Exhibit B: Time Schedule of Completion City of Renton Highlands 435 Pressure Zone Reservoirs Improvements Phase 1 – Emergency Generator Replacement and Radio Equipment Relocation Task Anticipa tedCompletion Task 1 – Standby Emergency Backup Generator Design November 30, 2014 Task 2 – VHF Radio Equipment Relocation Design November 30, 2014 Task 3 – Design Review Meetings 60-percent - October 31, 2014 90-percent - November 30, 2014 Task 4 – Finalize Plans and Specifications December 19, 2014 Task 5 – Permitting Unknown Task 6 – Services During Bidding Dependent on Construction Schedule CONTRACT COMPLETION DATE: December 31, 2015