HomeMy WebLinkAboutFinal_PSA_Exhibit B_Completion Schedule_Highlands EG ReplacementExhibit B: Time Schedule of Completion City of Renton – WTR2703759 Replace Highlands Reservoir Site Emergency Electrical Power Generator Task Anticipated Completion Date  Task 1 – Standby Emergency Backup Generator Design 90 working days after Notice to Proceed (NTP)  Task 2 – VHF Radio Equipment Relocation Design 90 working days after NTP  Task 3 – Design Review Meetings 60-percent – 30 working days after NTP 90-percent – 60 working days after NTP  Task 4 – Finalize Plans and Specifications 90 working days after NTP  Task 5 – Permitting Unknown  Task 6 – Services During Bidding Dependent on Construction Schedule   CONTRACT COMPLETION DATE: December 31, 2015