HomeMy WebLinkAboutRES 3975CITY OF RENTON,WASHINGTON
RESOLUTION NO.3975
A RESOLUTION OF THE CITY OF RENTON,WASHINGTON,
AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE THE
UTILITY CONSTRUCTION AGREEMENT BETWEEN THE CITY OF
RENTON AND THE WASHINGTON STATE DEPARTMENT OF
TRANSPORTATION REGARDING THE INCLUSION OF THE CITY
FIBER OPTIC CONDUIT IN THE 1-405/1-5 TO SR 169 STAGE 2-
WIDENING PROJECT.
WHEREAS,the Washington State Department of Transportation (WSDOT)1-405/1-5 to
SR 169 Stage 2-Widening project,scheduled to begin in early 2009,will build an additional lane
on 1-405 in each direction between SR 167 and SR 169,reconstruct Benson Road from City Hall
south over 1-405 and widen Talbot Road between South Renton Village Place and Puget Drive;
and
WHEREAS,the IS Division and the Transportation Division require conduit to extend
the City fiber network south ofI-405;and
WHEREAS,cost and construction efficiencies will be realized by including this work
with the WSDOT 1-405 Stage 2 project,since this project will build a new Benson Road bridge
and will reconstruct a significant portion of Talbot Road S.;and
WHEREAS,the Utility Construction Agreement establishes that this conduit work will
be bid separately within the WSDOT Stage 2 project and will be funded by the City;
NOW,THEREFORE,THE CITY COUNCIL OF THE CITY OF RENTON,
WASHINGTON,DOES RESOLVE AS FOLLOWS:
SECTION I.The above recitals are found to be true and correct in all respects.
1
SECTION II.
RESOLUTION NO.3975
The Mayor and City Clerk are hereby authorized to execute the
Utility Construction Agreement with WSDOT for the purpose of extending the City fiber
network south ofI-405.
PASSED BY THE CITY COUNCIL this 6th day of __O_c_t_o_b_e_r__,2008.
~./;v1.LJ~
Bonnie I.Walton,City Clerk
APPROVED BY THE MAYOR this 6th day of October ,2008.
Appr~as to form:.
~~""~fIt"~/l..u~
Lawrence 1.Warren,City Attorney
RES.1372:9/17/08:scr
2