Construc�on Mi�ga�on Descrip�on
Proposed Construc�on Dates: 1/1/20 – 9/1/20
Hours and Days of Opera�on: M-F, 7AM – 4PM
Proposed Hauling and Transporta�on Routes: transporta�on routes will go from the site on 116th and
then north to 168th Street or south to Petrovitsky Road. All routes are on arterials and not through
residen�al neighborhoods.
Measures to be implement to minimize dust, traffic and transporta�on impact, erosion, mud, noise, and
other noxious characteris�cs:
Dust: Given that construc�on will largely occur during fall and winter, dust issues are not
an�cipated. However, if dust is an issue, Contractor to provide water tank.
Traffic: Site provides significant laydown area for equipment and materials, therefore no traffic
impact is foreseen on site or on public streets.
Erosion/Mud: Contractors to establish and inspect BMPs related to erosion and sediment such
as filter fence, waddles, wheel washes, protec�on of catch basins and storm drains, etc.
Contractor to follow pollutant control measures. No stockpiling of soil an�cipated. Dewatering
not expected.
Noise: No adverse noise expected. Construc�on to occur during day�me hours.
Noxious characteris�cs: None an�cipated.
Special hours: none proposed.
Preliminary traffic control plan: no traffic control plan an�cipated.