Project Name Date Shift
Sheet 1 of 2 day
Weather
AM PM
Inspector IDR Report #
No. No.
1
3 Operators with CDB
2
1
1
1
1
1
1
Photos/Videos taken today?x Yes No File:
Inspector's Shift Hours
From:
To:Inspector's Signature
10.0 hrs
Reviewed By
Signs Barricades
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
cloudy ,hi 51 low 38
Traffic Control
Reviewed
Subcontractor Number & Classification
Plan SheetItem Quanity
IDR Sheet
Item Number Material / Item Description
CS 683E Cat Vibratory Roller
General Foreman with CDB
D5G Cat Dozer
313C Cat small excavator
HM 300 Komatsu offroad dump truck
partly cloudy, hi 56 low 51
Daniel Quehl 20091103 DQ
Laborer with CDB
Foreman with CDB
Bid Items Inspected Today/Field Note
Flaggers
EX270 Hitachi excavator
Location Structure#/Station
Acceptable
Date
6:30 AM
Date
4:30 PM
TR (11.4.09)
11/03/009
November 3, 2009
Daniel Quehl
Inspector's Daily Report
Project Number
Sheet 2 of 2
Inspector IDR Report #
20091103 DQ
November 3, 2009
DateIDR Sheet
Daniel Quehl
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
Inspector's Notes
Attended the CDB morning activity meeting.
Activities today at the Defoor site:
Performed observation for the placement of unsuitable materials being used for topsoil along the 2:1 slope from
stations 10+00 to10+50. This material was being transported from the on site stockpile located between stations
12+00 to13+00 next to Cedar road. There was a total of 500 cubic yards of this material placed today transported
from 20 truck loads.
Performed observation for the cut of compacted fill material for the ditchline running next to the access road from
stations 10+00 to 11+00, and the installation then of Geotextile unwoven filter fabric and quarry spalls along the
same locations. There was a total of 330 cubic yards of quarry spalls placed today transported by 15 truck loads
and 1 1/4 rolls of the Geotextile fabric.
Visited by Mazi Hadi the inspector with WSDOT and Ken Viren the MaterialsTechnician with WSDOT throughout
the day.
Visited by Robert Patcheck with CDB, Allan Brown with CDB,Ryan Andrews with CDB and Andy Anderson with
CDB to see the progress of the project.
Personal present at the Defoor site:
1. Dan Lonsdale-General Foreman with CDB
2. Jeremiah Perez-Foreman/Operator with CDB
3. Jay C-Operator with CDB
4. Allan Osborne-Operator with CDB
5. Dave Dover-Laborer with CDB
6. Jesus-Laborer with CDB
Equipment used at the Defoor site:
1. EX270 Hitachi Excavator
2. D5G Cat Dozer
3. 313C Cat small excavator
4. HM 300-2 Komatsu offroad dump truck
5. CS 683E Cat Vibratory Roller