HomeMy WebLinkAbout20091006_TIBInspector's Daily Report
Project Name Date Shift
Sheet 1 of 2 day
Weather
AM PM
Inspector IDR Report #
No.
11
1 Laborer-CDB 7
13
2
1
1
1
1
1
1
1
Photos/Videos taken today? Yes X No File:
Inspector's Shift Hours
From:
To:Inspector's Signature
13hrs
Reviewed By
Laborers-CTI
October 6, 2009
October 6, 2009
Tim Bergstrom
8:30pm
TR (10.7.2009)
Yesno
Acceptable
Date
7:30am
Date
Hitachi EX450 Excavator
Location Structure#/Station
Komatsu TC9
Bid Items Inspected Today/Field Note
Flaggers
Sunny and Clear 59F to 60 F
Tim Bergstrom 20091006 TB
Operator-CDB
General Foreman-CDB Foreman-CTI
Operators-CTI
John Deere Dozer 650J
Dynapac 16 Ton Vibratory Roller
Water Truck
Hitachi 270LC Pac Hoe
IDR Sheet
Item Number Material / Item Description
Major Equipment on Project
CDB Number & Classification
Cat Dozer D6H LGP
Cat D5GXL Dozer
John Deere Offroad Dump Trucks
Subcontractor Number & Classification
Plan SheetItem Quanity
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
Sunny and Clear 47 F to 59 F
Traffic Control
Yes
Reviewed
yes
Signs Barricades
no
Inspector's Daily Report
Project Number
Sheet 2 of 2
Inspector IDR Report #
IDR Sheet
Tim Bergstrom
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
Inspector's Notes
October 6, 2009
Date
20091006 TB
Personel Used on Project this day;
1)Kevin Wicklund - Superintendant CTI
2) Mark Klinkhammer - Foreman CTI
3) Will - Operator CTI
4) Leo - Operator CTI
5) Ken Hann - Operator CTI
6) Robert Gamble - Operator
7) Mike Forest - Laborer CTI
8) Bill Smith - Operator/Laborer CTI
9) Jim Brown - Laborer GaryMerlino
T09082 Todays activities listed for CDB at Defoor Site:
Observation and soil testing on common borrow placed over SF-55 geogrid reinforcing from stations 15+50 to 15+95 on lift at
elevation 221' left over from the 10/5/2009.
Observation and soil testing on common borrow placed over SF-20 geogrid reinforcing from stations 11+75 to 15+95 for
secondary lift at elevation at 222'.
Observation and soil testing on common borrow placed over SF-55 geogrid reinforcing from stations 11+75 to 15+95 on lift at
elevation 223'.
Performed soil density testing at above locations as per T310 using a nuclear density gauge model number 3440 and a standard
proctor value of 113.0 pcf @ 12.6 optimum moisture. The tests met the required compaction on fill and contractor was informed
of test results. See attached Field Density Report for results and locations.
The common borrow used had previously been transported by conveyor belt from the Rolling Hills site south of Thunder Creek.
The following items were verified:
1) Proper type of geogrid reinforcing was used and was not damaged prior to installation.
2) Checked to assure the minimum embedment depth was attained according to approved plans & specifications.
3) Checked that geogrid was attached together, subcontractor was using twist ties placing with 1' to 2' spacing and overlapping
geogrid 2" to 6".
4) A total of 49 rolls of SF-55 geogrid placed as primary reinforcment and 3 rolls of SF-20 geogrid placed as secondary
reinforcing was layed today.
5) Fill placed did not exceed 1' lifts verified by laser to check elevations each lift.
6) Geogrid was laying flat and not bundled up prior to fill.
Foreman on site verified approximately 3025 cubic yards of material was placed today.
Observed one 350 offroad dump trucks driving over compacted material throughout the day with no deflection or yielding in the
material.
The CTI subcontractor placed a total of two full lifts of fill today and one partial lift not completed the previous day.
Lifts at elevations of 222, 223, and 224 ft above sea level were compacted and tested. No further testing is required until the
next lift at 225 ft above sea level is placed.
Lab work was also done including loggin in of grout specimens as well as compressive strength testing of one 7 day aged
concrete cylinder. The specimen tested today was above design strength at 7 days with a compressive strength result of 5530
psi.
TImothy I. Bergstrom,
Mayes Testing Engineers, Inc.
tbergstrom@mayestesting.com
253-223-5360
Page of3a 112.2 Moisture %:SoilFIELD DENSITY TEST REPORT11.7Direct TransmissionDirect TransmissionT09082WSDOT I405, I5 to SR169T. BergstromProject No.:Project:Inspector:21Date: 10/6/2009Specification Compaction and Material :95% -- T99Tan Silty Sand with Trace OversizeTan Silty Sand with Trace OversizeTan Silty Sand with Trace OversizeTan Silty Sand with Trace Oversize*99.3*98.3Type and Number of earth moving units:2 excavators 2 dozersASTM D 698 (Standard Proctor)ASTM D 1557 (Modified Proctor)9.810.312.3120.9123.4124.5Direct TransmissionDirect TransmissionAlong the 1.5:1 slope at station 13+00 50' east of the bottom Geogrid benchAverageAlong the 1.5:1 slope at station 14+50 50' east of the bottom Geogrid benchAlong the 1.5:1 slope at station 14+50 35' east of the bottom Geogrid bench* See Density WorksheetType and Number of Compaction units:Number of Passes:1 hoepack 1 roller3to4Part-time observationDry Density: 11QC Sample:Test No.:Thickness of lift:Contractor AdvisedFull-time observationMethod of Adding Moisture:firehose1 footComments:LocationIn our opinion, fill generally meets specifications as indicated by test numbers:Soil Type DescriptionTan Silty Sand with Trace OversizeTan Silty Sand with Trace OversizeTan Silty Sand with Trace OversizeAlong the 1.5:1 slope at station 13+00 50' east of the bottom Geogrid benchAlong the 1.5:1 slope at station 14+50 35' east of the bottom Geogrid benchIn our opinion, fill does not meet specifications as indicated by test numbers:Fill test meets compaction specifications-10 ft-10 ft-12 ft-12 ft-11 ft-181ftTest #11a23aAverage2a3Along the 1.5:1 slope at station 14+50 35' east of the bottom Geogrid benchAverage20Tan Silty Sand with Trace OversizeTan Silty Sand with Trace Oversize*97.1Wet Density (PCF)13.010.9Depth or Elevation (feet)Direct TransmissionDirect Transmission*113.0MTE Nuclear Gauge No.:Compaction %FieldASTM D 6938Moisture Content %Dry Density (PCF)Backscatter / Direct Transmission11.010.8112.0107.4107.1110.1109.912.0LaboratoryMax Dry Density (PCF)12.6OMC %12.6126.6119.1118.7112.212.612.6*113.0*113.0*113.012.612.6*99.2*95.0*94.8*97.4*96.1*97.2*113.0*113.020225 Cedar Valley Road, Suite 110 Ph 425.742.9360 Lynnwood, WA 98036 Fax 425.745.1737 10029 S. Tacoma Way, Suite E-2 Ph 253.584.3720 Tacoma, WA 98499 Fax 253.584.3707 7911 NE 33rd Drive, Suite 190 Ph 503.281.7515 Portland, OR 97211 Fax 503.281.7579 MTE 1400-2C, Rev 2, 4/1/08
Page of*98.0*96.0*96.5*96.0*96.3*98.3*113.0*113.0*113.0*113.0*113.012.612.6123.0120.3123.2113.212.612.611.0LaboratoryMax Dry Density (PCF)12.6OMC %12.612.012.9110.7108.5109.1108.5111.1MTE Nuclear Gauge No.:Compaction %FieldASTM D 6938Moisture Content %Dry Density (PCF)Backscatter / Direct Transmission*97.0Wet Density (PCF)11.010.9Depth or Elevation (feet)Direct TransmissionDirect Transmission*113.020Tan Silty Sand with Trace OversizeTan Silty Sand with Trace Oversize56aAverage5a6Staging area next to driveway station 15+00AverageTest #44a-9 ft-9 ft-8 ft-8 ft-5 ft-5 ftIn our opinion, fill does not meet specifications as indicated by test numbers:Fill test meets compaction specificationsLocationIn our opinion, fill generally meets specifications as indicated by test numbers:Soil Type DescriptionTan Silty Sand with Trace OversizeTan Silty Sand with Trace OversizeTan Silty Sand with Trace OversizeAlong the 1.5:1 slope at station 13+00 50' east of the bottom Geogrid benchStaging area next to driveway station 15+00Thickness of lift:Contractor AdvisedFull-time observationMethod of Adding Moisture:firehose1 footComments: * See Density WorksheetType and Number of Compaction units:Number of Passes:1 hoepack 1 roller3to4Part-time observationDry Density: 12QC Sample:Test No.:Along the 1.5:1 slope at station 13+00 50' east of the bottom Geogrid benchAverageAlong the 1.5:1 slope at station 13+00 35' east of the bottom Geogrid benchAlong the 1.5:1 slope at station 13+00 35' east of the bottom Geogrid benchDirect TransmissionDirect Transmission14.213.613.8123.9126.4126.8Type and Number of earth moving units:2 excavators 2 dozersASTM D 698 (Standard Proctor)ASTM D 1557 (Modified Proctor)Specification Compaction and Material :95% -- T99Tan Silty Sand with Trace OversizeTan Silty Sand with Trace OversizeTan Silty Sand with Trace OversizeTan Silty Sand with Trace Oversize*100.2*99.322Date: 10/6/2009T09082WSDOT I405, I5 to SR169T. BergstromProject No.:Project:Inspector:3a 113.2 Moisture %:SoilFIELD DENSITY TEST REPORT12.9Direct TransmissionDirect Transmission20225 Cedar Valley Road, Suite 110 Ph 425.742.9360 Lynnwood, WA 98036 Fax 425.745.1737 10029 S. Tacoma Way, Suite E-2 Ph 253.584.3720 Tacoma, WA 98499 Fax 253.584.3707 7911 NE 33rd Drive, Suite 190 Ph 503.281.7515 Portland, OR 97211 Fax 503.281.7579 MTE 1400-2C, Rev 2, 4/1/08
Project #:Date: 10/6/2009
Project :20
Inspector: Test Method: WSDOT FOP for AASHTO T310
123
11+25-15+00 11+25-15+00 11+25-15+00
T09082-32 T09082-32 T09082-32
13+00 14+50 14+50
NA NA NA
Common Common Common
10 ft 12 ft 11 ft
0 degrees 112 107.1 109.9
90 degrees 107.4 110 112.2
average 109.7 108.6 111.1
0 degrees 13 10.8 12.3
90 degrees 10.9 9.8 11
average 12.0 10.3 11.7
10.06 10.18 10.48
000
10.06 10.18 10.48
0.22 0.14 0.27
000
0.22 0.14 0.27
213
97.81 98.62 97.42
113 113 113
97.1 96.1 98.3
12.6 12.6 12.6
12.6 12.6 12.6
12.6 12.6 12.6
Thomas B Robinson
(7) Optimum Moisture of Fine Material, passing #4 (from Maximum Density Curve Report)
(8) Optimum Moisture of Coarse Material, retained #4 (from Maximum Density Curve Report)
(5) % Retained on #4 Sieve (% Oversize) = Mass Retained / Mass of Sample
Mass of Sample (Dry or SSD) = (1) - (2)
(3) Mass of Retained on #4 Sieve + Tare
(4) Mass of Tare B
Mass of Material Retained on #4 Sieve = (3) - (4)
Gradation Determination
Moisture Content
Optimum Moisture Content Corrected = ((6 x 7) + (5 x 8)) / 100
(6) % Passing #4 Sieve = (100 - % Retained)
Density and Optimum Moisture Determination WSDOT T99
Percent Compaction (% of maximum) = (Dry Density / Corrected Maximum Density) x 100
Maximum Density (from Maximum Density Curve Table)
Soils Field Density Worksheet for WSDOT Projects (WSDOT SOP 615)
Moisture Density Curve #
Test Station
Station to Station
Worksheet used when Maximum Density is determined using WSDOT Method T99
T. Bergstrom
WSDOT I405, I5 to SR169 Stage 2 MTE Nuclear Gauge #:
T09082
Reviewed By:
Comments:
Test Hole Number
(1) Mass of Sample (Dry or SSD) + Tare
(2) Mass of Tare A
Average Moisture Content
Reference to Centerline
Average Dry Density lb/cu.ft.
Gauge Readings
Material Type
Depth of Material
Dry Density lbs/cu.ft.
Project #:Date: 10/6/2009
Project :20
Inspector: Test Method: WSDOT FOP for AASHTO T310
456
11+25-15+00 11+25-15+00 11+25-15+00
T09082-32 T09082-32 T09082-32
13+00 13+00 15+00
NA NA NA
Common Common Common
9 ft 8 ft 5 ft
0 degrees 110.7 109.1 111.1
90 degrees 108.5 108.5 113.2
average 109.6 108.8 112.2
0 degrees 11 12.9 13.8
90 degrees 10.9 14.2 12
average 11.0 13.6 12.9
11.15 10.49 10.57
000
11.15 10.49 10.57
0.28 0.3 0.25
000
0.28 0.30 0.25
332
97.49 97.14 97.63
113 113 113
97.0 96.3 99.2
12.6 12.6 12.6
12.6 12.6 12.6
12.6 12.6 12.6
Thomas B Robinson
Test Hole Number
(1) Mass of Sample (Dry or SSD) + Tare
(2) Mass of Tare A
Average Moisture Content
Reference to Centerline
Average Dry Density lb/cu.ft.
Gauge Readings
Material Type
Depth of Material
Dry Density lbs/cu.ft.
Reviewed By:
Comments:
Soils Field Density Worksheet for WSDOT Projects (WSDOT SOP 615)
Moisture Density Curve #
Test Station
Station to Station
Worksheet used when Maximum Density is determined using WSDOT Method T99
T. Bergstrom
WSDOT I405, I5 to SR169 Stage 2 MTE Nuclear Gauge #:
T09082
Optimum Moisture Content Corrected = ((6 x 7) + (5 x 8)) / 100
(6) % Passing #4 Sieve = (100 - % Retained)
Density and Optimum Moisture Determination WSDOT T99
Percent Compaction (% of maximum) = (Dry Density / Corrected Maximum Density) x 100
Maximum Density (from Maximum Density Curve Table)
(7) Optimum Moisture of Fine Material, passing #4 (from Maximum Density Curve Report)
(8) Optimum Moisture of Coarse Material, retained #4 (from Maximum Density Curve Report)
(5) % Retained on #4 Sieve (% Oversize) = Mass Retained / Mass of Sample
Mass of Sample (Dry or SSD) = (1) - (2)
(3) Mass of Retained on #4 Sieve + Tare
(4) Mass of Tare B
Mass of Material Retained on #4 Sieve = (3) - (4)
Gradation Determination
Moisture Content