RESOLUTION NO. 2622
A RESOLUTION OF THE CITY OF RENTON, WASHINGTON,
PROVIDING FOR TRANSFER OF FUNDS FOR WATER AND
SEWER CAPITAL IMPROVEMENT PROJECTS.
WHEREAS, Water and Sewer Utility Connection Charge revenues,
accounted for in Cumulative Reserve Fund No. 3665, are to be used as
a resource for Water and Sewer Capital Improvement Projects, and
WHEREAS, the City Council has approved the 1985 Water and Sewer
Capital Improvement Program as required by Ordinance #3665; list
attached hereto as Exhibit "A" and made a part hereof as if fully
set forth, and
WHEREAS, Ordinance No. 3949 did appropriate $134,000 to said
Cumulative Reserve, and the total amount now available is $374,000, and
WHEREAS, it is now necessary to provide for the transfer of $374 ,000
from Cumulative Reserve Fund #3665 to the Water and Sewer Construction
Fund, and such transfer being necessary and in the public interest and
for the public benefit , NOW THEREFORE,
THE CITY COUNCIL OF THE CITY OF RENTON, WASHINGTON, DO RESOLVE
AS FOLLOWS:
Section I : The Director of Finance is hereby authorized and
directed to make the following transfers:
Cumulative Reserve Fund #3665 - decrease Ending Fund Balance
Appropriation and increase Operating Transfers-Out Appropriation:
From: a/c 128/000/00. 508 .00.00.00 (Ending Fund Balance) . . . . . . $240,000
Unto: a/c 128/000/15. 597.38. 55.21 (Operating Transfers-Out) . . $240,000
Transfer from Cumulative Reserve Fund #3665 (Fund #128) to
Water and Sewer Construction (Fund #421) :
From: a/c 128/000/15. 597.38.55.21 (Operating Transfers-Out) . . $374 ,000
(Expend - Cash Transfer)
Unto: a/c 421/000/397.00.00.28 (Operating Transfers-In) . . . . . . $374 ,000
( Increase Revenue Estimate; Revenue Received - Cash Transfer)
Unto: a/c 421/000/15. 596. 38.65.15 (Water System
Improvements/Major - Increase Appropriation . . . . . . . . . . . . $374 ,000
-1-
CITY OF RENTON, WASHINGTON
W
RESOLUTION NO. 2622 - Continued
PASSED BY THE CITY COUNCIL this 14th day of October, 1985.
Maxine E. Motor, City Clerk
APPROVED BY THE MAYOR this 14th day of October, 1985.
t�Cu�OCa51t� `Pn
Barbara Y. hinpoch, Mayor
Approved as to Form:
Lawrence J. Warren, City.,Attorney
-2-
+ EXHIBIT "A"
_ CITY OF RENTON RESOLUTION No. 2622 1985 ANNUAL BUDGET
Department: PUBLIC WORKS DEPARTMENT Fund: WATER AND SEWER UTILITY FUND
WATER AND SEWER CONSTRUCTION FUND
Division: ALL DIVISIONS OF WATER/SEWER UTILITY Account: 401 and 421
1985 WATER AND SEWER CONSTRUCTION PROGRAM
WATER SYSTEM REHABILITATION PROJECTS
Capital
Project 8
CP-16 Replacement of 12" steel watermain in Union Avenue NE
from NE 17th Street to BE 99th Street. Proposed Street
project. $ 173,000
8" D.I. watermain in NE Sixth Street from Monroe Avenue
NE to Union Avenue NE (in conjunction with Street project). 81,000
(a/c 65.27 on page 260) Sub-total = 254,000
SANITARY SEWER SYSTEM REHABILITATION PROJECTS
Sunset Pump Station sewer repair, Phase II
Sewer TV, joint and manhole grouting
Glencoe Division II S 60,000
Cedar River Park sewer repair
Sewer TV, joint and manhole grouting
To protect City water supply wells from possible
sewage leaks. 30,000
Lake Washington sewer investigation and design
Investigate the submerged City sewer off of Kennydale,
in Lake Washington for stability and design improvements
to flush system. 30,000
. Sewer replacement (1985) - Miscellaneous:
a. Wells Avenue South - from South Fifth Street
to South Fourth Street
b. Alley between Meadow Avenue North and Factory
Avenue North from North Second Street to North
Third Street
c. Powell Avenue SW - from Langston Road to SW Third
Place 90,000
(a/c 65.28 on page 260) Sub-total $ 210,000
-3-
EXHIBIT "A"
CITY OF RENTON RESOLUTION NO. 2.622 1985 ANNUAL BUDGET
Department: PUBLIC WORKS DEPARTMENT Fund: WATER AND SEWER UTILITY FUND
WATER AND SEWER CONSTRUCTION FUND
Division: ALL DIVISIONS OF WATER/SEWER UTILITY Account: 401 and 421
1985 WATER AND SEWER CONSTRUCTION PROGRAM - Continued
WATER SYSTEM PROJECTS/MAJOR
CP-35 Well #9 Pump House $ 138,000
CP-70 West Hill Booster Pump Station 109,000
CP-91 Installation of 12" D.I. watermain in Grady Way at
Springbrook Creek (in conjunction with Street project). 18,000
CP-51 Installation of 12" D.I. watermain in Grant Avenue South
from South Tenth Street to South Seventh Street, and in
South Seventh Street from Grant Avenue South to Renton
Avenue South. 52,000
CP-61 Installation of 8" D.I. watermain and transfer of
watermain from WD #58 at.the Plat of Ponderosa Estates
near Rolling Hills Reservoir. 38,000
CP-62 Construction of pressure reducing station at South 26th
Street and Benson Road South. 21,000
CP-65 Design of South Talbot Hill Reservoir 70,000
CP-105 Reconstruction of telemetry system 291,000
CP-122 Installation of 3" conduit and wire from new City Shops
to City Hall 56,000
Installation of 12" watermain in Lind Avenue South from
South 16th Street to Grady Way South (in conjunction
with WSDOT bridge widening). 50,000
Installation of two PRV stations at South 20th Street
and Shattuck Avenue South. 40,000
Purchase of 2,100 L.F. of installed 8" watermain and
miscellaneous services from W.D. #14 in conjunction with
West Hills Project. 30,000
Miscellaneous pump adjustments and additions 29,000
1211 watermain installation of Wells Avenue North from
North Riverside Drive to north side of North First Street.
(Replacement of services and hydrants on North First Street
in conjunction with street overlay project.) 70,000
P-1 Channel - SW Seventh Street 12" watermain relocation
for P-1 Channel excavation. 40,000
CP-120 Purchase of Squire property at Springbrook Springs.
160,000
CP-65 Purchase of Covenant Church property for South Talbot Hill
Reservoir. 40,000
CP-85 Purchase of future site of Black River Quarry Reservoir 10,000
CP-75 Installation of 24" transmission main in South Second Street. 30,000
CP-76 West Hill Reservoir 300,000
We 65.15 on page 260) Sub-total $1,592,000
—4—
§R CITY OF RENTON EXHIBIT "A"
• i RESOLUTION N0. 2622 1985 ANNUAL BUDGET
EWER UTILITY FUND
Department: PUBLIC WORKS DEPARTMENT Fund: WATER AND S
WATER AND SEWER CONSTRUCTION FUND
Division: ALL DIVISIONS OF WATER/SEWER UTILITY Account: 901 and 921
1985 WATER AND SEWER CONSTRUCTION PROGRAM - Continued
SANITARY SEWER SYSTEM PROJECTS/MAJOR
Honey .Creek Interceptor Sewer:
New 12" sewer, pump station in Honey Creek from Devil's
Elbow to Sunset Boulevard NE and Union Avenue NE, together
with downstream sewer system revisions. $ 960,000
CBD SW 24" Trunk Sewer Replacement - Phase II:
Replace 24" South CBD sewer in Shattuck Avenue South
alignment from Tobin Avenue South to South Second
Street through High School. Coordinate with upcoming
WSDOT overlay of South Second Street (SR-900). 142,000
East Hennydale Interceptor:
New 12" sanitary sewer from NE 27th Street to Azalea
Lane pump station (in conjunction with Aberdeen Avenue
NE Forward Thrust project). 100,000
Duvall Avenue NE Sewer Extension (or North First Street
Sewer Replacement CBD-N):
Extend 8"sewers to eliminate Eastwood Park pump station
(eliminate inadequate pump station by gravity flow to
the south). 110,000
Renton Avenue Sever Extension:
Rebuild existing Tobin Avenue and Victoria Place sewer
and Rainier Avenue South crossing (in conjunction with
WSDOT Rainier Avenue South overlay). 50,000
Sever Replacement - Shattuck Avenue South Interceptor -
Phase I CBD-SE:
Replace existing 811, 1011, and 12" sewers in Shattuck
Avenue South from South Fourth Street to South Seventh
Street. 40,000
(a/c 65.19 on page 260) Sub-total $1,402,000
TOTAL CONSTRUCTION PROGRAMS ...... $3,458,000