I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
rain showers ,hi 51 low 47
Traffic Control
Reviewed
Subcontractor Number & Classification
Plan SheetItem Quanity
IDR Sheet
Item Number Material / Item Description
General Foreman with CDB General Foreman with Terra Dynamics
Foreman with Terra Dynamics
cloudy, hi 55 low 49
Daniel Quehl 20091109 DQ
Bid Items Inspected Today/Field Note
Flaggers
Location Structure#/Station
Acceptable
Date
6:30 AM
Date
1:30 PM
TR (11.10.09)
Laborers with Terra Dynamics
11/09/009
November 9, 2009
Daniel Quehl
Inspector's Daily Report
Project Number
Sheet 2 of 2
Inspector IDR Report #
20091109 DQ
November 9, 2009
DateIDR Sheet
Daniel Quehl
I-405/I-5 to SR169 Stage 2 - Widening
and SR515 Interchange Project
Inspector's Notes
Attended the CDB morning activity meeting.
Attended the WSDOT class for Substructures.
Performed observation for the placement of Type 2 Compost and wattles along the 2:1 slopes from stations 10+00
to 11+00 and stations 15+40 to 15+95 by Terra Dynamics. There was a total of 25 cubic yards placed today by 1
truck load.
Was visited by Ken Viren the Materials technician with WSDOT and Bob Pyle the inspector with WSDOT
throughout the day.
Personal present at Defoor site:
1. Todd Brandon-Foreman/Operator with Terra Dynamics
2. Herman Garrido-Laborer with Terra Dynamics
3. Manuel Garrido-Laborer with Terra Dynamics
4. Reginaldo Morales-Laborer with Terra Dynamics
Equipment present at Defoor site:
1. 312C Cat excavator
2. 270L Hitachi excavator(idle today)
3. D5G Cat Dozer(idle today)