HomeMy WebLinkAboutSR_HEX_Staff_Report_Exhibits_Talbot_Hill_Substation_Current_Limiting_Reactors_FINAL_190702DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Project Location Map
HEX Report
A. REPORT TO THE HEARING EXAMINER
Hearing Date: July 9, 2019
Project File Number: PR19-000212
Project Name: Talbot Hill Substation Current Limiting Reactors
Land Use File Number: LUA19-000097, CUP-H, SA, ECF, SF
Project Manager: Angelea Weihs, Associate Planner
Owner: Puget Sound Energy, Inc.; PO Box 97034, EST 4W, Bellevue, WA 98009-9734
Applicant/Contact: Kerry Kriner, Puget Sound Energy, PO Box 97034, EST 4W, Bellevue, WA 98009-
9734
Project Location: 2400 S Puget Drive
Project Summary: Puget Sound Energy (PSE) is requesting a Hearing Examiner Conditional Use Permit,
Site Plan Review, and a Special Fence Permit for proposed Talbot Hill Substation
improvements located at 2400 S Puget Dr. (parcel number 2023059066). The project
site totals 13.4 acres and is zoned Residential-8 (R-8). PSE is proposing to install six
Current Limiting Reactors (CLRs) within a fenced enclosure adjacent to the existing
Talbot Hill Substation. The proposed CLRs are large, highly customized coils that are
each supported by three insulators. For safety and security purposes, the CLRs will
also be installed on elevated pedestals with foundations, and enclosed by an eight
foot security fence. A new 190-foot long by 85-foot wide gravel pad will be
constructed to support the CLRs and the enclosure. The equipment will be accessed
by a new approximately 330-foot long by 15-foot wide gravel access road that will
connect to an existing gravel driveway which extends from Puget Dr. SE to the
substation entrance on PSE parcel number 2023059003. Stormwater from the new
impervious surface will be split between a new infiltration drywell and the existing
stormwater pond that serves the substation. No modifications to the existing
stormwater pond will occur. The proposal also includes the installation of a new
three-pole 230 kV H-frame (77 feet, 67 feet, and 77 feet above grade) outside the
fenced area to accommodate a reconfiguration of an existing transmission line
needed as part of the substation modernization. No tree or significant vegetation
removal is proposed as part of this project. The project site contains moderate
coalmine hazards, moderate landslide hazards, and sensitive slopes (within 50 feet).
The applicant has submitted a Technical Information Report (TIR) and Geotechnical
Engineering Study with the application.
Site Area: 13.4 acres
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 2 of 16
HEX Report
B. EXHIBITS:
Exhibits 1-7: As shown in the Environmental Review Committee (ERC) Report
Exhibit 8: Staff Report to the Hearing Examiner
Exhibit 9: Environmental Review Committee Determination of Non-Significance
Exhibit 10: Tree Removal and Landscape Plan, prepared by Thomas Luke Early, Licensed Landscape
Architect, dated December 13, 2016
Exhibit 11: Current Limiting Reactors Plans and Elevations
Exhibit 12: 230 kV H-frame Pole Elevations
Exhibit 13: Existing Fence Photos
C. GENERAL INFORMATION:
1. Owner(s) of Record: Puget Sound Energy, Inc.; PO Box 97034, EST 4W,
Bellevue, WA 98009-9734
2. Zoning Classification: Residential-8 (R-8)
3. Comprehensive Plan Land Use Designation: Residential Medium Density (MD)
4. Existing Site Use: Public Utility
5. Critical Areas: Moderate coalmine hazards, moderate landslide
hazards, and sensitive slopes
6. Neighborhood Characteristics:
a. North: Single family residential, R-8 zone
b. East: Public Utility, R-8 zone
c. South: Single family residential, R-8 zone
d. West: Public Utility, R-8 zone
7. Site Area: 13.4 acres
D. HISTORICAL/BACKGROUND:
Action Land Use File No. Ordinance No. Date
Comprehensive Plan N/A 5758 06/22/2015
Zoning N/A 5758 06/22/2015
Annexation N/A 1871 03/08/1961
Hearing Examiner
Conditional Use Permit,
Environmental Review, and
Site Plan Review
LUA16-000922 N/A 02/28/2017
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 3 of 16
HEX Report
E. PUBLIC SERVICES:
1. Existing Utilities
a. Water: No water service is proposed or required for the redevelopment project.
b. Sewer: No sewer service is proposed or required for the redevelopment project.
c. Surface/Storm Water: The site currently contains an existing substation and with a newly installed
on-site stormwater detention system. There are no existing drainage improvements along Beacon
Way S or Puget Drive SE.
2. Streets: The proposed development fronts Beacon Way South along the east property line. Beacon Way
South is classified as a Residential Access Road and is located within the City of Seattle Cedar River
Pipeline Easement.
3. Fire Protection: Renton Regional Fire Authority (RRFA)
F. APPLICABLE SECTIONS OF THE RENTON MUNICIPAL CODE:
1. Chapter 2 Land Use Districts
a. Section 4-2-020: Purpose and Intent of Zoning Districts
b. Section 4-2-060: Zoning Use Table – Uses Allowed in the Zoning Designations
c. Section 4-2-110: Residential Development Standards
2. Chapter 3 Environmental Regulations and Overlay Districts
a. Section 4-3-050: Critical Area Regulations
3. Chapter 4 City-Wide Property Development Standards
4. Chapter 6 Streets and Utility Standards
a. Section 4-6-060: Street Standards
5. Chapter 9 Permits – Specific
a. Section 4-9-030: Conditional Use Permits
b. Section 4-9-070: Environmental Review Procedures
c. Section 4-9-200: Master Plan and Site Plan Review
6. Chapter 11 Definitions
G. APPLICABLE SECTIONS OF THE COMPREHENSIVE PLAN:
1. Land Use Element
2. Utilities Element
H. FINDINGS OF FACT (FOF):
1. The Planning Division of the City of Renton accepted the above master application for review on May 2,
2019, and determined the application complete on May 15, 2019. The project complies with the 120-day
review period.
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 4 of 16
HEX Report
2. The project site is located at 2400 S Puget Drive.
3. The project site is currently developed with an existing 230-kV electrical substation.
4. Access to the site would be provided via a new approximately 330-foot long by 15-foot wide gravel access
road that will connect to an existing gravel driveway which extends from Puget Dr. SE to the substation
entrance on PSE parcel number 2023059003.
5. The property is located within the Residential Medium Density (MD) Comprehensive Plan land use
designation.
6. The site is located within the Residential-8 (R-8) zoning classification.
7. No tree or significant vegetation removal is proposed as part of this project.
8. The project site contains moderate coalmine hazards, moderate landslide hazards, and sensitive slopes.
9. Approximately 1,050 cubic yards of material would be cut on-site and approximately 1,200 cubic yards of
fill is proposed to be brought into the site.
10. The applicant is proposing to begin construction on August 26, 2019, and end construction on December
31, 2019.
11. No other public or agency comments were received.
12. Pursuant to the City of Renton's Environmental Ordinance and SEPA (RCW 43.21C, 1971 as amended), on
June 17, 2019, the Environmental Review Committee issued a Determination of Non-Significance (DNS)
for the Talbot Hill Substation Current Limiting Reactors (Exhibit 12). A 14-day appeal period commenced
on June 21, 2019, and ended on July 5, 2019. No appeals of the threshold determination have been filed
as of the date of this report.
13. Representatives from various city departments have reviewed the application materials to identify and
address issues raised by the proposed development. These comments are contained in the official file,
and the essence of the comments has been incorporated into the appropriate sections of this report and
the Departmental Recommendation at the end of this report.
14. Comprehensive Plan Compliance: The site is designated Residential Medium Density (MD) on the City’s
Comprehensive Plan Map. The purpose of the MD designation is to allow a variety of single-family and
multi-family development types, with continuity created through the application of design guidelines, the
organization of roadways, sidewalks, public spaces, and the placement of community gathering places
and civic amenities. The proposal is compliant with the following development standards if all conditions
of approval are met:
Compliance Comprehensive Plan Analysis
Policy L-29: Minimize erosion and sedimentation in and near sensitive areas by
requiring appropriate construction techniques and resource practices, such as low
impact development.
Policy L-30: Protect the integrity of natural drainage systems, existing land forms, and
maintain wildlife habitat values by preserving and enhancing existing vegetation and
tree canopy coverage to the maximum extent possible and by restoring hydrological
flows and improving the condition of shorelines.
Policy L-33: Emphasize the use of open ponding and detention, vegetated swales, rain
gardens, clean roof run-off, right-of-way landscape strips, open space, and stormwater
management techniques that mimic natural systems, maximize water quality and
infiltration where appropriate, and which will not endanger groundwater quality.
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 5 of 16
HEX Report
Policy L-37: Land uses in areas subject to flooding, seismic, geologic, and coal mine
hazards should be designed to prevent property damage and environmental
degradation before, during, and after construction.
Policy U-73: Encourage electricity purveyors to make facility improvements and
additions within existing utility corridors wherever possible.
Policy U-2: Protect the health and safety of Renton citizens from environmental
hazards associated with utility systems through the proper design and siting of utility
facilities.
Goal U-O: Promote the availability of safe, adequate, and efficient electrical service
within the City and its planning area, consistent with the regulatory obligation of the
utility to serve customers.
Goal L-BB: Maintain a high quality of life as Renton grows by ensuring that new
development is designed to be functional and attractive.
15. Zoning Development Standard Compliance: The site is classified Residential-8 (R-8) on the City’s Zoning
Map. Development in the R-8 zone is intended to create opportunities for new single family residential
neighborhoods and to facilitate high-quality infill development that promotes reinvestment in existing
single family neighborhoods. It is intended to accommodate uses that are compatible with and support a
high-quality residential environment and add to a sense of community. The proposed expansion of the
Public Utility use requires a Conditional Use Permit in order to be allowed in the R-8 zone. The proposal is
compliant with the following development standards if all conditions of approval are met:
Compliance R-8 Zone Develop Standards and Analysis
N/A
Density: The allowed density range in the R-8 zone is a minimum of 4.0 to a maximum
of 8.0 dwelling units per net acre. Net density is calculated after the deduction of
sensitive areas, areas intended for public right-of-way, and private access easements.
Staff Comment: Not applicable, no residential dwelling units are proposed.
N/A
Lot Dimensions: The minimum lot size permitted in the R-8 zone is 5,000 sq. ft. A
minimum lot width of 50 feet is required (60 feet for corner lots) and a minimum lot
depth of 80 feet is required.
Staff Comment: No applicable. No changes to the lot size, width, or depth are proposed.
Setbacks: The required setbacks in the R-8 zone are as follows: front yard is 20 feet,
side yard is 5 feet, side yard along the street 15 feet, and the rear yard is 20 feet.
Staff Comment: The subject property is triangular in shape. The proposed new Current
Limiting Reactor enclosure would maintain a setback of 218.40 feet from the south
property line, a 185.60-foot setback from the east property line, and an approximately
235-foot setback from the west property line. The proposed improvements would exceed
all the minimum required setback areas.
Building Standards: The R-8 zone has a maximum building coverage of 50%, a maximum
impervious surface coverage of 65%, and a maximum building height of 2 stories with a
wall plate height of 24 feet. Nonresidential accessory structures are restricted to a
maximum wall plate height of 12 feet. Roofs with a pitch equal to or greater than 4:12
may project an additional six (6) vertical feet from the maximum wall plate height.
Staff Comment: Plans and elevations for the new Current Limiting Reactors (CLRs)
(Exhibit 11) and for the new three-pole 230 kV H-frame (Exhibit 12) were submitted with
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 6 of 16
HEX Report
the project application. A new 190-foot long by 85-foot wide gravel pad will be
constructed to support the CLRs and the enclosure. The equipment will be accessed by a
new approximately 330-foot long by 15-foot wide gravel access road that will connect
to an existing gravel driveway which extends from Puget Dr. SE to the substation
entrance on PSE parcel number 2023059003.
There is approximately 151,942 square feet of existing impervious surface on site. The
applicant proposes approximately 29,439 square feet of new impervious surface, for a
total impervious surface of 181,381 square feet. The proposal would result in an
impervious surface coverage of approximately 31 percent. The proposed improvements
would comply with the impervious surface coverage requirements for the R-8 zone.
Landscaping: The City’s landscape regulations (RMC 4-4-070) require that all portions
of the development area not covered by structures, required parking, access, circulation
or service areas, be landscaped with native, drought-resistant vegetative cover. The
perimeter of all new flow control and/or water quality treatment stormwater facilities
shall be landscaped in accordance with the provisions of RMC 4-4-070 and the Surface
Water Design Manual. A landscaping strip with a minimum fifteen feet (15') of width
shall be located on the outside of the fence. Plantings shall be consistent with the
Surface Water Design Manual and RMC 4-4-070. Additionally, trees must be spaced as
determined by the Department of Community and Economic Development. Trees and
shrubs are prohibited on any berm serving a drainage-related function, within the
fenced area of the drainage facility, and within ten feet (10') of any manmade drainage
structure (e.g., catch basins, ditches, pipes, vaults, etc.); however, groundcover is
required and subject to City review and approval.
Staff Comment: The project site received Site Plan Review approval in February of 2017
under LUA16-000922 in order to deviate from storm drainage facility landscaping
standards for a new detention pond. A tree removal and landscape plan (Exhibit 10) was
reviewed and approved in compliance with conditions of approval for LUA16-000922.
The existing stormwater detention pond approved under this permit is located along the
southeastern edge of the existing substation. As an alternative to the required fifteen
feet of landscaping around the stormwater pond perimeter, the applicant proposed
landscape screening southwest of the stormwater pond, immediately south of the
existing access driveway, and to the west of the stormwater pond outside of the
perimeter fence. This screening currently serves to fill in gaps of existing natural
vegetation screening that occurs between the substance and the nearest residential
homes approximately 460 feet to the south. The landscaping replaced non-native plant
cover such as blackberry shrubs and non-native grasses.
The existing sight-obscuring landscaped visual buffer is 20 feet in width in the two
locations and contain a mixture of trees and large shrubs, some of which will mature to
35 feet tall. The visual buffer plantings included Vine Maple, Western Serviceberry,
Beaked Hazelnut, California Wax Myrtle, Silk Tassel and Strawberry Trees planted at 6
feet triangular on-center spacing.
In addition, existing tree canopy/vegetation screening is located between the substation
and residential uses to the south, which blocks views from the southeast and southwest
of the site. No additional trees or significant vegetation removal is proposed as part of
this project.
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 7 of 16
HEX Report
Tree Retention: The City’s adopted Tree Retention and Land Clearing Regulations
(RMC4-4-130) require the retention of 30 percent (30%) of trees in a residential
development.
Significant trees shall be retained in the following priority order:
Priority One: Landmark trees; significant trees that form a continuous canopy;
significant trees on slopes greater than twenty percent (20%); Significant trees adjacent
to critical areas and their associated buffers; and Significant trees over sixty feet (60') in
height or greater than eighteen inches (18") caliper.
Priority Two: Healthy tree groupings whose associated undergrowth can be preserved;
other significant native evergreen or deciduous trees; and Other significant non- native
trees.
Priority Three: Alders and cottonwoods shall be retained when all other trees have been
evaluated for retention and are not able to be retained, unless the alders and/ or
cottonwoods are used as part of an approved enhancement project within a critical area
or its buffer.
Staff Comment: Not applicable, no tree removal or significant vegetation removal is
proposed as part of this project.
Parking: Vehicle traffic to and from the existing substation use include routine
inspections and operations. The substation site provides ample on-site paved space to
accommodate parking for inspection/maintenance vehicles.
16. Design Standards: Residential Design and Open Space Standards (RMC 4-2-115) are applicable in the R-8
zone to new residential dwelling units. The proposal does not include any residential dwelling units;
therefore the residential design and open space standards are not applicable.
17. Critical Areas: Project sites which contain critical areas are required to comply with the Critical Areas
Regulations (RMC 4-3-050). The proposal is consistent with the Critical Areas Regulations:
Compliance Critical Areas Analysis
Geologically Hazardous Areas: Based upon the results of a geotechnical report and/or
independent review, conditions of approval for developments may include buffers
and/or setbacks from buffers. A standard 15-foot building setback is required for all
structures from Protected Slope areas.
A 50-foot buffer and 15-foot building setback are required from Very High Landslide
Hazard Areas.
Staff Comment: A geotechnical report (Exhibit 5), dated February 1, 2017, and an
addendum letter (Exhibit 6), dated January 29, 2019, completed by GeoEngineers, Inc.
was submitted with the application. The project site contains moderate coalmine
hazards, moderate landslide hazards and sensitive slopes. The report discusses the soil
and groundwater characteristics of the site including infiltration potential and
provides recommendations for project design and construction.
The site improvements for this project include approximately 0.42 acres of new
impervious surface, including a gravel pad for the CLRs and an access road. The total
acreage for this project is 0.56 acres of development. The cut will be approximately
1,050 cubic yards and the fill will be approximately 1,200 cubic yards. The proposed
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 8 of 16
HEX Report
expansion will be graded to the south to drain to the existing pond located to the south
of the expansion area.
The report and addendum state that the site is mapped in a moderate coal mine hazard
area; however, based on the depth of historical coal mining activity and the relatively
shallow depth of the proposed improvements, there is a low coal mine hazard at the
site. The addendum identifies that the site is mapped in a 25 to 40 percent steep slope
area and in a moderate landslide hazard area; however, the geotechnical engineer has
concluded that the proposed improvements would not adversely affect the stability of
the slopes in or around the site.
According to the report, the soils mapped in the project vicinity are predominantly
glacial till, but include localized areas of ice-contact glacial deposits overlying the till.
Based on the provided report and addendum, the soils underlying the CLR yard area
have a low risk of liquefying under the design earthquake event and a low risk of lateral
spread and earthquake-induced slope movement. The site is approximately 5 miles
south of the Seattle Fault Zone, which is thought to have a recurrence interval on the
order of 1,000 years. Based on the distance from the nearest mapped fault, there is a
low risk of fault rupture at the site.
Per the provided addendum, GeoEngineers recommend that the new access road
surfacing section consist of a minimum of three inches of crushed surfacing top course
overlying nine inches of crushed surfacing base course, which is the same road surfacing
section used for the existing access road, which this access will extend from.
Furthermore, GoeEngineers recommend that the road section be compacted to a firm
and unyielding condition using smooth drum vibratory compaction equipment.
The geotechnical report includes specific recommendations for: site preparation,
shallow and mat foundations, drilled shafts, retaining walls, earthwork, temporary
slopes, erosion and sedimentation control, and the stormwater pond for the substation
expansion project reviewed and approved in 2017 under file number LUA16-000922.
The addendum letter recommends that the earthquake engineering, foundation design,
and earthwork recommendations previously presented in the geotechnical report be
used for design of the proposed Current Limiting Reactors (CLRs) improvements.
18. Conditional Use Analysis: Puget Sound Energy is requesting a Hearing Examiner Conditional Use Permit,
Site Plan Review, and a Special Fence Permit for proposed Talbot Hill Substation improvements.
Improvements include the installation of six Current Limiting Reactors (CLRs) within a new fenced
enclosure, a new (190' long by 85' wide) gravel pad to support the CLRs and the enclosure, the installation
of a new three-pole 230 kV H-frame, and a new gravel access road. The proposal is compliant with the
following conditional use criteria, pursuant to RMC 4-9-030.D. Therefore, staff recommends approval of
the requested Conditional Use Permit.
Compliance Conditional Use Criteria and Analysis
a. Consistency with Plans and Regulations: The proposed use shall be compatible
with the general goals, objectives, policies and standards of the Comprehensive
Plan, the zoning regulations and any other plans, programs, maps or ordinances of
the City of Renton.
Staff Comment: See FOF 14 for Comprehensive Plan and zoning regulation compliance.
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 9 of 16
HEX Report
b. Appropriate Location: The proposed location shall not result in the detrimental
overconcentration of a particular use within the City or within the immediate area
of the proposed use. The proposed location shall be suited for the proposed use.
Staff Comment: The proposed location of the substation improvements will not result
in detrimental overconcentration of a particular use within the City or within the
immediate area. The Current Limiting Reactors (CLRs) will be located adjacent to the
existing Talbot Hills Substation. The applicant states that this location is necessary due
to the function of the CLRs to support the Puget Sound Energy and Bonneville Power
Administration transmission lines within the utility corridor. No other use besides utility
infrastructure is proposed to be located on the project site.
c. Effect on Adjacent Properties: The proposed use at the proposed location shall not
result in substantial or undue adverse effects on adjacent property.
Staff Comment: The proposed use at the proposed location will not result in substantial
or undue adverse effects on adjacent property. The adjacent property includes an
existing regional utility corridor with electric infrastructure and other underground
utilities operated by various providers. The property downhill to the south of the site is
also owned by Puget Sound Energy and contains transmission lines, significant trees,
and recreational facilities. This parcel serves as a buffer to the residential community
to the south. The substation is over 460 feet from the nearest residential lot. The Current
Limiting Reactors will be situated on the site adjacent to the existing substation north
of the existing access driveway and behind a group of significant trees.
d. Compatibility: The proposed use shall be compatible with the scale and character
of the neighborhood.
Staff Comment: Talbot Substation is an existing substation that was constructed in the
early 1960’s. The proposal includes the installation of six Current Limiting Reactors
(CLRs) within a new fenced enclosure, a new (190' long by 85' wide) gravel pad to
support the CLRs and the enclosure, the installation of a new three-pole 230 kV H-frame,
and a new gravel access road. The maximum overall height of the new proposed CLRs
is 23 feet and 10.25 inches. The maximum overall height of the new three-pole 230kV
H-Frame is 77 feet. The substation is over 460 feet from the nearest residential lot and
completely surrounded by transmission corridors. The proposal includes existing
vegetation screening, which will restrict views of the substation and proposed
improvements to the surrounding neighborhood. The proposed improvements are part
of the same use that has been on the site for more than 50 years. The proposed use is
compatible with the scale and character of the neighborhood.
e. Parking: Adequate parking is, or will be made, available.
Staff Comment: See parking discussion under FOF 15, Zoning Development Standard
Compliance: Parking.
f. Traffic: The use shall ensure safe movement for vehicles and pedestrians and shall
mitigate potential effects on the surrounding area.
Staff Comment: The Talbot Hill substation property is accessed via an existing access
driveway extending from Puget Drive SE (See Exhibit 2). As part of the project, the
applicant is proposing a new approximately 330-foot long by 15-foot wide gravel access
road that will connect to this existing driveway. The project would not generate a
significant number of vehicle trips during construction or operation. Daily trips during
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 10 of 16
HEX Report
construction will likely include delivery of materials and commuting of the construction
crew. No additional trips would be required during operation of the substation, except
for routine inspections and operation. The proposed improvements will not result in
increased traffic to and from the substation site. Impacts to the surrounding area are
not anticipated.
g. Noise, Light and Glare: Potential noise, light and glare impacts from the proposed
use shall be evaluated and mitigated.
Staff Comment: The applicant states that noise from the Current Limiting Reactors will
not exceed existing site noise levels and will be within the regulated noise thresholds.
As stated above, the substation is over 460 feet from the nearest residential lot and
completely surrounded by transmission corridors. Therefore, any noise generated by the
substation and proposed improvements is anticipated to be absorbed by the
surrounding corridors. Light, glare or noise volumes would not result in an impact to the
surrounding neighborhood.
h. Landscaping: Landscaping shall be provided in all areas not occupied by buildings,
paving, or critical areas. Additional landscaping may be required to buffer adjacent
properties from potentially adverse effects of the proposed use.
Staff Comment: See discussion under FOF 15, Zoning Development Standard:
Landscaping.
19. Site Plan Review: The project site received Site Plan Review approval in February of 2017 under LUA16-
000922 in order to deviate from storm drainage facility landscaping standards. Pursuant to RMC 4-9-200.H,
major modifications to an approved master plan or site plan require a new application. For Master Plan
applications compliance with the review criteria for Site Plans are analyzed at a general level of detail to
ensure nothing would preclude the development of the Site Plan. Given Site Plan applications are evaluated
for compliance with the specific requirements of the RMC 4-9-200.E.3 the following table contains project
elements intended to comply with level of detail needed for Site Plan requests:
Compliance Site Plan Criteria and Analysis
Compliant if
conditions of
approval are
met
a. Comprehensive Plan Compliance and Consistency.
Staff Comment: See previous discussion under FOF 14, Comprehensive Plan Analysis.
b. Zoning Compliance and Consistency.
Staff Comment: See discussion under FOF 15, Zoning Development Standard
Compliance.
N/A
c. Design Regulation Compliance and Consistency.
Staff Comment: Not applicable. See discussion under FOF 16, Design Standards.
N/A d. Planned action ordinance and Development agreement Compliance and
Consistency.
Compliant if
condition of
approval is
met
e. Off-site Impacts.
Structures: Restricting overscale structures and overconcentration of development
on a particular portion of the site.
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 11 of 16
HEX Report
Staff Comment: See scale and overconcentration discussion under FOF 18, Conditional
Use Analysis: Appropriate Location.
Circulation: Providing desirable transitions and linkages between uses, streets,
walkways and adjacent properties.
Staff Comment: The existing access driveway extending from Puget Drive SE would
provide the required circulation between the development and the adjacent properties.
Utilities, Loading and Storage Areas: Locating, designing and screening storage
areas, utilities, rooftop equipment, loading areas, and refuse and recyclables to
minimize views from surrounding properties. Locate utilities underground
consistent with RMC 4-6-090.
Staff Comment: The overall development (public utility) would be screened via the
existing trees and landscaping identified in FOF 15, Zoning Development Standard:
Landscaping. No loading areas or refuse and recyclable areas are proposed for the site.
Views: Recognizing the public benefit and desirability of maintaining visual
accessibility to attractive natural features.
Staff Comment: The landscape of the areas is relatively flat with large trees and heavy
vegetation restricting visibility from the site. The nearest residential uses are more than
460 feet from the substation. Therefore, the proposed height of the
structure/improvements are appropriate for this situation.
Landscaping: Using landscaping to provide transitions between development and
surrounding properties to reduce noise and glare, maintain privacy, and generally
enhance the appearance of the project.
Staff Comment: See discussion under FOF 15, Zoning Development Standard:
Landscaping.
Lighting: Designing and/or placing exterior lighting and glazing in order to avoid
excessive brightness or glare to adjacent properties and streets.
Staff Comment: The application materials do not indicate a proposal for lighting for the
Current Limiting Reactors and fence enclosure, nor was a lighting plan provided with
the application; therefore, staff recommends as a condition of approval that if lighting
is proposed, a lighting plan shall be provided at the time of building permit review that
demonstrates compliance with RMC 4-4-075.
f. On-site Impacts.
Structure Placement: Provisions for privacy and noise reduction by building
placement, spacing and orientation.
Staff Comment: See compatibility discussion under FOF 18, Conditional Use Analysis:
Compatibility, and Noise discussion under FOF 18, Conditional Use Analysis: Noise,
Light, and Glare.
Structure Scale: Consideration of the scale of proposed structures in relation to
natural characteristics, views and vistas, site amenities, sunlight, prevailing winds,
and pedestrian and vehicle needs.
Staff Comment: The proposed new Current Limiting Reactors have a maximum height
of 23 feet and 10.25 inches. The maximum overall height of the new three-pole 230kV
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 12 of 16
HEX Report
H-Frame is 77 feet. The nearest residential uses are more than 460 feet from the
substation, with existing vegetation restricting visibility from the site. The proposed
control house will not result in substantial or undue adverse effects on adjacent
property.
Natural Features: Protection of the natural landscape by retaining existing
vegetation and soils, using topography to reduce undue cutting and filling, and
limiting impervious surfaces.
Staff Comment: See discussions under FOF 15, Zoning Development Standard: Tree
Retention and Building Standards.
Reducing Parking Impervious Areas: Design parking areas to minimize impervious
surfaces, including but not limited to: (1) breaking up parking areas and directing
stormwater flows to multiple low impact development features such as
bioretention areas; (2) locating parking near trees to provide stormwater uptake;
(3) retaining or adding vegetation to parking areas; (4) placing existing parking that
exceeds maximum parking ratios in permeable pavement designed consistent with
the Surface Water Design Manual in RMC 4-6-030; and (5) using other low impact
development techniques consistent with RMC 4-6-030
Staff Comment: Not applicable. No parking lot is proposed with this project. Visitors to
the site will be limited to routine maintenance for the proposed equipment.
Landscaping: Use of landscaping to soften the appearance of parking areas, to
provide shade and privacy where needed, to define and enhance open spaces, and
generally to enhance the appearance of the project. Landscaping also includes the
design and protection of planting areas so that they are less susceptible to damage
from vehicles or pedestrian movements.
Staff Comment: See FOF 15, Zoning Development Standard: Landscaping.
g. Access and Circulation.
Location and Consolidation: Providing access points on side streets or frontage
streets rather than directly onto arterial streets and consolidation of ingress and
egress points on the site and, when feasible, with adjacent properties.
Staff Comment: The equipment will be accessed by a new approximately 330-foot long
by 15-foot wide gravel access road that will connect to an existing gravel driveway
which extends from Puget Dr. SE to the substation entrance on PSE parcel number
2023059003. No new ingress and egress points are proposed on the public street.
Internal Circulation: Promoting safety and efficiency of the internal circulation
system, including the location, design and dimensions of vehicular and pedestrian
access points, drives, parking, turnarounds, walkways, bikeways, and emergency
access ways.
Staff Comment: See the location and consolidation discussion under FOF 19, Site Plan
Review. The proposed improvements are adequate to promote safety and efficiency of
the international circulation system.
Loading and Delivery: Separating loading and delivery areas from parking and
pedestrian areas.
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 13 of 16
HEX Report
Staff Comment: Not applicable. No loading and delivery areas are proposed.
Transit and Bicycles: Providing transit, carpools and bicycle facilities and access.
Staff Comment: Per RMC 4-4-080F.11, the proposal is exempt from bicycle parking
requirements.
Pedestrians: Providing safe and attractive pedestrian connections between parking
areas, buildings, public sidewalks and adjacent properties.
Staff Comment: The proposed use will not increase pedestrian traffic on or near the site.
Access to the site is provided via an existing access driveway extending through parcel
number 2023059064 to the south from Puget Drive Southeast. Puget Drive Southeast is
classified as a Minor Arterial Street. A new approximately 330-foot long by 15-foot wide
gravel access road will connect the proposed equipment to the existing driveway. See
FOF 19, Site Plan Review: Transportation, for more details.
h. Open Space: Incorporating open spaces to serve as distinctive project focal points
and to provide adequate areas for passive and active recreation by the
occupants/users of the site.
Staff Comment: See FOF 16, Design Standards. The project is exempt from open space
requirements.
i. Views and Public Access: When possible, providing view corridors to shorelines and
Mt. Rainier, and incorporating public access to shorelines
Staff Comment: The proposed improvements would not block view corridors to
shorelines or Mt. Rainier. The public access requirement is not applicable to the
proposal.
j. Natural Systems: Arranging project elements to protect existing natural systems
where applicable.
Staff Comment: The project site contains moderate coalmine hazards, moderate
landslide hazards, and sensitive slopes. No other critical areas are located on the
project site. No tree removal or significant vegetation removal is proposed.
Complaint
Provided
Condition of
Approval is
Met
k. Services and Infrastructure: Making available public services and facilities to
accommodate the proposed use:
Police and Fire.
Staff Comment: Police and Renton Fire Authority staff indicates that sufficient resources
exist to furnish services to the proposed development. No fire impact fees are applicable
for this project.
Water and Sewer.
Staff Comment: No sewer or water service is proposed or required for the
redevelopment project.
Drainage.
Staff Comment: A Technical Information Report (TIR) (Exhibit 3), dated March, 2019,
was submitted by Power Engineers with the Land Use Application. Based on the City of
Renton’s flow control map, the site falls within the Flow Control Duration Standard area
matching Forested Site Conditions and is within the Black River Drainage Basin. The
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 14 of 16
HEX Report
development is subject to Full Drainage Review in accordance with the 2017 City of
Renton Surface Water Design Manual. All core requirements and the six special
requirements are discussed in the Technical Information Report.
The report states that the existing substation and access road to the south convey runoff
to the existing detention pond on site. The pond was designed in 2016 for adherence to
the City of Renton’s Area-Specific Flow Control Facility. The existing substation runoff is
captured in catch basins and conveyed to the existing detention pond which sits
immediately south of the existing substation. Surface runoff from the areas peripheral
to the existing substation also drain southward. The site for the expansion area also
drains primarily to the south and south west.
The proposed improvements would be graded to the south to drain to the existing pond
located to the south of the expansion area. The control structure in the existing pond
would be modified to control the additional impervious flow from the proposed pad.
The new access road would be constructed at existing grade to maintain existing
drainage patterns to the extent possible.
The report states that existing pond has adequate capacity to receive the discharge
from converted surfaces. Following attenuation in the existing pond, stormwater will
discharge to the natural location southwest of the site.
Based on the proposal, the expansion project would not contribute any new Pollution
Generating Impervious Surface (PGIS) or Pollution Generating Pervious Surface (PGPS)
since the proposed land cover does not meet the definition of a pollution generating
surface. As a result, the report states that the project qualifies for the Surface Area
Exemption from the requirement to provide a water quality facility.
A geotechnical report (Exhibit 5), dated February 1, 2017, and an addendum letter
(Exhibit 6), dated January 29, 2019, completed by GeoEngineers, Inc. was submitted
with the application. The Geotechnical report notes that infiltration is possible within
the site; therefore, staff recommends as a condition of approval that the applicant
submit a revised geotechnical report at the time of civil construction permit application
that evaluates infiltration to its maximum extent feasible.
Transportation.
Staff Comment: Access to the site is proposed via a new approximately 330-foot long
by 15-foot wide gravel access road that will connect to an existing gravel driveway
which extends from Puget Dr. SE to the substation entrance on PSE parcel number
2023059003. Increased traffic created by the development would be mitigated by
payment of transportation impact fees. Currently this fee is assessed at $6.84 per
square foot. This fee increases each year and the applicable fee is paid at the time of
building permit issuance.
N/A l. Phasing: The applicant is not requesting any additional phasing.
m. Stormwater: Providing optimal locations of stormwater infiltrating low impact
development facilities. Avoiding placement of buildings or impervious areas on
soils with infiltration capability to the maximum extent practicable.
Staff Comment: See discussions under FOF 19, Site Plan Review: Drainage.
20. Special Fence Permit Analysis: The applicant is requesting a Special Fence Permit, per RMC 4-4-040, in
order to build an 8-foot tall chain link fence around the proposed Current Limiting Reactors. The proposal
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 15 of 16
HEX Report
is compliant with the following Special Fence Permit criteria, pursuant to RMC 4-4-040G.2, if all conditions
of approval are met. Therefore, staff is recommending approval of the requested Special Fence Permit.
Compliance Special Fence Permit Criteria and Analysis
a. The proposed fence improves the privacy and security of the adjoining yard space.
Staff Comment: The applicant asserts that the strict application of the fencing height
regulations for the proposed electrical utility infrastructure is not practical or safe. The
existing substation facility on the site is surrounded by an 8-foot high barbed chain link
fence (See Exhibit 13), which meets Puget Sound Energy (PSE) safety and security
standards. The Bonneville Power Administration’s (BPA) substation to the east across
Beacon Way South has similar fencing for safety and security purposes. The applicant
states that, to not allow an 8-foot high fence around the Current Limiting Reactors
(CLRs) would be inconsistent with existing utility facilities within the zoning district and
would deprive PSE from the ability to safely and securely operate the CLRs.
b. The proposed fence does not detract from the quality of the residential
environment by being out of scale or creating vast blank walls along public
roadways.
Staff Comment: The substation is over 460 feet from the nearest residential lot to the
south. The proposed fence does not detract from the quality of the residential
environment. Allowing an 8-foot high fence is consistent with existing utility
infrastructure fencing on the site and within the adjacent utility corridor properties. The
fenced enclosure will be set back on the property, uphill from residential development
in the vicinity, but not directly adjacent to the site. The adjacent property includes an
existing regional utility corridor with electric infrastructure and other underground
utilities operated by various providers. The property downhill to the south of the site is
also owned by Puget Sound Energy and contains transmission lines, significant trees,
and recreational facilities. This parcel serves as a buffer to the residential community
to the south.
c. The proposed fence compliments the environment it serves in an aesthetically
pleasing manner.
Staff Comment: The 8-foot high chain-link fence is consistent with existing utility
infrastructure fencing on the site and in the vicinity and meets safety and security
standards.
d. The proposed fence does not present a hazard to vehicular or pedestrian traffic.
Staff Comment: The project site does not abut a public street. The nearest private street
is more than 185.6 feet away from the proposed fence enclosure.
21. Availability and Impact on Public Services:
Compliance Availability and Impact on Public Services Analysis
Police and Fire: See FOF 19, Site Plan Review: Police and Fire.
Parks: No park impact fees are applicable for this project.
Storm Water: An adequate drainage system shall be provided for the proper drainage
of all surface water.
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Hearing Examiner
LUA19-000097, CUP-H, SA, ECF, SF
Report of July 9, 2019 Page 16 of 16
HEX Report
Staff Comment: See FOF 19, Site Plan Review: Drainage.
Water: No water service is proposed or required for the redevelopment project.
Sanitary Sewer: No sewer service is proposed or required for the redevelopment
project.
I. CONCLUSIONS:
1. The subject site is located in the Residential Medium Density (MD) Comprehensive Plan designation and
complies with the goals and policies established with this designation, see FOF 14.
2. The subject site is located in the Residential-8 (R-8) zoning designation and complies with the zoning and
development standards established with this designation provided the applicant complies with City Code
and conditions of approval, see FOF 15.
3. The proposed Error! Reference source not found. complies with the Critical Areas Regulations provided
the applicant complies with City Code, see FOF 17.
4. The proposed substation improvements comply with the Conditional Use Permit criteria as established by
City Code and state law provided all advisory notes and conditions are complied with, see FOF 18.
5. The proposed substation improvements comply with the Site Plan Review criteria as established by City
Code and state law provided all advisory notes and conditions are complied with, see FOF 19.
6. The proposed fence enclosure complies with the Special Fence Permit criteria as established by City Code
and state law provided all advisory notes and conditions are complied with, see FOF 20.
7. There are adequate public services and facilities to accommodate the proposed Error! Reference source
not found., see FOF 21.
J. RECOMMENDATION:
Staff recommends approval of the Talbot Hill Substation Current Limiting Reactors Conditional Use Permit, File
No. LUA19-000097, CUP-H, SA, ECF, SF, as depicted in the Site Plan (Exhibit 2), subject to the following
conditions:
1. The applicant shall submit a revised geotechnical report at the time of civil construction permit application
that evaluates infiltration to its maximum extent feasible.
2. If lighting is proposed, a lighting plan shall be provided at the time of building permit review that
demonstrates compliance with RMC 4-4-075.
CITY OF RENTON
DEPARTMENT OF COMMUNITY AND ECONOMIC DEVELOPMENT
STAFF REPORT TO THE HEARING EXAMINER
EXHIBITS
Project Name:
Talbot Hill Substation Current Limiting
Reactors
Land Use File Number:
LUA19-000097, CUP-H, SA, ECF, SF
Date of Hearing
July 9, 2019
Staff Contact
Angelea Weihs
Associate Planner
Project Contact/Applicant
Kerry Kriner
Puget Sound Energy
PO Box 97034, EST 4W,
Bellevue, WA 98009-9734
Project Location
2400 S Puget Drive
The following exhibits are included with the Staff Report to the Hearing Examiner:
Exhibits 1-7: As shown in the Environmental Review Committee (ERC) Report
Exhibit 8: Staff Report to the Hearing Examiner
Exhibit 9: Environmental Review Committee Determination of Non-Significance
Exhibit 10: Tree Removal and Landscape Plan, prepared by Thomas Luke Early, Licensed Landscape
Architect, dated December 13, 2016
Exhibit 11: Current Limiting Reactors Plans and Elevations
Exhibit 12: 230 kV H-frame Pole Elevations
Exhibit 13: Existing Fence Photos
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Project Location Map
SR_ERC_Report_Talbot_Hill_Substation_190614_FINAL
ENVIRONMENTAL REVIEW COMMITTEE REPORT
ERC Meeting Date: June 17, 2019
Project File Number: PR19-000212
Project Name: Talbot Hill Substation Current Limiting Reactors
Land Use File Number: LUA19-000097, CUP-H, SA, ECF, SF
Project Manager: Angelea Weihs, Associate Planner
Owner: Puget Sound Energy, Inc.; PO Box 97034, EST 4W, Bellevue, WA 98009-9734
Applicant/Contact: Kerry Kriner, Puget Sound Energy, PO Box 97034, EST 4W, Bellevue, WA 98009-
9734
Project Location: 2400 S Puget Drive
Project Summary: Puget Sound Energy (PSE) is requesting a Hearing Examiner Conditional Use
Permit, Environmental (SEPA) Review, Site Plan Review, and a Special Fence
Permit for proposed Talbot Hill Substation improvements located at 2400 S Puget
Drive (parcel number 2023059066). The project site totals 13.4 acres and is zoned
Residential-8 (R-8). PSE is proposing to install six Current Limiting Reactors (CLRs)
within a fenced enclosure adjacent to the existing Talbot Hill Substation. The
proposed CLRs will be installed on elevated pedestals with foundations, and
enclosed by an eight foot security fence. A new 190 foot long by 85 foot wide
gravel pad will be constructed to support the CLRs and the enclosure. The
equipment will be accessed by a new approximately 330 foot long by 15 foot wide
gravel access road that will connect to an existing gravel driveway which extends
from Puget Dr. SE. The proposal also includes the installation of a new three-pole
230 kV H-frame (77 feet, 67 feet, and 77 feet above grade) outside the fenced
area. No tree or significant vegetation removal is proposed as part of this project.
The project site contains moderate coalmine hazards, moderate landslide
hazards, and sensitive slopes (within 50 feet). The applicant submitted a Technical
Information Report (TIR) and Geotechnical Engineering Study with the
application.
Exist. Bldg. Area SF: NA Proposed New Bldg. Area (footprint):
Proposed New Bldg. Area (gross):
NA
NA
Site Area: 50.4 acres Total Building Area GSF: NA
STAFF
RECOMMENDATION:
Staff Recommends that the Environmental Review Committee issue a
Determination of Non-Significance (DNS).
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Environmental Review Committee
LUA19-000097, CUP-H, SA, ECF, SF
Report of June 17, 2019 Page 2 of 5
SR_ERC_Report_Talbot_Hill_Substation_190614_FINAL ERC Report_LUA 19-000097_Talbot Hill Substation
PART ONE: PROJECT DESCRIPTION / BACKGROUND
Puget Sound Energy (PSE) is requesting a Hearing Examiner Conditional Use Permit, Environmental (SEPA) Review, Site
Plan Review, and a Special Fence Permit for proposed Talbot Hill Substation improvements located at 2400 S Puget Dr
(parcel number 2023059066). The project site totals 13.4 acres and is zoned Residential-8 (R-8). PSE is proposing to
install six Current Limiting Reactors (CLRs) within a fenced enclosure adjacent to the existing Talbot Hill Substation.
The proposed CLRs are large, highly customized coils that are each supported by three insulators. For safety and
security purposes, the CLRs will also be installed on elevated pedestals with foundations, and enclosed by an eight
foot security fence. A new 190 foot long by 85 foot wide gravel pad will be constructed to support the CLRs and the
enclosure. The equipment will be accessed by a new approximately 330 foot long by 15 foot wide gravel access road
that will connect to an existing gravel driveway which extends from Puget Dr. SE to the substation entrance on PSE
parcel number 2023059003. Stormwater from the new impervious surface will be split between a new infiltration
drywell and the existing stormwater pond that serves the substation. No modifications to the existing stormwater
pond will occur.
The proposal also includes the installation of a new three-pole 230 kV H-frame (77 feet, 67 feet, and 77 feet above
grade) outside the fenced area to accommodate a reconfiguration of an existing transmission line needed as part of
the substation modernization. No tree or significant vegetation removal is proposed as part of this project. The project
site contains moderate coalmine hazards, moderate landslide hazards, and sensitive slopes (within 50 feet). The
applicant has submitted a Technical Information Report (TIR) and Geotechnical Engineering Study with the application.
PART TWO: ENVIRONMENTAL REVIEW
In compliance with RCW 43.21C.240, the following environmental (SEPA) review addresses only those project impacts
that are not adequately addressed under existing development standards and environmental regulations.
A. Environmental Threshold Recommendation
Based on analysis of probable impacts from the proposal, staff recommends that the Responsible Officials:
Issue a DNS with a 14-day Appeal Period.
B. Exhibits
Exhibit 1: Environmental Review Committee (ERC) Report
Exhibit 2: Site Plan
Exhibit 3: Drainage Report, prepared by Power Engineers, dated March 2019
Exhibit 4: Drainage Control Plan, prepared by Power Engineers, dated April 1, 2019
Exhibit 5: Geotechnical Report, prepared by GeoEngineers, dated February 1, 2017
Exhibit 6: Geotechnical Report Addendum Letter, prepared by GeoEngineers, dated January 29,
2019
Exhibit 7: Advisory Notes
C. Environmental Impacts
The Proposal was circulated and reviewed by various City Departments and Divisions to determine whether the
applicant has adequately identified and addressed environmental impacts anticipated to occur in conjunction with
the proposed development. Staff reviewers have identified that the proposal is likely to have the following probable
impacts:
1. Earth
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Environmental Review Committee
LUA19-000097, CUP-H, SA, ECF, SF
Report of June 17, 2019 Page 3 of 5
SR_ERC_Report_Talbot_Hill_Substation_190614_FINAL ERC Report_LUA 19-000097_Talbot Hill Substation
Impacts: A geotechnical report (Exhibit 5), dated February 1, 2017, and an addendum letter (Exhibit 6),
dated January 29, 2019, completed by GeoEngineers, Inc. was submitted with the application. The project
site contains moderate coalmine hazards, moderate landslide hazards and sensitive slopes. The report
discusses the soil and groundwater characteristics of the site including infiltration potential and provides
recommendations for project design and construction.
The site improvements for this project include approximately 0.42 acres of new impervious surface,
including a gravel pad for the CLRs and an access road. The total acreage for this project is 0.56 acres of
development. The cut will be approximately 1,050 cubic yards and the fill will be approximately 1,200
cubic yards. The proposed expansion will be graded to the south to drain to the existing pond located to
the south of the expansion area.
The report and addendum state that the site is mapped in a moderate coal mine hazard area; however,
based on the depth of historical coal mining activity and the relatively shallow depth of the proposed
improvements, there is a low coal mine hazard at the site. The addendum identifies that the site is mapped
in a 25 to 40 percent steep slope area and in a moderate landslide hazard area; however, the geotechnical
engineer has concluded that the proposed improvements would not adversely affect the stability of the
slopes in or around the site.
According to the report, the soils mapped in the project vicinity are predominantly glacial till, but include
localized areas of ice-contact glacial deposits overlying the till. Based on the provided report and
addendum, the soils underlying the CLR yard area have a low risk of liquefying under the design
earthquake event and a low risk of lateral spread and earthquake-induced slope movement. The site is
approximately 5 miles south of the Seattle Fault Zone, which is thought to have a recurrence interval on
the order of 1,000 years. Based on the distance from the nearest mapped fault, there is a low risk of fault
rupture at the site.
GeoEngineers state in the provided addendum that the proposed stormwater improvements will be
designed in accordance with the 2017 City of Renton Surface Water Design Manual. In accordance with
the requirements of Chapter 5.2 of the Manual, GeoEngineers evaluated the site for infiltration potential.
Due to the presence of shallow, medium dense to very dense glacial till, GeoEngineers state that
infiltration is not feasible on site.
Per the provided addendum, GeoEngineers recommend that the new access road surfacing section consist
of a minimum of three inches of crushed surfacing top course overlying nine inches of crushed surfacing
base course, which is the same road surfacing section used for the existing access road, which this access
will extend from. Furthermore, GoeEngineers recommend that the road section be compacted to a firm
and unyielding condition using smooth drum vibratory compaction equipment.
The geotechnical report includes specific recommendations for: site preparation, shallow and mat
foundations, drilled shafts, retaining walls, earthwork, temporary slopes, erosion and sedimentation
control, and the stormwater pond for the substation expansion project reviewed and approved in 2017
under file number LUA16-000922. The addendum letter recommends that the earthquake engineering,
foundation design, and earthwork recommendations previously presented in the geotechnical report be
used for design of the proposed Current Limiting Reactors (CLRs) improvements. It is anticipated that the
City’s currently adopted erosion control, construction, building codes and drainage regulations would
adequately mitigate for any impacts that could result from the proposed improvements; therefore, no
further mitigation is recommended.
Mitigation Measures: No further mitigation recommended.
Nexus: N/A
2. Air
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Environmental Review Committee
LUA19-000097, CUP-H, SA, ECF, SF
Report of June 17, 2019 Page 4 of 5
SR_ERC_Report_Talbot_Hill_Substation_190614_FINAL ERC Report_LUA 19-000097_Talbot Hill Substation
Impacts: It is anticipated that some temporary air quality impacts could be associated with site work and
building construction required to develop this site. Project development impacts during construction may
include dust, resulting from grading and exhaust from construction vehicles. Dust control would be
mitigated through the use of watering of the site as needed.
No further site specific mitigation for the identified impacts from typical vehicle and construction exhaust
is required.
Mitigation Measures: No further mitigation recommended.
Nexus: N/A
3. Water
a. Storm Water
Impacts: A Technical Information Report (TIR) (Exhibit 3), dated March, 2019, was submitted by Power
Engineers with the Land Use Application. Based on the City of Renton’s flow control map, the site falls
within the Flow Control Duration Standard area matching Forested Site Conditions and is within the
Black River Drainage Basin. The development is subject to Full Drainage Review in accordance with
the 2017 City of Renton Surface Water Design Manual. All core requirements and the six special
requirements are discussed in the Technical Information Report.
The report states that the existing substation and access road to the south convey runoff to the
existing detention pond on site. The pond was designed in 2016 for adherence to the City of Renton’s
Area-Specific Flow Control Facility. The existing substation runoff is captured in catch basins and
conveyed to the existing detention pond which sits immediately south of the existing substation.
Surface runoff from the areas peripheral to the existing substation also drain southward. The site for
the expansion area also drains primarily to the south and south west.
The proposed improvements would be graded to the south to drain to the existing pond located to
the south of the expansion area. The control structure in the existing pond would be modified to
control the additional impervious flow from the proposed pad. The new access road would be
constructed at existing grade to maintain existing drainage patterns to the extent possible.
The report states that existing pond has adequate capacity to receive the discharge from converted
surfaces. Following attenuation in the existing pond, stormwater will discharge to the natural location
southwest of the site.
Based on the proposal, the expansion project would not contribute any new Pollution Generating
Impervious Surface (PGIS) or Pollution Generating Pervious Surface (PGPS) since the proposed land
cover does not meet the definition of a pollution generating surface. As a result, the report concludes
that the project qualifies for the Surface Area Exemption from the requirement to provide a water
quality facility.
It is anticipated that the City’s currently adopted 2017 City of Renton Surface Water Design Manual
would mitigate for any potential surface water impacts that could be generated by the project
proposal, therefore no further mitigation is recommended at this time.
Mitigation Measures: No further mitigation recommended.
Nexus: N/A
D. Comments of Reviewing Departments
The proposal has been circulated to City Department and Division Reviewers. Where applicable, their comments
have been incorporated into the text of this report and/or “Advisory Notes to Applicant.”
Copies of all Review Comments are contained in the Official File and may be attached to this report.
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
City of Renton Department of Community & Economic Development
Talbot Hill Substation Current Limiting Reactors
Staff Report to the Environmental Review Committee
LUA19-000097, CUP-H, SA, ECF, SF
Report of June 17, 2019 Page 5 of 5
SR_ERC_Report_Talbot_Hill_Substation_190614_FINAL ERC Report_LUA 19-000097_Talbot Hill Substation
The Environmental Determination decision will become final if the decision is not appealed within the 14-day
appeal period (RCW 43.21.C.075(3); WAC 197-11-680).
Environmental Determination Appeal Process: Appeals of the environmental determination must be filed in writing
together with the required fee to: Hearing Examiner, City of Renton, 1055 South Grady Way, Renton, WA 98057, on
or before 5:00 p.m. on July 5, 2019. RMC 4-8-110 governs appeals to the Hearing Examiner and additional information
regarding the appeal process may be obtained from the City Clerk’s Office, Renton City Hall – 7th Floor, (425) 430-
6510.
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
CITY OF RENTON
DEPARTMENT OF COMMUNITY AND ECONOMIC DEVELOPMENT
STAFF REPORT TO THE ENVIRONMENTAL REVIEW COMMITTEE
EXHIBITS
Project Name:
Talbot Hill Substation Current Limiting
Reactors
Land Use File Number:
LUA19-000097, CUP-H, SA, ECF, SF
Date of Meeting
June 17, 2019
Staff Contact
Angelea Weihs
Associate Planner
Project Contact/Applicant
Kerry Kriner, Puget Sound
Energy, PO Box 97034, EST
4W, Bellevue, WA 98009-
9734
Project Location
2400 S Puget Drive
The following exhibits are included with the ERC Report:
Exhibit 1: Environmental Review Committee (ERC) Report
Exhibit 2: Site Plan
Exhibit 3: Drainage Report, prepared by Power Engineers, dated March 2019
Exhibit 4: Drainage Control Plan, prepared by Power Engineers, dated April 1, 2019
Exhibit 5: Geotechnical Report, prepared by GeoEngineers, dated February 1, 2017
Exhibit 6: Geotechnical Report Addendum Letter, prepared by GeoEngineers, dated January 29,
2019
Exhibit 7: Advisory Notes
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
EXISTINGSUBSTATION PADEXISTING ACCESS ROAD18.0' APPROXIMATEROAD WIDTH32.0' APPROXIMATE WIDTH 200.0' WIDE BPA EASEMENTA.F.N. 356049610' WIDE OLYMPIC PIPELINE EASEMENTREC. NO. 731026049510' WIDE OLYMPIC PIPELINE EASEMENTREC. NO. 731026049566.0' ROAD RIGHT-OF-WAY100' WIDE CITY OF SEATTLETRANSMISSION LINE EASEMENTA.F.N. 5333805EX. PONDEX. WATERMANHOLECLR PADEX. DRAINAGESTRUCTURE (TYP.)S85° 45' 05.00"W807.855'N1° 46' 11.80"E150.831'N85° 45' 05.00"E772.741'N71° 05
'
18.31"E197.597
'N89° 36' 50.13"E377.127'S1° 43' 51.18"W
228.229'S37° 45' 04.91"E515.473'L=188.980,R=1465.690D=7.3875S45° 08' 19.91"E718.908'S89° 10' 15.24"W2315.079'N1° 46' 11.80"E825.192'N71° 05' 18.31"E858.741'EX. CEDAR RIVERPIPELINE (LOCATION NOTVERIFIED)BPA EASEMENTA.F.N. 5178076218.4'EX. LIGHTPOLE (TYP.)981.8'NEW ACCESS ROADWVEX. WATERVALVE589.8'185.6'70.0'180.0'LEGEND:PROPOSED CLR AREAEXISTING SUBSTATIONEXISTING SECTION BOUNDARYEXISTING PROPERTY BOUNDARYEXISTING EASEMENTSEXISTING SUBSTATION ENCLOSURE (CHAIN LINK FENCE)PROPOSED CLR ENCLOSURE (CHAIN LINK FENCE)EXISTING UTILITY POLEPROPOSED UTILITY POLEEXISTING IMPERVIOUS COVERPROPOSED IMPERVIOUS COVERTOTAL POST-DEVELOPED IMPERVIOUSCOVERIMPERVIOUS COVER SUMMARY3.83 ACREA0.42 ACRES4.25 ACRESISSUED FOR PERMITJOB NUMBERDRAWING NUMBERREVSITE PLANS.DWG
PUGET SOUND ENERGYTALBOT HILL CLR STATIONSITE PLANEX A1506800SMT 04/01/2019PPG 04/01/2019HSL 04/01/20191"=80'JOB NUMBERDRAWING NUMBERREVISIONSTHIS DRAWING WAS PREPARED BY POWERIS PROHIBITED UNLESS WRITTEN PERMISSIONCONTAINED IN THIS DRAWING FOR ANY PURPOSEREUSE OF THIS DRAWING OR ANY INFORMATIONAND UNIQUE REQUIREMENTS OF THE PROJECT.TAKING INTO CONSIDERATION THE SPECIFICENGINEERS, INC. FOR A SPECIFIC PROJECT,FROM BOTH POWER AND POWER'S CLIENT ISGRANTED.REVSCALE:DATECKDDSGNDRNREFERENCE DRAWINGSAPPDDSGNCKDDRNFOR 24x36 DWG ONLY12345678REVEDCBA1" = 80'80240160040FEET147.7'25.2'EXHIBIT 2EXISTING POND FENCE (CHAIN LINK)EXISTING SUBSTATION ENCLOSURE (CHAIN LINK FENCE)PROPOSED CLR ENCLOSURE (CHAIN LINK FENCE)New access road: 330' long x 15' wide = 4950 sfDocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
March 2019
TECHNICAL INFORMATION REPORT
Talbot Hill CLR Installation
Renton, Washington
PROJECT NUMBER: 15060
PROJECT CONTACT: Stuart Toraason
EMAIL: stuart.toraason@powereng.com
PHONE: (513)326-1504
Entire DocumentAvailable in
Laserfiche
Submittals Folder
EXHIBIT 3
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
EXISTINGSUBSTATIONPADEX. PONDNEW CLR AREAEXISTING ACCESS ROADEXPANSION AREA (0.64 ACRES)EXISTING SUBSTATIONAREA (TYP.)T
T
T
TT
T
T
T EX. CONTROL CABLEEXISTING EMERGENCYOVERFLOWDRAINAGE CULVERTPROPOSED CLR ACCESS ROADEX. BPA EASEMENTAREAPROPOSED DRAINAGEDITCHEXISTING ROAD R/W LINE (TYP.)EXISTING CONTROLSTRUCTURE TO BEMODIFIED OR REPLACED(TYPE 2 CATCH BASIN)LEGEND:PROPOSED CLR STATION GRAVEL SURFACEPROPOSED ROAD GRAVEL SURFACEPROPOSED CONCRETE PADPROPOSED RIPRAPEXPANSION AREA (0.64 ACRES)EXISTING SUBSTATION (5.89 ACRES)EXISTING PARCEL BOUNDARYEXISTING EASEMENTEXISTING CLR ENCLOSURE (CHAIN LINK FENCE)EXISTING TREE LINE TO BE MAINTAINEDDRAINAGE DIRECTION FLOW ARROWEXISTING UTILITY POLEPROPOSED UTILITY POLEUSE WATER TIGHT COUPLING TO EXTENDEXISTING IMPERVIOUS COVERPROPOSED IMPERVIOUS COVERTOTAL POST-DEVELOPEDIMPERVIOUS COVER3.83 ACRES0.42 ACRES4.25 ACRESIMPERVIOUS COVER SUMMARYREPLACE PLATEWITH 1" ORIFICEREPLACE PLATEWITH 1/2" ORIFICERAISE TO 433.501.0'REPLACE PLATEWITH 1" ORIFICEUSE WATER TIGHT COUPLING TO EXTENDEXISTING 12-INCH DIAMETER PVC RISER 12"12" CONCRETE RISERON EXISTING TYPE 2CATCH BASINSTRUCTURE (TYP.)ISSUED FOR PERMITJOB NUMBERDRAWING NUMBERREVDRAINAGECONTROLPLAN.DWG
PUGET SOUND ENERGYTALBOT HILL CLR STATIONDRAINAGE CONTROL PLANEX C1506800SMT 04/01/2019PPG 04/01/2019HSL 04/01/20191"=40'JOB NUMBERDRAWING NUMBERREVISIONSTHIS DRAWING WAS PREPARED BY POWERIS PROHIBITED UNLESS WRITTEN PERMISSIONCONTAINED IN THIS DRAWING FOR ANY PURPOSEREUSE OF THIS DRAWING OR ANY INFORMATIONAND UNIQUE REQUIREMENTS OF THE PROJECT.TAKING INTO CONSIDERATION THE SPECIFICENGINEERS, INC. FOR A SPECIFIC PROJECT,FROM BOTH POWER AND POWER'S CLIENT ISGRANTED.REVSCALE:DATECKDDSGNDRNREFERENCE DRAWINGSAPPDDSGNCKDDRNFOR 24x36 DWG ONLY12345678REVEDCBAEXHIBIT 4DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
Earth Science + Technology
Geotechnical Engineering Services Revised
Report
Talbot Substation Improvements
Renton, Washington
for
Puget Sound Energy
February 1, 2017
Entire DocumentAvailable in
Laserfiche
Submittals Folder
EXHIBIT 5
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
2101 4th Avenue, Suite 950
Seattle, Washington 98121
206.728.2674
January 29, 2019
Puget Sound Energy
35131 SE Center Street, SQE-OTC
Snoqualmie, Washington 98065
Attention: Christopher Russell, PE
Subject: Addendum Letter
Geotechnical Engineering Services
Talbot Hill Substation CLR Improvements
Renton, Washington
File No. 0186-953-06
INTRODUCTION AND PROJECT UNDERSTANDING
This letter presents the results of GeoEngineers, Inc. (GeoEngineers) additional geotechnical engineering
services for the proposed current limiting reactor (CLR) improvements at the Puget Sound Energy (PSE)
Talbot Hill Substation located at 2400 Puget Drive SE in Renton, Washington. We previously provided
geotechnical recommendations for this project in our revised report dated February 1, 2017 and have
provided geotechnical construction observation services during Phases 1 and 2 of the substation
improvements. This letter incorporates and supersedes a previous draft dated January 25, 2019.
The Talbot Hill substation is located adjacent to the Bonneville Power Administration (BPA) Maple Valley
substation, and the two substations are interconnected. We understand BPA has identified potential risks
to their substation equipment in the event of an interconnection electrical fault. The site is shown in relation
to existing improvements in the Vicinity Map, Figure 1 and the Site Plan, Figure 2.
This project involves constructing six CLRs, one for each phase of the two transmission line interties, which
will act as surge protectors. The CLRs will be installed on elevated pedestals in a new yard area at the
southeast corner of the existing PSE Talbot Hill Substation (approximately 190 feet long and 85 feet wide).
The CLR yard area will be accessed by a new gravel access road. We understand the new yard area will
involve some grading but will not require retaining walls. The existing topography in the area of the proposed
CLR yard is slightly uneven, ranging from Elevation 441 to 445 feet.
Our geotechnical engineering services were completed in accordance with our proposal dated December
10, 2019. Our scope of work included developing geotechnical conclusions and recommendations and
preparing this addendum letter.
Entire Document
Available in
Laserfiche
Submittals Folder
EXHIBIT 6
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Page 1 of 2 LUA19-000097
ADVISORY NOTES TO APPLICANT
The following notes are supplemental information provided in conjunction with the administrative land use
action. Because these notes are provided as information only, they are not subject to the appeal process for
the land use action.
Planning:
(Contact: Angelea Weihs, 425-430-7312, aweihs@rentonwa.gov)
1. RMC section 4-4-030.C.2 limits haul hours between 8:30 am to 3:30 pm, Monday through Friday unless
otherwise approved by the Development Services Division.
2. Commercial, multi-family, new single family and other nonresidential construction activities shall be
restricted to the hours between seven o’clock (7:00) a.m. and eight o’clock (8:00) p.m., Monday through
Friday. Work on Saturdays shall be restricted to the hours between nine o’clock (9:00) a.m. and eight
o’clock (8:00) p.m. No work shall be permitted on Sundays.
3. Within thirty (30) days of completion of grading work, the applicant shall hydroseed or plant an
appropriate ground cover over any portion of the site that is graded or cleared of vegetation and where
no further construction work will occur within ninety (90) days. Alternative measures such as mulch,
sodding, or plastic covering as specified in the current King County Surface Water Management Design
Manual as adopted by the City of Renton may be proposed between the dates of November 1st and
March 31st of each year. The Development Services Division’s approval of this work is required prior to
final inspection and approval of the permit.
4. A National Permit Discharge Elimination System (NPDES) permit is required when more than one acre is
being cleared.
5. The applicant may not fill, excavate, stack or store any equipment, dispose of any materials, supplies or
fluids, operate any equipment, install impervious surfaces, or compact the earth in any way within the
area defined by the drip line of any tree to be retained.
6. The applicant shall erect and maintain six foot (6') high chain link temporary construction fencing around
the drip lines of all retained trees, or along the perimeter of a stand of retained trees. Placards shall be
placed on fencing every fifty feet (50') indicating the words, “NO TRESPASSING – Protected Trees” or on
each side of the fencing if less than fifty feet (50'). Site access to individually protected trees or groups
of trees shall be fenced and signed. Individual trees shall be fenced on four (4) sides. In addition, the
applicant shall provide supervision whenever equipment or trucks are moving near trees.
7. This permit is shall comply with the Bald and Golden Eagle Protection Act. The permitted is responsible
for adhering to the U.S. Fish and Wildlife Service National Bald Eagle Management Guidelines (2007) and
/or your U.S. Fish and Wildlife Service permit.
Development Engineering:
(Contact: Justin T. Johnson, 425-430-7291, jtjohnson@rentonwa.gov)
1. See Attached Development Engineering Memo dated June, 2019
Fire Authority:
(Contact: Corey Thomas, 425-430-7024, cthomas@rentonwa.gov)
1. No Comments
Technical Services:
(Contact: Amanda Askren, 425-430-7369, aaskren@rentonwa.gov)
EXHIBIT 7
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
ADVISORY NOTES TO APPLICANT
Page 2 of 2 LUA19-000097
1. No Comments
Community Services:
(Contact: Leslie Betlach, 425-430-6619, lbetlach@rentonwa.gov)
1. No Comments
Police:
(Contact: Cyndie Parks, 425-430-7521, cparks@rentonwa.gov)
1. No Comments
Building:
(Contact: Craig Burnell, 425-430-7290, cburnell@rentonwa.gov)
1. Recommendations of the geotechnical report must be followed as a condition of building permits.
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
M E M O R A N D U M
DATE: June 13, 2019
TO: Angelea Weihs, Planner
FROM: Justin Johnson, Civil Engineer III, Plan Review
SUBJECT: Talbot Hill Substation improvements
2400 S Puget Dr
LUA19-0000097
I have completed a preliminary review of the application of the above-referenced proposal
located at parcel 2023059066 and have the following comments: The applicant is proposing to
install an expansion of the substation located off of Puget Drive.
WATER
1. Based on the application the City of Renton does not have any water comments.
SANITARY SEWER
1. Based on the application the City of Renton does not have any waste water comments.
STORM DRAINAGE
1. The site currently contains an existing substation and there is newly installed on-site stormwater
detention system. There are no existing drainage improvements along Beacon Way S or Puget
Drive SE.
2. A geotechnical report was prepared by GeoEngineers on February 1st 2017 for the previous
project worked on this site.
a. The Geotech report mentions that infiltration may be feasible. Please provide an
updated Geotech report during your civil construction permit describing the work for
this project and includes information on the water table and soil permeability
(infiltration rates that meet 2017 RSWDM criteria).
3. Refer to Figure 1.1.2.A – Flow Chart to determine what type of drainage review is required for
this site. The site falls within the City’s Flow Control Standard area matching Forested
Conditions. The site falls within the Black River drainage basin. Drainage plans and a drainage
report complying with the adopted 2017 Renton Surface Water Design Manual will be required.
4. On-site BMPs satisfying Core Requirement #9 are be required for the site. Applicant is proposing
to use the reduced impervious surface credit.
a. The Geotechnical report notes that infiltration is possible within the site, therefore
infiltration must be evaluate to its maximum extent feasible prior to continuing on to
other On-Site BMPs (i.e. basic dispersion).
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
PSE Substation Improvements LUA19-0000097
Page 2 of 2
June 13, 2019
5. Applicant will need to ensure that the detention system installed with permit number
C17001111 has the capacity to support the new impervious surface. Frontage improvements for
the stormwater conveyance system will be installed with permit C17001111.
6. There is a 2019 system Development Charge of $0.72 per sq foot of new impervious surface
area, but not less than $1,800.00.
TRANSPORTATION
1. Current traffic impact fee is $6.84/SF for light industrial use. Payment of the transportation
impact fee is due at the time of issuance of the building permit.
2. The proposed development fronts Beacon Way South along the east property line(s). Beacon
Way South is classified as a Residential Access Road and is located within the City of Seattle
Cedar River Pipeline Easement. As the road is not public right-of-way, no dedication or frontage
improvements will be required as part of the re-development.
3. Frontage improvements along Puget Drive S was required as part of Civil Construction Permit
C17001111. A deferral permit has been obtained for the frontage improvements, therefore
frontage improvements are not required as part of this project.
4. Per the requirements of RMC 4-6-060, the proposed private access should be in a tract with a
minimum easement width of 26 feet and a minimum paved width of 20 feet and must have a
minimum pavement thickness of 4” of asphalt over 6” of crushed rock to meet city of Renton
standards. The private access should meet the requirements of the Renton Fire Authority.
GENERAL COMMENTS
1. Applicant will need to obtain a civil construction permit for the proposed work within the site.
2. Adequate separation between utilities as well as other features shall be provided in accordance
with code requirements.
a. 7-ft minimum horizontal and 1-ft vertical separation between storm and other utilities is
required with the exception of water lines which require 10-ft horizontal and 1.5-ft
vertical.
b. The stormwater line should be minimum 5 feet away from any other structure or wall or
building.
c. Trench of any utility should not be in the zone of influence of the retaining wall or of the
building.
3. All construction permits for utility and street improvements will require separate plan
submittals. All plans shall confirm to the Renton Drafting Standards. A licensed Civil Engineer
shall prepare the civil plans. Please visit the Development Engineering Forms page for the most
up-to-date plan submittal requirements:
http://rentonwa.gov/business/default.aspx?id=42473
4. A landscaping plan shall be included with the civil plan submittal. Each plan shall be on separate
sheets.
5. All utility lines (i.e. electrical, phone, and cable services, etc.) serving the proposed development
must be underground. The construction of these franchise utilities must be inspected and
approved by a City of Renton inspector.
6. Fees quoted in this document reflect the fees applicable in the year 2019 only and will be
assessed based on the fee that is current at the time of the permit application or issuance, as
applicable to the permit type. Please visit www.rentonwa.gov for the current development fee
schedule.
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
Enclosure
cc: King County Wastewater Treatment Division Ramin Pazooki, WSDOT, NW Region
Boyd Powers, Department of Natural Resources Larry Fisher, WDFW
Karen Walter, Fisheries, Muckleshoot Indian Tribe Duwamish Tribal Office
Melissa Calvert, Muckleshoot Cultural Resources Program US Army Corp. of Engineers
Stephanie Jolivette, Office of Archaeology & Historic Preservation Washington State Department of Ecology
June 21, 2019
Washington State
Department of Ecology
Environmental Review Section
PO Box 47703
Olympia, WA 98504-7703
Subject: ENVIRONMENTAL (SEPA) THRESHOLD DETERMINATION
Transmitted herewith is a copy of the Environmental Determination for the following project reviewed
by the Environmental Review Committee (ERC) on June 17, 2019:
SEPA DETERMINATION: Determination of Non-Significance (DNS)
PROJECT NAME: Talbot Hill Substation Current Limiting Reactors
PROJECT NUMBER: LUA19-000097, CUP-H, SA, ECF, SF
Appeals of the environmental determination must be filed in writing on or before 5:00 p.m. on July
5, 2019, together with the required fee with: Hearing Examiner, City of Renton, 1055 South Grady Way,
Renton, WA 98057. Appeals to the Examiner are governed by RMC 4-8-110 and information regarding
the appeal process may be obtained from the City Clerk’s Office, (425) 430-6510.
Please refer to the enclosed Notice of Environmental Determination for complete details. If you have
questions, please call me at (425) 430-7312.
For the Environmental Review Committee,
Angelea Weihs
Associate Planner
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
SIGNATURES:
Gregg Zimmerman, Administrator
Public Works Department
Date Rick M. Marshall, Administrator
Renton Regional Fire Authority
Date
Kelly Beymer, Administrator
Community Services Department
Date C.E. Vincent, Administrator Date
Department Of Community & Economic Development
ENVIRONMENTAL (SEPA) DETERMINATION OF
NON-SIGNIFICANCE (DNS)
PROJECT NUMBER: LUA19-000097, CUP-H, SA, ECF, SF
APPLICANT: Kerry Kriner, Puget Sound Energy, PO Box 97034, EST 4W, Bellevue, WA 98009
PROJECT NAME: Talbot Hill Substation Current Limiting Reactors
PROJECT DESCRIPTION: Puget Sound Energy (PSE) is requesting a Hearing Examiner Conditional Use
Permit, Environmental (SEPA) Review, Site Plan Review, and a Special Fence Permit for proposed Talbot Hill Substation
improvements located at 2400 S Puget Drive (parcel number 2023059066). The project site totals 13.4 acres and is zoned
Residential-8 (R-8). PSE is proposing to install six Current Limiting Reactors (CLRs) within a fenced enclosure adjacent to
the existing Talbot Hill Substation. The proposed CLRs will be installed on elevated pedestals with foundations, and
enclosed by an eight foot security fence. A new 190 foot long by 85 foot wide gravel pad will be constructed to support
the CLRs and the enclosure. The equipment will be accessed by a new approximately 330 foot long by 15 foot wide gravel
access road that will connect to an existing gravel driveway which extends from Puget Dr. SE. The proposal also includes
the installation of a new three-pole 230 kV H-frame (77 feet, 67 feet, and 77 feet above grade) outside the fenced area.
No tree or significant vegetation removal is proposed as part of this project. The project site contains moderate coalmine
hazards, moderate landslide hazards, and sensitive slopes (within 50 feet). The applicant submitted a Technical
Information Report (TIR) and Geotechnical Engineering Study with the application.
PROJECT LOCATION: 2400 S Puget Drive
LEAD AGENCY: City of Renton
Environmental Review Committee
Department of Community & Economic Development
The City of Renton Environmental Review Committee has determined that it does not have a probable significant adverse
impact on the environment. An Environmental Impact Statement (EIS) is not required under RCW 43.21C.030(2)(c). This
Determination of Non-Significance is issued under WAC 197-11-340. Because other agencies of jurisdiction may be
involved, the lead agency will not act on this proposal for fourteen (14) days.
Appeals of the environmental determination must be filed in writing on or before 5:00 p.m. on July 5, 2019. Appeals
must be filed in writing together with the required fee with: Hearing Examiner, City of Renton, 1055 South Grady Way,
Renton, WA 98057. Appeals to the Examiner are governed by RMC 4-8-110 and more information may be obtained from
the Renton City Clerk’s Office, (425) 430-6510.
PUBLICATION DATE: June 21, 2019
DATE OF DECISION: June 17, 2018
DocuSign Envelope ID: EAEF8F0A-FB97-4552-9FAF-C1CFC9A08FB6
6/17/2019 | 11:37 AM PDT
6/17/2019 | 2:44 PM PDT
6/17/2019 | 11:26 AM PDT
6/18/2019 | 2:26 PM PDT
MULCH PER SPECIFICATIONS(MULCH STEM)
NSCALE:FILE NO:
SHEET:
REV NODRAWING NO
12345678
12345678
A
B
C
D
E
A
B
C
D
E
CADD NO:
CLASS:
DATE (M/D/Y)SUBSTATION
ENGINEERING
DEPARTMENT
$FILE$$DATE$$USER$$$DGN$$CODE:
ENGINEER
REVIEWED
REVISION DESCRIPTION:
CAD
APPROVED
WO NUMBER:
OF
D-
Know what'sbelow.
before you dig.Call
R
SITE
1
TAL
90'-0"90'-0"70'-0"67'-0"67'-0"23'-0"23'-0"
180'-0"12'-6‚"10'-0"10'-0"12'-6‚"10'-0"10'-0"1"= 10'-0"
TALBOT HILL SUBSTATION
230KV SWITCHYARD
CLR LAYOUT
B
XXXXXXX
ISSUED FOR 60% REVIEW
43'-0"47'-0"47'-0"43'-0"
24'-9"18'-3"18'-3"28'-9"28'-9"18'-3"18'-3"24'-9"45'-0"25'-0"4"9"7"
8"4"6"17'-0"17'-0"NORTH-SOUTH BASELINE
N X°XX'XX WN X°XX'XX WEAST-WEST BASELINEL
L
LC CLR
L
CLR
C L
CLR
C L
CLR
C L
CLR
C
L
CLR
C L
CLR
C
--
B C
-
A
LAYOUT
1
MC2
MC1
12'-1•"
15'-2‡"
4"9"7"
8"4"6"
12'-1•"
15'-2‡"
MC2
MC1
SUPPORT
C CABLE
SUPPORT
C CABLE
STRUCTURE
TRANSMISSION
STRUCTURE
TRANSMISSION
DRAWINGS
SEE PLAN & PROFILE
STRUCTURE
TRANSMISSION
SCALE:FILE NO:
SHEET:
REV NODRAWING NO
12345678
12345678
A
B
C
D
E
A
B
C
D
E
CADD NO:
CLASS:
DATE (M/D/Y)SUBSTATION
ENGINEERING
DEPARTMENT
$FILE$$DATE$$USER$$$DGN$$CODE:
ENGINEER
REVIEWED
REVISION DESCRIPTION:
CAD
APPROVED
WO NUMBER:
OF
D-
Know what'sbelow.
before you dig.Call
R
SITE
1
TAL
AROUND SITE
WITH 1' OF BARB WIRE
7' COMPOSITE FENCE
TRANSMISSION LINE
OVERHEAD
TRANSMISSION LINE
OVERHEAD
APPX. 52'-0"7'-0"APPX. 23'-10‚"APPX. 35'-4•"7'-0"AROUND SITE
WITH 1' OF BARB WIRE
7' COMPOSITE FENCE
MC2
SUBSTATION
TO TALBOT
ELEVATION A-A
L
CLR
C
L
CLR
C L
CLR
C L
CLR
C L
CLR
C
L
CLR
C
L
L
CLR
C
ELEVATION B-B
XXXXXXX
TALBOT HILL SUBSTATION
230KV SWITCHYARD
CLR ELEVATIONS
1/8"= 1'-0"
ELEV
1
SUBSTATION
TO MAPLE VALLEY
APPX. 16'-7…"AROUND SITE
WITH 1' OF BARB WIRE
7' COMPOSITE FENCE
SUBSTATION
TO TALBOT
L
CLR
C
ELEVATION C-C
SUBSTATION
TO MAPLE VALLEY
APPX. 52'-0"APPX. 42'-0"12'-1•"
15'-2‡"
YARDS
BETWEEN REACTOR
BARB WIRE
WITHOUT 1' OF
FENCE
7' COMPOSITE
MC1
24'-9"18'-3"18'-3"28'-9"28'-9"18'-3"18'-3"24'-9"
43'-0"47'-0"47'-0"43'-0"
90'-0"
180'-0"
90'-0"APPX. 42'-0"70'-0"
45'-0"25'-0"45'-0"25'-0"
70'-0"
17'-0"17'-0"APPX. 18'-9"ISSUED FOR 60% REVIEW
IN
OUT
13'-4†"6'-8…"12'-1•"
15'-2‡"
IN
OUT
13'-4†"6'-8…"MC1 MC1
MC2
12'-1•"
15'-2‡"6'-8…"13'-4†"APPX. 23'-10‚"12'-1•"
15'-2‡"6'-8…"13'-4†"8'-6"MC2 MC2
MC1
8'-6"8'-6"8'-6"B
SUPPORT
CABLE
C L
SUPPORT
CABLE
C
ASSEMBLY
CABLE SUPPORT6'-8"11'-6"17'-0"17'-0"
SUPPORT
CABLE
C
SUPPORT
CABLE
CL L6'-8"11'-6"ASSEMBLY
CABLE SUPPORT6'-8"6'-8"18'-9"APPX. 23'-6•"APPX. 27'-7‚"7'-0"INLINE INSULATOR
INLINE INSULATOR
TALBOT HILL SUBSTATION 230 kV 3-POLE DEADEND
75'-0"
65'-0"
75'-0"
5'-0"5'-0"5'-0"
1'-4"
1'-0"
1'-4"
FINISHED
GRADE
2'-0"
(TYP)