HomeMy WebLinkAboutContract *MW CAG-04-089
Transportation Improvement Board
FY 2005 Program Project Funding Status
Agency RENTON TO Project Number P-P-102(P01)-1
Project Name Benson Road S
440 Ft S of Main Ave S to South 26th St
Update the project schedule and funding source information. Both agency officials must sign the form
before returning it to the TIB office. The project must be included on your adopted Six Year
Transportation Program (TIP) before TIB authorizes Design Phase. Include the page from the adopted
TIP that includes the project. Please mail the completed form and TIP excerpt to the:
Transportation Improvement Board ❖ Post Office Box 40901 ❖ Olympia, WA 98504-0901
PROJECT SCHEDULE
Update the project schedule targets or indicate NO CHANGE in the table below
Date Shown on Note NO CHANGE or
Application New Target Month/Year
Construction Approval Date May 2005 No Change
.........................................................................................._...................._......_.............................................................................__.............._.___........................................................................................................................................................................................................................
Contract Bid Award
................................................__........_._._._.__.._._...._.._............................................................................................._....................................................................................................................................
Contract Completion Oct 2005 No Change
PROJECT FUNDING PARTNERS
Update the funding partners and corresponding amounts or indicate NO CHANGE in the space provided
Funding Partners Amount Note FUNDS COMMITTED or
Changes for Each Partner
RENTON 93,000 Funds Committed
..................................................................................................._.......................................................__.._......._..._.._..........................................._.....................................................................................................................................................................................---........................................
WSDOT 0
...............................................................................................................................................................................................I....................................................................................
Federal Funds 0
.......................................................................................................................................................................... ....... .............................................................................................
Developer Mitigation 238 .
900 Funds Committed
...................................................................................................................._.................................._..............................................................................................................._........................................................................................._................................................................................................................................
....................................._...._......................................................_..._.................._........._.._..................................._...................................................._........................_._.............._......................................................................................................---..........................................................
............................................_........................................._..........................................................._......._............................_......................................_._.........................................................................................................................................................................................................................
........................................................................................................................................................................................._...._......................................................................................................._................................................._........_..........................................................................................................
........................................................................................................................................._............................................._.....__......._..........................................................................................................................................................................................................................................---..............
..........
...................................................................................................................................................................................................................................................................................................................................................................................................................................................................................
TOTAL LOCAL FUNDS $331,900 Funds Committed
By signing below, you certify that all funds shown in the Project Funding
Partners table are committed for the project.
Mayor or Public Works Director
2�" ktl� -.2.2 0
Signatur & Date
Kathy Keolker-Wheeler Mayor
Printed or Typed Name Title
Financial Officer Attest: „ „(�t.r (.!/Y��/✓rte
1 (0 .Michele Neumann. Deputy City Clerk
Signature & Date
Victoria Runkle Administrator, Finance & Info. Systems
Printed or Typed Name Title
TIB Funding Status Report.doc
CAG-04-089 Addendum 1-04
Wash ingtorr-Sta te
o Transportation Improvement Board
n Impe
Transmittal Letter
TIB Members
June 29, 2004 u r
COuncilmember William Ganley v"
Chair,City of Battle Ground OI - F,
NT r�h�r
Mr. Greg Zimmerman P. E. "� �C`��I,D� �
Commissioner Leo Bowman ,
Vice Chair,Benton County public Works Administrator
Mr.John Akers,P.E City of Renton
City of Ellensburg y
Ms.Bonnie Berk 1055 South Grady Way
Berk and Associates Renton, WA 98055-3232
Councilmember Jeanne Burbidge
City of Federal Way
Mr.George Cress Pedestrian Safety and Mobility Program
Port of Longview TIB Project Number P-P-102(P01)-1 .( ., "
f
Ms.Kathleen Davis
WSDOT Benson Road S JUL - 9 2004
Ms.Paula Hammond,P E 440 Ft S of Main Ave S to South 26th St I
WS°GT Design and Construction Phase Approval yp
Councilmember Neil McClure
City of Yakima
Councilmember Rob McKenna This is to confirm that the TIB has authorized the design and construction
King County phases of this project effective June 29, 2004. Please sign the enclosed Fuel
C'tyolfBelrngharn Tax Grant Distribution Agreement and return the original to the TIB. After
Mr.Dave Nelson completion of the project design, send a half-size set of plans, specifications and
Grant County
Mr Dave O'Connell the final engineer's estimate to your TIB project engineer. You will receive
Mason County approval to advertise the contract after TIB staff has reviewed the plans and
Commissioner Mike Shelton contract documentation.
Island County
Mr.David ae
City of Wenatchee Reimbursement requests will be processed after an executed Fuel Tax Grant
Mr.Arnold TOmac Distribution Agreement is received by the TIB. You may request reimbursement
Bicycle Alliance of Washington from TIB beginning July 1, 2004.
Mr.Theo Yu
Office of Financial Management
Mr.Jay Weber Future Requirements
:ounty Road Administration Board 1. In accordance with TIB Guidelines, complete an Updated Cost Estimate
Ms.Kim Zentz
Spokane Transit Autr;ority (UCE) form after bid opening and prior to agency award of the contract.
Contact your TIB project engineer to request the form. After receiving the
completed UCE form, your project engineer will give approval to award the
contract.
Mr.Stevan Gorcester 2. Submit a TIB Reimbursement Form to request payment for incurred eligible
Executive Director project costs. Requests for reimbursement can be submitted electronically at
P.O.Box 40901
Olympia,WA 98504-0901 www.tib.wa.gov/services/reimbursements/reimbursements.htm.
Phone.360-586-1140
Fax 360-586-1165
www.tibwa.gov For assistance with your project, contact Greg Armstrong, TIB Project Engineer,
at (360) 586-1142 or via e-mail at GregA @TIB.wa.gov.
Investing in your local community
/����► \ Washington Stat ansportation Improvement Board CAG-04-089 Addendum 1-04
0 Fuel Tax Gran istribution Agreement
LEAD AGENCY: City of Renton
PROJECT NUMBER: P-P-102(P01)-1
PROJECT TITLE: Benson Road S
PROJECT TERMINI: 440 Ft S of Main Ave S to South 26th St
1.0 PURPOSE
The Washington State Transportation Improvement Board (hereinafter referred to as
"TIB") hereby grants funds for the project specified in the attached documents, and as
may be subsequently amended, subject to the terms contained herein. It is the intent of
the parties, TIB and the grant recipient, that this Agreement shall govern the use and
distribution of the grant funds through all phases of the project. Accordingly, the project
specific information shall be contained in the attachments hereto and incorporated
herein, as the project progresses through each phase.
This Agreement, together with the attachments hereto, the provisions of chapter 47.26
Revised Code of Washington, the provisions of title 479 Washington Administrative
Code, and TIB Policies, constitutes the entire agreement between the parties and
supercedes all previous written or oral agreements between the parties.
2.0 PARTIES TO AGREEMENT
The parties to this Agreement are TIB, or its successor, and the grant recipient, or its
successor, as specified in the attachments.
3.0 TERM OF AGREEMENT
This Agreement shall be effective upon execution by TIB and shall continue through
completion of each phase of the project, unless terminated sooner as provided herein.
4.0 AMENDMENTS
This Agreement may be amended by mutual agreement of the parties. Such
amendments shall not be binding unless they are in writing and signed by personnel
authorized to bind each of the parties.
5.0 ASSIGNMENT
The grant recipient shall not assign or transfer its rights, benefits, or obligations under
this Agreement without the prior written consent of TIB. The grant recipient is deemed
to consent to assignment of this Agreement by TIB to a successor entity. Such consent
shall not constitute a waiver of the grant recipient's other rights under this Agreement.
6.0 GOVERNANCE & VENUE
This Agreement shall be construed and interpreted in accordance with the laws of the
state of Washington and venue of any action brought hereunder shall be in the Superior
Court for Thurston County.
TIB Form 190-500 Page 1 of 3 Rev.2/14/2003
Washington Stat ,ansportation Improvement Board
Fuel Tax GranfDistribution Agreement
7.0 TERMINATION
7.1 UNILATERAL TERMINATION
Either party may terminate this Agreement upon 30 days' prior written notice to
the other party. If this Agreement is so terminated, the parties shall be liable only
for performance rendered or costs incurred in accordance with the terms of this
Agreement prior to the effective date of termination.
7.2 TERMINATION BY MUTUAL AGREEMENT
Either party may terminate this contract in whole or in part, at any time, by mutual
agreement with a 30 calendar day written notice from one party to the other.
7.3 TERMINATION FOR CAUSE
In the event TIB determines the grant recipient has failed to comply with the
conditions of this Agreement in a timely manner, TO has the right to suspend or
terminate this Agreement. TIB shall notify the grant recipient in writing of the
need to take corrective action. If corrective action is not taken within 30 days, the
Agreement may be terminated. TIB reserves the right to suspend all or part of
the Agreement, withhold further payments, or prohibit the grant recipient from
incurring additional obligations of funds during the investigation of the alleged
compliance breach and pending corrective action by the grant recipient or a
decision by TIB to terminate the Agreement. The grant recipient shall be liable
for damages as authorized by law including, but not limited to, repayment of
misused grant funds. The termination shall be deemed to be a Termination for
Convenience if it is determined that the grant recipient: (1) was not at fault, or (2)
failure to perform was outside of the grant recipient's control, fault or negligence.
The rights and remedies of TO provided in this Agreement are not exclusive and
are in addition to any other rights and remedies provided by law.
7.4 TERMINATION FOR CONVENIENCE
TIB may, by ten (10) days written notice, beginning on the second day after the
mailing, terminate this Agreement, in whole or in part, because federal or state
funds are no longer available for the purpose of meeting TIB's obligations, or for
any reason. If this Agreement is so terminated, TIB shall be liable only for
payment required under this Agreement for performance rendered or costs
incurred prior to the effective date of termination.
7.5 TERMINATION PROCEDURE
Upon receipt of notice of termination, the grant recipient shall stop work and/or
take such action as may be directed by TIB.
TIB Form 190-500 Page 2 of 3 Rev.2/14/2003
Washington Stat ansportation Improvement Board
Fuel Tax Granistribution Agreement
8.0 ATTACHMENTS
Attachment 1 specifies the grant program applicable to this project, identifies the grant
recipient, and contains the list of additional documents specific to the project which will
be attached and incorporated into this Agreement, together with subsequent
amendments, as the project progresses through each phase of design and construction.
Approved as to Form
This 14th Day of February, 2003
Christine O. Gregoire
Attorney General
By:
Signature on file
Jeanne A. Cushman
Assistant Attorney General
Lead Agency Transportation Improvement Board
Sigrfiture of Chairman/Mayor Date Executive Director Dat
Kathy Keolker—Wheeler, Mayor
Print Name Print Name
Attest:
.111 •
Bonnie I. Walton, City Clerk
TIB Form 190-500 Page 3 of 3 Rev.2/14/2003
r"
Attachment 1
Pedestrian Safety and Mobility Program
Project Description
and
List of Documents to be Attached to Agreement at each
Phase of the Project
Project Information
Lead Agency: City of Renton
Project Number: P-P-102(P01)-1
Project Title: Benson Road S
Project Termini: 440 Ft S of Main Ave S to South 26th St
TIB funds for the project are as follows:
Phase TIB Funds
Design 12,000
Construction 138,000
Total Grant 150,000
Documents Required Prior to Advertising
• Plans and Specifications package
• Final Engineer's Estimate
Documents Required at Bid Award Phase
• Bid Award Updated Cost Estimate Form
• Bid Tabulations
• Cost change justification
Documents Required at Contract Completion Phase
• Contract Completion Updated Cost Estimate Form
• Final Quantities and Ledger
• Cost change justification
Amendments to Agreement (if any)
TO Form 190-605 Rev.2/14/2003