above locations per T310 and SOP 615 (Method 1) using a Troxler nuclear density gauge
model 3440. The moisture density relationship value of 115.9 with a 12.4% optimum moisture was used per Mayes Testing
lab number T-09082-28. The test met the 95% required compaction. The contractor was informed of test results. See
attached Field Density Report and Density Work Sheet for results and locations.
While the Geogrid Reinforcing was being installed from stations 10+35 to 14+00 the following was verified:
1. Checked to assure that the proper type of Geogrid reinforcing was being used and was not damaged.
2. Checked to assure the minimum embedment depth was attained according to approved plans&specs
3. Checked that Geogrid was attached together, with the subcontractor using twist ties placed at a 1' to spacing and
overlapping the Geogrid 2 to 6 inches.
4. There was 30 Rolls Miragrid and Miragrid 3XT/SF-55(remainder of the used rolls used in place of SF-20) for Secondary
Geogrid reinforcing were placed today.
5. That fill being placed did not exceed 1'. The subcontractor is using a laser to check elevations on each lift.
6. That the Geogrid was laying flat and not bundled up prior to fill being placed.
7. The unused Geogrid was covered with black plastic to protect from the sun.
Elevations 217 and 218 were completed from stations 10+35 to 14+00 with installation and inspection of the Primary and
Secondary Geogrid reinforcing. At elevation 219 the fill was placed from stations 10+35 to 11+00 and compacted but no
Primary Geogrid reinforcing had been placed at this elevation yet.
CTI placed a total of 2,117 cubic yards of common borrow 1,742 cubic yards moved by the dozer and 375 cubic yards
transported from 15 truck loads. There was 3,432 cubic yards transported from the conveyor belt today from 156 truck loads.
Performed observation of the fully loaded 350D offroad dump truck and water truck driving over the
compacted areas and material appeared to be firm and unyielding.
Visited by Don Robertson the Safety manager with Gary Merlino,Robert Patcheck with CDB, and Chad Webley the Field
Eng. with CDB to see the progress of the project.
Ken Viren the materials technician with WSDOT performed a soils density test per T310 and obtained a sample per SOP
615. Bob Pyle the compliance inspector with WSDOT visited the site throughout the day.
The stockpile of the unsuitable materials which was located on the northeast area of the site was all transported today to the
non reinforcing area next to Cedar road from stations 12+00 to 14+00 and covered with plastic. There was a total of 3,075
cubic yards transported today from a total of 123 truck loads.
Performed observation while excavation was taking place from stations 15+00 to 15+95 in non reinforcing area where the
stockpile of unsuitable materials was located to ensure that the area was free of any organics prior to fill with common
borrow. Organics though were encountered while excavating. Roch Player the Engineer with CDB was contacted and
visited the site giving his approval,after his inspection of the area including the organics encountered,to go ahead with fill
using the common borrow.
Inspector's Daily Report
Project Number
Sheet 3 of 3
Inspector IDR Report #
Inspector's Notes
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project October 1, 2009
Daniel Quehl
IDR Sheet Date
20091001 DQ
Personal present at the Defoor site:
1. Dan Lonsdale-General Foreman with CDB
2. Kevin Wicklund-Foreman with CTI
3.Mark Klinkhammer-Operator with CTI
4.Ken Hashon -Operator with CTI
5.Mark Furnier-Operator with CTI
6.Jay Knudtsen-Operator with CTI
7.Bill Smith-Laborer /Operator with CTI
8. Robert Gamble-Operator with CTI
9.Mike Forest-Laborer with CTI
10.Mark Candee-Operator with CDB
11. Jim Davis-Laborer with CDB
12.Will Fletland-Operator with CTI
13. Dave Dover-Foreman with CDB
14.Matt Axelson-Laborer with CDB
15.Jesus-Laborer with CDB
Equipment used on the site:
1.350P John Deere offroad dump truck
2.Two EX450 Hitachi excavators
3. EX270LC Hitachi excavator with Hoepack
4.D6 Cat dozer
5.Dynapac 16 ton vibratory roller
6.650J John Deere dozer
7.water truck
8.312C Cat Excavator (idle today)
9.TC-9 Komatsu small dump crawler(idle today)
Page of**120.8121.8115.9AverageDepth or Elevation (feet)Direct TransmissionDirect TransmissionCompaction %FieldMoisture Content %Dry Density (PCF)Backscatter / Direct TransmissionLaboratoryMax Dry Density (PCF)9520115.9MTE Nuclear Gauge No.:Wet Density (PCF)9.410.2ASTM D 693812.4Test #11a-12'below finishgrde-12'below finishgrdeLocationIn our opinion, fill generally meets specifications as indicated by test numbers:Soil Type DescriptionTan silty sand with trace of oversizeTan silty sand with trace of oversizeTan silty sand with trace of oversizeFill over Geogrid Reinforcing at Defoor site 140' east of ditchline at station 11+35Contractor AdvisedFull-time observationMethod of Adding Moisture:fire hose and water truck1 footComments: *See Attached Density Work Sheet for test #1Type and Number of Compaction units:Number of Passes:16 ton roller&Hoepack3to4Part-time observationDry Density: 10.2QC Sample:Test No.:Fill over Geogrid Reinforcing at Defoor site 140' east of ditchline at station 11+35Project No.:Type and Number of earth moving units:Dozer and ExcavatorASTM D 698 (Standard Proctor)ASTM D 1557 (Modified Proctor)Specification Compaction and Material :95%-T99 11Date: 10/01/009T09082WSDOT I405,I5 to SR169Daniel QuehlMoisture %:SoilFIELD DENSITY TEST REPORT1a 110.6In our opinion, fill does not meet specifications as indicated by test numbers:Fill test meets compaction specificationsProject:Inspector:110.4110.6OMC %12.420225 Cedar Valley Road, Suite 110 Ph 425.742.9360 Lynnwood, WA 98036 Fax 425.745.1737 10029 S. Tacoma Way, Suite E-2 Ph 253.584.3720 Tacoma, WA 98499 Fax 253.584.3707 7911 NE 33rd Drive, Suite 190 Ph 503.281.7515 Portland, OR 97211 Fax 503.281.7579 MTE 1400-2C, Rev 2, 4/1/08
Project #:Date: 10/1/2009
Project :20
Inspector: Test Method: WSDOT FOP for AASHTO T310
123
10+35 to 15+95
T-09082-28
11+35
N/A
Common
-12
0 degrees 110.4
90 degrees 110.6
average 110.5 0.0 0.0
0 degrees 9.4
90 degrees 10.2
average 9.8 0.0 0.0
11.98
0.00
11.98 0.00 0.00
0.40
0.00
0.40 0.00 0.00
3 #DIV/0! #DIV/0!
96.68 #DIV/0! #DIV/0!
115.9
95.3 #DIV/0! #DIV/0!
12.4
12.4
12.4 #DIV/0! 12.4
Thomas B Robinson
Reviewed By:
Comments:
Soils Field Density Worksheet for WSDOT Projects (WSDOT SOP 615)
Moisture Density Curve #
Test Station
Station to Station
Worksheet used when Maximum Density is determined using WSDOT Method T99
Daniel Quehl
WSDOT I405,I5 to SR169 MTE Nuclear Gauge #:
Material Type
Depth of Material
Dry Density lbs/cu.ft.
Test Hole Number
Optimum Moisture Content Corrected = ((6 x 7) + (5 x 8)) / 100
(6) % Passing #4 Sieve = (100 - % Retained)
Density and Optimum Moisture Determination WSDOT T99
Percent Compaction (% of maximum) = (Dry Density / Corrected Maximum Density) x 100
Maximum Density (from Maximum Density Curve Table)
(7) Optimum Moisture of Fine Material, passing #4 (from Maximum Density Curve Report)
(8) Optimum Moisture of Coarse Material, retained #4 (from Maximum Density Curve Report)
(1) Mass of Sample (Dry or SSD) + Tare
(2) Mass of Tare A
T-09082
Gradation Determination
Average Moisture Content
Reference to Centerline
Moisture Content
Average Dry Density lb/cu.ft.
Gauge Readings
(5) % Retained on #4 Sieve (% Oversize) = Mass Retained / Mass of Sample
Mass of Sample (Dry or SSD) = (1) - (2)
(3) Mass of Retained on #4 Sieve + Tare
(4) Mass of Tare B
Mass of Material Retained on #4 Sieve = (3) - (4)