HomeMy WebLinkAboutLUA-05-029Printed: 03-11-2005
Payment Made:
~ITY OF RENTON
1055 S. Grady Way
Renton. WA 98055
Land Use Actions
RECEIPT
Permit#: LUA05-028
03/11/200512:54 PM Receipt Number:
DEVELOPMENT PLANNING
CITY OF RENTON
MAR 11 2005
RECEIVED
R0501284
Total Payment: 450.00 Payee: HARBOUR HOMES INC
Current Payment Made to the Following Items:
Trans Account Code Description Amount
5015 000.345.81.00.0012 Lot Line Adjustment 450.00
Payments made for this receipt
Trans Method Description Amount
Payment Check #12071 450.00
Account Balances
Trans Account Code Description Balance Due
3021 303.000.00.345.85 Park Mitigation Fee
5006 000.345.81.00.0002 Annexation Fees
5007 000.345.81.00.0003 Appeals/Waivers
5008 000.345.81.00.0004 Binding Site/Short Plat
5009 000.345.81.00.0006 Conditional Use Fees
5010 000.345.81.00.0007 Environmental Review
5011 000.345.81.00.0008 Prelim/Tentative Plat
5012 000.345.81.00.0009 Final Plat
5013 000.345.81.00.0010 PUD
5014 000.345.81.00.0011 Grading & Filling Fees
5015 000.345.81.00.0012 Lot Line Adjustment
5016 000.345.81.00.0013 Mobile Home Parks
5017 000.345.81.00.0014 Rezone
5018 000.345.81.00.0015 Routine Vegetation Mgmt
5019 000.345.81.00.0016 Shoreline Subst Dev
5020 000.345.81.00.0017 Site Plan Approval
5021 000.345.81.00.0018 Temp Use or Fence Review
5022 000.345.81.00.0019 Variance Fees
5024 000.345.81.00.0024 Conditional Approval Fee
5036 000.345.81.00.0005 Comprehensive Plan Amend
5909 000.341.60.00.0024 Booklets/EIS/Copies
5941 000.341.50.00.0000 Maps (Taxable)
5954 604.237.00.00.0000 Special Deposits
5955 000.05.519.90.42.1 Postage
5998 000.231.70.00.0000 Tax
Remaining Balance Due: $0.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
.00
City of., ion Department of Planning / Building / Public Jrks
ENVIRONMENTAL & DEVELOPMENT APPLICATION REVIEW SHEET
REVIEWING DEPARTMENT: I;) '" '10
APPLICATION NO: LUA05-029, TP
APPLICANT: John Hobson, Citvof Renton
PROJECT TITLE: Sunset Sewer Temo Storaae Permit
SITE AREA: 39,225 sauare feet
LOCATION: 701 Sunset Blvd NE
COMMENTS DUE: MARCH 30, 2005
DATE CIRCULATED: MA~~
PROJECT MANAGIt1'I:' Jill Hall
'--PLAN REVIEW: KavrillT1'G rick
BUILDING AREA (oross): NlA
I WORK ORDER NO: 77396
-J
//
SUMMARY OF PROPOSAL: The proposal is to use a 3 parcel site as a staging area for use during the construction of the Sunset
Sewer Interceptor Phase II project. The site will be used to store pipe, manhole sections, backfill aggregates, construction equipment,
a job shack and other items normally associated with utility construction. All construction material will be removed and site reseeded
at the end of construction. The staging area will be in operation from April 2005 through November 2005.
A. ENVIRONMENTAL IMPACT (e.9-Non-Code) COMMENTS
Element of the Probable Probable More Element of the Probable Probable More Environment MInor Major Information
Impacts Impacts Necessary Environment Minor Major Information Impacts Impacts Necessary
Earth
Air
Water
Plants ecreation
Land/Shoreline Use 'iIi'ies
Animals ,
Environmental Health Public Services
Energy/
Natural Resources
Abporl . ~~'~L:
B. POLICY-RELA TED COMMENTS
C. CODE-RELATED COMMENTS
We have reviewed this application with particular attention to those areas in which we have expertise and have identified areas of probable impact or
areas where additional infonnation f'lneeded to properly assess this proposal.
OYQ?)M :1-IX'-()~
Signature of Director or Authorized Representative Date
--
CITY OF RENTON
PLANNING / BUILDING / PUBLIC WORKS
MEMORANDUM
Date: May 2, 2005
To: City Clerk's Office
From: Stacy M. Tucker
Subject: Land Use File Closeout
Please complete the following information to facilitate project closeout and indexing by the City
Clerk's Office
Project Name: Sunset Sewer Temporary Storage
LUA (file) Number: LUA-05-029, TP
Cross-References: LUA04-161, ECF, LUA05-033, TP
AKA's: Sunset Sewer Staging Area
Project Manager: Jill Hall
Acceptance Date: March 16, 2005
Applicant: John Hobson -City of Renton
Owner: George Kalasountas
Contact: John Hobson -City of Renton
PID Number: 3119900005; 3119900010; 3119900011
ERC Decision Date:
ERC Appeal Date:
Administrative Approval: April 4, 2005
Appeal Period Ends: April 18, 2005
Public Hearing Date:
Date Appealed to HEX:
By Whom:
HEX Decision: Date:
Date Appealed to Council:
By Whom:
Council Decision: Date:
Mylar Recording Number:
Project Description: The proposal is to use a 3 parcel site as a staging area for use during the
construction of the Sunset Sewer Interceptor Phase II project. The site will be used to store pipe,
manhole sections, backfill aggregates, construction equipment, a job shack and other items
normally associated with utility construction. All construction material will be removed and site
reseeded at the end of construction. The staging area will be in operation from April 2005 through
November 2005.
Location: 701, 715 Sunset Blvd NE
Comments:
John Hobson
City of Renton -Utilities
,
(applicant / contact) .
Updated: 03/22/05
PARTIES OF RECORD
Sunset Sewer Temp Storage
LUA05-029, TP
Marsha Stubbins George Kalasountas
9563 Malbis Lane
Daphne, AL 36526
tel: 251-626-1081
(owner)
821 Sunset Blvd NE ste: #6-1
Renton, WA 98056
tel: 425-227-6482
(party of record)
(Page 1 of 1)
City of Renton File Number: LUA05-029, TP
Project Name: Sunset Sewer Temporary Storage
Location: 701 Sunset Boulevard NE Renton, WA 98055
Parcels: 311990-0005,311990-0010, and 311990-0011
Property Owners: George Kalasountas
Applicant Name: John Hobson, City of Renton
ProJect Description: The applicant has applied for a Temporary Use permit for
a temporary construction staging area during construction of the Sunset Sewer
Interceptor Phase II project. The site will be used to store pipe, manhole
sections, backfill aggregates, construction equipment, a job shack and other
items associated with utility construction. All construction material will be
removed and the site reseeded at the end of construction. The staging area will
be in operation from April 2005 through November 2005.
Date of Permit Issuance: April 4, 2005
Date of Expiration: November 30, 2005
Conditions of Approval:
1. None
Approved by the City of Renton
Development Services Division Director
04£:,1 LI, 2{)o5
Date: April 4, 2005
Appeals: Appeals of permit issuance must be filed in writing by April 18, 2005
together with the required $75.00 application fee to the City of Renton Hearing
Examiner, City of Renton, 1055 South Grady Way, Renton, WA 98055.
Appeals to the Examiner are governed by City of Renton Municipal Code
Section 4-8-110. Additional information regarding the appeal process may be
obtained from the Renton City Clerk's Office, (425) 430-6510.
City of Renton Department of Planning / Building / Public liVorks
ENVIRONMENTAL & DEVELOPMENT APPLICATION REVIEW SHEET
SUMMARY OF PROPOSAL: The proposal is to use a 3 parcel site as a staging area for use
Sewer Interceptor Phase II project. The site will be used to store pipe, manhole sections, b'~'~~:!:~I"~I~r~~~~ 7'1)'ljjiSt'm.:fi a job shack and other items normally associated with utility construction. All construction IT removed and site resee(ted
at the end of construction. The staging area will be in operation from April 2005 through November 2005.
A. ENVIRONMENTAL IMPACT (e.g. Non-Code) COMMENTS
Element of the Probable Probable More Element of the Probable Probable More
Environment Minor Major Information
Impacts Impacts Necessary Environment Minor Major Information Impacts Impacts Necessary
Earth Housin
Air Aesthetics
Water Li htlG/are
Plants Recreation
Land/Shoreline Use Utilities
Animals Transportation
Environmental Health Public Services
Energyl Historic/Cultural
Natural Resources Preservation
Airport Environment
10,000 Feet
14000 Feet
B. POLICY-RELATED COMMENTS
C. CODE-RELATED COMMENTS
We have reviewed this application with particular attention to those areas in which we have expertise and have identified areBS of probable impact or
areas where additional information is needed to properly assess this proposal.
~!?IJA
Signature of Director or Authorized Representative Date 7
City of Renton Department 01 Planning / Building / Public Works
ENVIRONMENTAL & DEVELOPMENT APPLICATION REVIEW SHEET
REVIEWING DEPARTMENT: p. COMMENTS DUE: MARCH 30, 2005
APPLICATION NO: LUA05-029, TP • DATE CIRCULATED: MARCH 16,2005
APPLICANT: John Hobson, City of Renton PROJECT MANAGER: Jill Hall
..... -PROJECT TITLE: Sunset Sewer Temp StoraQe Permit PLAN REVIEW: Kayren Kittrick /f«fi=ol • _. ,~/El)
SITE AREA: 39,225 square feet BUILDING AREA (Qross): NJA
LOCATION: 701 Sunset Blvd NE I WORK ORDER NO: 77396 "'Ate J Ii ZOOS
SUMMARY OF PROPOSAL: The proposal is to use a 3 parcel site as a staging area for use during the construction of thS?\D'n9!i RENTON
Sewer Interceptor Phase II project The site will be used to store pipe, manhole sections, backfill aggregates, constructio~rplfi~/lfFEMS
a job shack and other items normally associated with utility construction. All construction material will be removed and site reseeded
at the end of construction, The staging area will be in operation from April 2005 through November 2005,
A. ENVIRONMENTAL IMPACT (e.g. Non-Code) COMMENTS
Element of the Probable Probable More Element of the Probable Probable More Environment Minor Major Information
Impacts Impacts Necessary Environment Minor Major Information
Impacts Impacts Necessary
Earth
Air
Water
Plants
.~
Land/Shoreline Use tilities
Animals
Environmental Health 'ublic SeMces
Energyl
Natural Resources
A~f.¥,~~et
B. POLICY-RELATED COMMENTS
C. CODE-RELATED COMMENTS
We have reviewed this application with particular attention to those areas in which we have expertise and have identified areas of probable impact or
here addition ;n~ rmatio ed properly a sess this proposal. 3/22If/5
Date
City of Re ... an Department of Planning I Building I Public ~.~,ks
ENVIRONMENTAL & DEVELOPMENT APPLICATION REVIEW SHEET
REVIEWING DEPARTMENT: Co: ~ LlDhcY'\ COMMENTS DUE: MARCH 30, 2005
APPLICATION NO: LUA05-029, TP DATE CIRCULATED: MARCH 16, 2005
APPLICANT: John Hobson, City of Renton PROJECT MANAGER: Jill Hall
PROJECT TITLE: Sunset Sewer Temp Storage Permit PLAN REVIEW: Kayren Kittrick
SITE AREA: 39,225 square feet BUILDING AREA (gross): N/A
LOCATION: 701 Sunset Blvd NE WORK ORDER NO: 77396
V/IL SUMMARY OF PROPOSAL: The proposal is to use a 3 parcel site as a staging area for use during the construction ofJl\e. Sunset
Sewer Interceptor Phase II project. The site will be used to store pipe, manhole sections, backfill aggregates, constructi6h"~quipment,
a job shack and other items normally associated with utility construction. All construction material will be removed and site reseeded
at the end of construction. The staging area will be in operation from April 2005 through November 2005.
A. ENVIRONMENTAL IMPACT (e.g_ Non-Code) COMMENTS
Element of the Probable Probable More Element of the Probable Probable More
Environment Minor Major Informat/on Environment Minor Major Information Impacts Impacts Necessary Impacts Impacts Necessary
Earth
Air
Water
Plants
Land/Shoreline Use titities
Animals
Environmental Health
Energy/
'If!lff!.Services
Natural Resources
~:~:~~~"~,
B. POLICY-RELA TED COMMENTS
C. CODE-RELA TED COMMENTS
We have reviewed this application with particular attention to those areas in which we have expertise and have identified BreBS of probable impact or
areas where dWonal information is needed to properly assess this proposal.
Si Date
City of Renton Department of Planning / Building / Public works
ENVIRONMENTAL & DEVELOPMENT APPLICATION REVIEW SHEET
REVIEWING DEPARTMENT: Po.r-k:..-c:, COMMENTS DUE: MARCH 30, 2005
APPLICATION NO: LUA05-029, TP DATE CIRCULATED: MARCH 16, 2005
APPLICANT: John Hobson, City of Renton PROJECT MANAGER: Jill Hall
PROJECT TITLE: Sunset Sewer Temp StoraQe Permit PLAN REVIEW: Kayren Kittrick
SITE AREA: 39,225 square feet BUILDING AREA (Qross): N/A
LOCATION: 701 Sunset Blvd NE I WORK ORDER NO: 77396
SUMMARY OF PROPOSAL: The proposal is to use a 3 parcel site as a staging area for use during the construction of the Sunset
Sewer Interceptor Phase II project. The site will be used to store pipe, manhole sections, backfill aggregates, construction equipment,
a job shack and other items normally associated with utility construction. All construction material will be removed and site reseeded
at the end of construction. The staging area will be in operation from April 2005 through November 2005.
A. ENVIRONMENTAL IMPACT (e.g. Non-Code) COMMENTS
Element of the Probable Probable More Element of the Probable Probable More
Environment Minor Major Information
Impacts Impacts Necessary
Environment Minor Major Information
Impacts Impacts Necessary
Earth Housing
Air Aesthetics
Water Light/Glare
Plants Recreation
LancVShoreline Use Utilities
Animals Transportation
Environmental Health Public Services
Energy/ Historic/Cultural
Natura! Resources Preservation
Airport Environment
10,000 Feet
14,000 Feet
B, POLICY-RELA TED COMMENTS
C. CODE-RELATED COMMENTS
We have reviewed this application with particular aNention to those areas in which we have expertise and have identified areas of probable impact or
areas where itiona.1 informati eded to properly assess this proposal,
City of Renton Department of Planning / Building / Public livurks
ENVIRONMENTAL & DEVELOPMENT APPLICATION REVIEW SHEET
REVIEWING DEPARTMENT: PltU\ ~ev'ipA I \ COMMENTS DUE: MARCH 30, 2005
APPLICATION NO: LUA05-029, TP DATE CIRCULATED: MARCH 16, 2005 ~ 0
APPLICANT: John Hobson, City of Renton PROJECT MANAGER: Jill Hall
PROJECT TITLE: Sunset Sewer Temp Storage Pennit PLAN REVIEW: Kayren Kittrick hlA",. -, V . • #~(I 4..: ;)
SITE AREA: 39,225 square feet BUILDING AREA (gross): NlA
LOCATION: 701 Sunset Blvd NE WORK ORDER NO: 77396
SUMMARY OF PROPOSAL: The proposal is to use a 3 parcel site as a staging area for use during the construction ~;y~~ Sunset
Sewer Interceptor Phase II project. The site will be used to store pipe, manhole sections, backfill aggregates, construction eqUipment,
a job shack and other items normally associated with utility construction. All construction material will be removed and site reseeded
at the end of construction. The staging area will be in operation from April 2005 through November 2005.
A. ENVIRONMENTAL IMPACT (e.g. Non-Code) COMMENTS
Element of the Probable Probable More Element of the Probable Probable More Environment Minor Major Information
Impacts Impacts Necessary Environment Minor Major Information Impacts Impacts Necessary
Earth
Air
Water
Plants ~
Land/Shoreline Use
Animals
Environmental Health 'ubfie SelViees
Energy/ ,
Natural Resources
Al~n: :~:~F~~t
B. POLICY-RELATED COMMENTS
C. CODE-RELA TED COMMENTS
tJ~
We have reviewed this application with particular attention to those areas in which we have expertise and have identified areas of probable impact or
areas where additional information is needed to properly assess this proposal.
Date \
City of Renton Department of Planning I Building I Public ~vorks
ENVIRONMENTAL & DEVELOPMENT APPLICATION REVIEW SHEET
REVIEWING DEPARTMENT: fi rt.-rvI ,1.1'" \ -J !; Ir' \ p " COMMENTS DUE: AR.Cit~30" 2005 ~7 \' r:" .!,' ,~l
fM!~' -
! J III APPLICATION NO: LUA05-029, TP DATE CIRCULATED:' AR H16,2005
APPLICANT: John Hobson, City of Renton PROJECT MANAGE~jJJiiIIHall MAR 1 6 ?nm: II ! II
PROJECT TITLE: Sunset Sewer Temp Storage Permit PLAN REVIEW: Kav en Kitbck :---' i ,
SITE AREA: 39,225 square feet BUILDING AREA (ar ss): N/A .. q} fY Or: REfnO,'J 1-., ... f"1 •. ,. , __ . I
I WORK ORDER NO: 77396
.. .. "",.:,'.! I LOCATION: 701 Sunset Blvd NE
SUMMARY OF PROPOSAL: The proposal is to use a 3 parcel site as a staging area for use during the construction of the Sunset
Sewer Interceptor Phase II project. The site will be used to store pipe, manhole sections, backfill aggregates, construction eqUipment,
a job shack and other items normally associated with utility construction. All construction material will be removed and site reseeded
at the end of construction. The staging area will be in operation from April 2005 through November 2005.
A. ENVIRONMENTAL IMPACT (e.g. Non-Code) COMMENTS
Element of tho Probable Probable More Element of the Probable Probable More
Environment Minor Major Information
Impacts Impacts Necessary
Environment Minor Major Information
Impacts Impacts Necessary
Earth Housina
M Aesthetics
Wat., Li.ahtIGlare
'Iants Recreation
~ Utilities
Trans rtation
Public Services
~~~~rz: p.
Historic/Cu/tural
Preservation
Airporl Environment
10,000 Feat
14,000 Feet
B. POLICY-RELATED COMMENTS
C. CODE-RELATED COMMENTS
We have reviewed this plication with p icu/ar attention to those areas in which we have expertise and have identified areas of probable impact or
a'eas where additional in . nnation is nee J. to properly,:-sess this proposal. 3ft & /0 {
Signature of Director r thorized Representaf e Date r I
City of Renton Department of Planning! Building! Public Works
ENVIRONMENTAL & DEVELOPMENT APPLICATION REVIEW SHEET
REVIEWING DEPARTMENT: T ro.t\c;Do(-Iruh'rl1'l COMMENTS DUE: MARCH 30, 2005
APPLICATION NO: LUA05-029, TP DATE CIRCULATED: MARCH 16,2005
APPLICANT: John Hobson, City of Renton PROJECT MANAGER: Jill Hall
PROJECT TITLE: Sunset Sewer Temo Storaoe Permit PLAN REVIEW: Kayren Kittrick
SITE AREA: 39,225 souare feet BUILDING AREA (oross): N/A
LOCATION: 701 Sunset Blvd NE I WORK ORDER NO: 77396
SUMMARY OF PROPOSAL: The proposal is to use a 3 parcel site as a staging area for use during the construction of the Sunset
Sewer Interceptor Phase II project. The site will be used to store pipe, manhole sections, backfill aggregates, construction equipment,
a job shack and other items normally associated with utility construction. All construction material will be removed and site reseeded
at the end of construction. The staging area will be in operation from April 2005 through November 2005.
A. ENVIRONMENTAL IMPACT (e.g. Non-Code) COMMENTS
Element of the Probable Probable More Element of the Probable Probable More
Environment Minor Major Information Environment Minor Major Information
Impacts Impacts Necessary Impacts Impacts Necessary
Earth Housi
Air Aesthetics
Water Li htlG/are
Plants Recreation
Land/Shoreline Use Utilities
Animals Trans(JOrtation
Environmental Health Public SeNices
Energy/ Historic/Cu/tural
Natural Resources PreselVation
Airport Environment
10,000 Feet
14000 Feet
B. POLICY-RELATED COMMENTS
\\.J(i'ht.
C. CODE-RELATED COMMENTS
We have reviewed this application with particular attention to those areas in which we have expertise and have identified areas of probable impact or
31~
a,eas where additional ·nformation is needed to properly assess this proposal. I I ~
Date (
City of Renton Department of Planning / Building / Public ,vorks
ENVIRONMENTAL & DEVELOPMENT APPLICATION REVIEW SHEET
REVIEWING DEPARTMENT: SU.r-faftJ" IlHlD •• yJpy ,
APPLICATION NO: LUA05-029, TP
APPLICANT: John Hobson, City of Renton
PROJECT TITLE: Sunset Sewer Temp Storage Permit
SITE AREA: 39,225 sguare feet
LOCATION: 701 Sunset Blvd NE
COMMENTS DUE: MARCH 30, 2005
DATE CIRCULATED: MARCH 16, 2005
PROJECT MANAGER: Jill Hall
PLAN REVIEW: Kayren Kittrick
BUILDING AREA (gross): N/A
WORK ORDER NO: 77396
be '7/7:" ('.
'v. SUMMARY OF PROPOSAL: The proposal is to use a 3 parcel site as a staging area for use during the construction of the'S'unset
Sewer Interceptor Phase II project. The site will be used to store pipe, manhole sections, backfill aggregates, construction equfpment,
a job shack and other items normally associated with utility construction. All construction material will be removed and site reseeded
at the end of construction. The staging area will be in operation from April 2005 through November 2005.
A. ENVIRONMENTAL IMPACT (e.g. Non-Code) COMMENTS
Element of the Probable Probable More Environment Minor Major Information
Impacts Impacts Necessary
Earth
Ai,
=i
;v~~'il!';
B. POLICY-RELATED COMMENTS
IIJfI'I1/
C. CODE-RELATED COMMENTS
M(}N
Element of the
Environment
Probable
Minor
Impacts
Probable Major
Impacts
MOl"" Information Necessary
We have reviewed this application with particular attention to those areas in which we have expertise and have identified areas of probable impact or
areas where additional information is needed to properly assess this proposal.
NOTICE OF APPLICATION
A Master Application has been flied and accepted with the Development Services Division of the City of Renton.
The following briefly describes the application and the necessary Public Approvals.
PROJECT NAME/NUMBER: Sunsat Sewer Temporary Storage Permit I LUA05-029, TP
PROJECT DESCRIPTION: The proposal is to use a 3 parcel site as a staging area for use during the
construction of the Sunset Sewer Interceptor Phase II project. The site will be used to store pipe, manhole sections,
backfill aggregates, construction equipment, a job shack and other items normally associated with utility construction. All
construction material will be removed and site reseeded at the end of construction. The staging area will be in operation
from April 2005 through November 2005.
PROJECT LOCATION: 701 Sunset Blvd NE
PUBLIC APPROVALS: Administrative Temporary Use Permit
APPLICANT/PROJECT CONTACT PERSON: John Hobson, City 01 Renton; Tel: (425) 430·7279
Eml: jhobson@ci.renton.wa.us
Comments on the above application must be submitted in writing to Jill Hall, Associate Planner, Development Services
Division, 1055 South Grady Way, Renton, WA 98055, by 5:00 PM on March 30, 2005. If you have questions about this
proposal, or wish to be made a party of record and receive additional notification by mail, contact the Project Manager at
(425) 430·7219. Anyone who submits written comments will automatically become a party of record and will be notified of
any decision on this project.
PLEASE INCLUDE THE PROJECT NUMBER WHEN CALLING FOR PROPER FILE IDENTIFICATION
DATE OF APPLICATION:
NOTICE OF COMPLETE APPLICATION:
DATE OF NOTICE OF APPLICATION:
\
March 11, 2005
March 16, 2005
March 16, 2005
If you would like to be made a party of record to receive further information on this proposed project, complete this form
and return to: City of Renton, Development Planning, 1055 South Grady Way, Renton, WA 98055.
File Name / No.: Sunset Sewer Temporary Storage Permit / LUA05·029, TP
NAME: ______________________________________________________________ __
MAILING ADDRESS: _______________________________ _
TELEPHONE NO.: ______________ _
A M .. ter Application lin been filed and a~c.pltd wltllthe o.nlopm.nt S.rvl ... , Olvilion olth. City 01 Ranton.
Til. lollowlng brl.tly d .... rlb •• th. appll~atton and the n_ .. ary Publl .. Approvel •.
PROJECT NAME/NUMBER, Sunl'lt Sewer Tempor.ry Stor9ge Permrt I LUA05·029. TP
PROJECT DESCRIPTION; The propotlal Is to ute a 3 parcel ,lIe at a Slaging area tor lISe durioQ Iha
COrls\ru~tion 01 the Sunset Sewer Interceptor Phase II project. The slta will be used 10 slore ptpe, manhole sections,
ba~k!1II alXlr&ljatal, COrlltructkm equipment, a job shack and olher items normally anoclated with utility CDrlItruction. All
CDrlstructkK! matenal will be remov&d and sne rHeeded at the end 01 construction. The staging ar&l'l will be In operation
from April 2005 through November 2005.
PROJECT LOCATION: 70t Sunset 8lvd NE
PUBLIC APPROVALS: Adminlstmtivo Tempomry Un Permit
APPUCANTIPROJECT CONTACT PERSON: JaM Hobson, City of Renton: Tal: (425) 430-7279
Eml: jhobsonOcl.rootOll.wa.us
Comments on 111& above appllcallon must be lubm~led In writinG \0 J1I1 HslI, Associate Planner, Oavelopment Services Division, '055 South Grady Way, Renton, WA 98055, by 5:00 PM 00 March 30, 2005. It you hllve qU8$IIDrlI about th"
lI'opollal. or w~h to be made II party 01 record and receive additional notillcation by mall, contact the Projeel MfmlGer at
(425) 430-7219, Anyoo& who ,ubm~ written commonts will automatically bacoma a party 01 ,,,cord and will ba not~lod ot
any deeJaIon Drlthil PfOJiCl.
PLEASE INCLUDE THE PROJECT NUMBER WHEN CALLING FOR PROPER FILE IDENTIFICATION
DATE OF APPLICATION:
NOTICE OF COMPLETE APPLJCATION:
DATE OF NOTICE OF APPLICATION:
Mllrch 11, 2005
Mllrch 16, 2005
March 16, 2005
11 you would like to be made a par1y 01 racord to racelva lur1her inlormaHon on thla proposed prolBCt, complete thilliorm
and return to: City 01 Renton, Development PlanninG, 1055 South Gredy Way, Renton, WA 98055.
File Name I No.: Sunset Sewer TemllQrary Storage Ponnlll LUAOs..029. TP
NAME:
MAILING ADDRESS
TELEPHONE NO.:
CERTIFICA TION
I, OeM J(J~ , hereby certify that .J copies of the above document
were posted by me in _3_ conspicuous places or nearby the described property on
DATE: '3.-1(; -OS SIGNED: ~ rR ~ ?
ubscribed and sworn before me, a Notary Public, in andjQrJh~..,Sfa,t.e ofWashinglon.re·idin4<'-~ tr r:,,-a,:~~~~, on lhe ,-X 01J! day of '--72JMd?A ~. -.u:::'&'L<~r".-.,~~~~fL -
NOTARY P Ie SIGNATURE:
MARILYN KAMCHEFF
MY APPOINTMENT EXPIRf!! Mm,"'
I
LIST OF SURROUNDING\l7W~~~~~~'NG
PROPERTY OWNERS
WITHIN 300-FEET OF THE SUBJECT SITE
City of Renton Development Services Division
1055 South Grady Way, Renton, WA 98055
Phone: 425-430-7200 Fax: 425-430-7231
MAR I I 200
RECEIVED
PROJECT NAME: S"''''{:,i?T SEWER. INrEl-;'C€!>,,,,R P .. r.t: G,~';"'~.:l~nc.J -Sr"\i,'NC=. A~-a..
APPLICATION NO: LUf\Cf)-D2q
The following is a list of property owners within 300 feet of the subject site. The Development Services
Division will notify these individuals of the proposed development.
NAME ADDRESS
Q:\ WEBIPW\DEVSERV\FonnslPlanning\owners.docOSI29/03
ASSESSOR'S PARCEL
NUMBER
...
(Attach additional sheets, if necessary)
NAME ADDRESS
Applicant Certification
,
ASSESSOR'S PARCEL
NUMBER
I, '> \PHt-! Ho ~Sco J , hereby certify that the above list(s) of adjacent property
(Print Name)
owners and their addresses were obtained from:
Title Company Records
~King County Assessors Records
Signedl_--"::~~~~~_____ Date "3 /4 los:
(Applicant) , I
NOTARY
ATTEST~::d swom before me, a Nota~ubIiC, in and for the State of Washington, '.
residing at~ , on the day of m% a::s= .1 ,20~ n P o ~"""'\'" : ...... J P "
Sign ~ , --~~~co.~,.: .... ~s-(''''' (N~tl.ryPubllc) I~~ ~ ,-\P\<\'~N fJ..«I.·~;..","'\ON".t;, .. "';t_II,
ATTEST: S.IIbscribed and swom befor~ a Notary Public, in ~nCHo:!e State of Washi!1Qton residing 0~ -:~n~e~ifl-daYOf=221~ ,20.a:;:
SiQnetr?.?7 cUriI-IT M-J 1/' '//?]A
-v
~~ARIL YN KAMCHEFF
Q:\WEB\PwtDEVS~~JrWJll~.?~C".dOC 2
I ~ ..
311990016504 186495010008 722750006008
ARROYO ALMA A BALYEAT CHRISTINE BANDA EMILIO R
848 SUNSET BL NE 321 HARRINGTON CT SE 9708 S 244TH PL
RENTON W A98056 RENTON W A98056 KENT W A98031
813790028001 186495011006 813790030007 BARBER WILUAM C BARKER JOHN I3ARTOLOME REIlECCA SR+GARBARENO GA YLE L 821 SUNSET BL D 3 901 SUNSET BV NE #C 309 901 SUNSET BL NE #C211
RENTON W A98056 RENTON W A98056 RENTON WA98056
813790032003 186495018001 722750003005
BEST LYNDA BIIlANCO DENNIS A+WIVINA R IlLANSFIELD STEPHEN M
901 SUNSET BL NE #C311 821 SUNSET ilL NE F3 711 AI3ERDEEN A V NE
RENTON W A98056 RENTON W A98056 RENTON W A98056
722750006503 722750002502 813790037002
CAMERER JOHN M CANUL NELSON M+YAEGGY LESDlA CARLSON RICHARD L+MAILE TRA
861 ABERDEEN AV NE 707 AI3ERDEEN A V NE 901 SUNSET BLVD NE D212
RENTON WA98056 RENTON W A98056 RENTON WA98056
813790004002 -j"Su·fH(.iw{-Aelclrt$ 813790012005 813790043000
CARTER ANNIE MAE 'FQ"bI~ CAVEN THOMAS L CHANDLER SCOTT A
2101 SW SUNSET BL ~O') 901 SUNSET BL #A 304 901 SUNSET BL NE #D 314
RENTON WA98055 RENTON WA98056 RENTON W A98056
722750005505 722750003500 813790014001
CHASE GARY E CHRISTENSEN RACHEL L CONIFF COLLEEN V
853 AIlERDEEN NE 815 ABERDEEN AV NE 901 SUNSET BL NE #B-106
RENTON W A98055 RENTON W A98056 RENTON W A98056
186495008002 31199002000 I 722750128000
CORNICK DAVID J+VANTANA P CORREA KENT & CYNTHIA R CRAIG MATTHEW A
821 SUNSET BL NE #c-j 670 SUNSET BL NE 2029 NE 7TH ST
RENTON W A98056 RENTON W A98056 RENTON W A98056
813790034009-ill S~~(;li,,* adLm-z 813790040006 722750129503
CUMMINGS SEAN P E ~~ .. DONCKERS MADELINE DUBUQUE RICHARD G +
KRISTA DARBY DUBUQUE 901 SUNSET BL NE #D 3\v\(!6 901 SUNSET BLVD NE D-215 2101 NE 6TH PL RENTON W A98056 RENTON WA98056 RENTON WA
722750004508 722750127507 722750001009
ENDRESMR FORGAARDWL FORGAARD WENDELL L
823 AI3ERDEEN A V NE 678 SUNSET BL NE 678 SUNSET BL NE
RENTON W A98056 RENTON WA98056 RENTON W A98056
722750004003 813790029009 186495015007
GALT CHERYL GAL V AN FERNANDO A GOETZINGER CHRISTINE M
12628 SE 169TH PL 901 SUNSET BLVD NE #C-308 821 SUNSET BL NE #E-4
RENTON W A98058 RENTON W A98056 RENTON W A98056
813790033001
GROOM DAVID & CHERYL
11631 SE 229TH PL
KENT W A98031
186495013002
HAMILTON SUSAN E
821 SUNSET BL NE #E-2
RENTON W A98056
311990018005 &311990018104
HESTING ROBERT W
812 SUNSET BL NE
RENTON W A98055
813790005009
HOUGHTON HARRIET A
901 SUNSET BL NE #A201
RENTON W A98056
186495003003
JOHNSON BRIAN+KRISTEN
821 SUNSET BL NE #B2
RENTON WA98055
722750000506
JOSEPH EZRA
6016 S ROXBURY
SEATTLE WA98118
311990016801
KALMBACH JOHN A+WENDY L
15508 206TH A V NE
RENTON WA98059
813 790031 005
KREIN KEVIN J
901 SUNSET BL NE #C310
RENTON W A98056
186495004001
LENKOV VLADIMIR+VALENTINA
821 SUNSET BLVD NE #B3
RENTON W A98055
I
813790010009
GRUNERT STEVE A
901 SUNSET BL NE #A302
RENTON WA98056
186495001007
HARBIN JANICE
821 SUNSETBLNE#AI
RENTON WA98056
186495005008
HOWARD SCOTT D+BRITrANY A
821 NE SUNSET BLVD B4
RENTON W A98056
186495016005
JONES SALLY A+LEWIS HUGH
821 SUNSETBVNE#F I
RENTON W A98056
813790006007
JUMP TIMOTHY R
90 I SUNSET BL NE A 202
RENTON WA98056
186495009000
KEIM ANDREW F
821 SUNSET BL NE #D I
RENTON WA98056
813790020008
KROMER MARDELL L
90 I SUNSET BL #B307
RENTON W A98056
722750130006
LI QI AN
2105 NE 6TH PL
RENTON W A98056
311990017502
GUTKA JAYT
844 SUNSET BL NE
RENTON W A98056
813 790026005
HESKE'H NOEL K
901 SUNSET BL #C209
RENTON W A98056
722750129008
HILL CLARENCE E
7817 S 134TH ST
SEATTLE WA98178
813790023002
JARVIS TRUDY G
901 SUNSET BL #CI IO
RENTON W A98056
813790041004
JONES SHARON KAY LEPAGE
901 SUNSET BL NE #D312
RENTON W A98056
311990000508&311990001001 &
311990001100
KALASOUNTASGEORGEP
9563 MALBIS LN
DAPHNE AL36526
311990002009
KALASOUNTAS JULIETIE CELEST
717 SUNSET BL NE
RENTON W A98056
813790008003
KIMHAE SOOK
901 SUNSET BL NORTHEAST A204
RENTON W A98056
81379000900 1-~pkdru:t
LANE BRIAN K Kk\~')
90 I SUNSET BL NE ~2l+I<s
RENTON W A98056
813790007005
MAGER ELEONORA S
901 SUNSET BL NE #A203
RENTON W A98056
722750001504
MARTINEZ ALEJANDRO
MARTINEZ LETICIA2102 NE 7TH ST
RENTON WA
722750128505
MOORE CYNTHIA J
2033 NE 7TH ST
RENTON W A98056
813790011007
PAPPAS LONNIE SCOTT
901 SUNSET BL NE #A-303
RENTON W A98056
605650010008 & 605650040005
PUGET SOUND ENERGY/ELEC
PROPERTY TAX DEPTPO BOX 90868
BELLEVUE W A 98009
813790021006
RICHARDSON EIKO+ROBERT W
94-768 LUMIAUAU
WAIPAHU HI96797
813790019000
SHODA DARREN A
901 SUNSET BL NE #B-306
RENTON W A98056
813790027003
SMITH LEW
14305 LYLE POINT RD
ANDERSON ISLAND W A98303
813790016006
STEVENSON KAREN M
901 SUNSET BL NE #B-205
RENTON W A98056
813790017004
TATAREK PATRICIA
901 SUNSET BL NE #B206
RENTON W A98056
311990017007
VUONG JIMMY D
4878 BEACON A V S
SEATTLE WA98108
I
186495017003
MCCALLUM DA VlD+BETrE
821 SUNSET BV NE #F-2 BLV
RENTON W A98056
813 790022004
MURATAAKIO
633 S RADBURY PL
DIAMOND BAR CA91765
311990003502
POOL BROTHERS CONSTRUCTION
POBOX 3023
RENTON W A98056
813790039008
SANCHEZ LUTGARDA A
901 SUNSET BL NE #D-214
RENTON W A98056
813 790002006
SMALLS TONY E
901 SUNSET BL NE #A-I02
RENTON W A98056
186495007004
SPEKTOR YEFIM+SOFY A
821 SUNSET BL NE
RENTON W A98058
186495002005
STUBBINS MARSHAL L
821 SUNSET BL NE #B-I
RENTON W A98055
813790003004
TRUONG PHI MINH
90 I SUNSET BL NE A I 03
RENTON W A98006
813790001008
WALKER ANGELA LEE
90 I SUNSET BL NE #A 10 I
RENTON WA98056
813790036004
MENESES OSCAR
901 SUNSET BL NE #D 115
RENTON W A98056
813790015008
NIELSEN JANET C
901 SUNSET BL NE #13-107
RENTON W A98056
722750002007
PREI'OTENTE ARTURO 0
JR+LEILANIE L
2106 NE 7TH ST
RENTON W A98056
186495006006
REECE KELLI M
821 SUNSET BL NE #C-I
RENTON W A98056
813790025007
SEBASTIAN ELLYN L
90 I SUNSET BL NE #C208
RENTON WA98056
813790018002
SMITH ALVIN H+IRENE D
90 I SUNSET BL NE #B-207
RENTON W A98056
813790024000
STEVENS JOSEPH
3497 S WATERFALL DR
GREEN VALLEY AZ85614
311990018500
SWEET TERRY
714 SUNSETNE
RENTON W A98056
813790038000
VEATURALSORAPONG
901 SUNSET BLVD #D213
RENTON W A98056
186495014000
WALLACE ELIZABETH L
821 SUNSET BL NE UNIT E-3
RENTON WA98056
.'
813790013003
WILLIAMS MOLLIE
901 SUNSET BL NE #B-I 05
RENTON W A98056
186495012004-~ln~t:n~
ZHAO-FAN rOON 3\221os-
821 SUNSET BL NE #E-I
RENTON W A98056
I
722750005000
WRIGHT-ALLEY BEVERL Y
851 ABERDEEN A V NE
RENTON W A98056
813790042002
YAMADA KOJI
901 SUNSET BL NE #0-313
RENTON W A9~05G
CITY )F RENTON .~~
Kathy Keolk~r-Wheeler, Mayor
PlanningIBuildingfPublicWorks Department
Gregg Zimmerman P.E., Administrator
March 16, 2005
John Hobson
City of Renton
1055 S GradyWay
Renton, WA 98055·
Subject: Sunset Sewer Temporary Storage Permit
LUA-05-029, TP
Dear Mr. Hobson:
The Development Planning Section of the City of Renton has determined that the
subject application is complete according to submittal requirements and, therefore, is
accepted for review.
You will be notified if any additional information is required to continue processing your
application.
Please contact me at (425) 430-7219 if you have any questions.
Sincerely,
t/v--IM
/Jill Hall .
Associate Planner
cc: George Kalasountas / Owner
------------~IO~5~5~S-ou~t~h~G-ra~d-y~W~a-y--R~e-n~to-n-,W~as~h7in-g~to-n~9~8~0755~-----------.~ * This paper contains 50% recycled material, 30% post consumer AIIEAD OF THE CURVE
03/11/2005 06:53 FAX ~003
141 uU3
City of Renton
LAND USE PERMIT
MASTER APPLICATION
PROPERTY OWNER(S)
.
NAME: ~EoRG.," KAl.ASc>V"'4"""'A\~
ADORESS: ql!S~~ """'I.e., ~ 4J
CllY: "b4~lt-IS' • Aa.:.. ZIP: .3"" S Z. "'"
TEL£PHOHE HUMBER: Z:S I -{p'Z.~-,'O~I
APPLICANT (If other than awner) .. ~ .
NAMI!: -J ... ~o..1 H~B.s.o,J .
COMPANY (if applk:ll""'):
Beu-ro,.l ellT"( "'F
ADORESS: IDSS S, b.I'Ab'i WA~
C'lY:R~tJ WA. ZIP: 9$o5;S"
TELEPHONE NUMBER
4e.6'-+~O-'(..7q
CONTACT PERSON
NAME; ,jO\\M ~.J
COMPANY or applicable): c::.\ T"'( t>F ~T(),J.
ADDRESS: \ 0 55 <'5. 4J!Ab'i \.:-lAy
CITY: ~~....t I.JA ZIP: 4t30SS
r
'~PHON& NUMBER Atfll E~AlLADDRESS: ~ -+~-'z..7'1
J"..b..,. .... &l e i .re" .... '" ""~. v 50
~~~~'"
PROJECT INFORMATION potto
PROJECT OR DEVELoPMENT NAME: • ..., S"'~sr &~ I~ ~ ...
C."US.:t1otoJ.. ..-....1 . I ut::.. .I\. REA.
PROJECTNloDORES8($)o1..0CATlON AND ZIP CODE:
.7q\ SuoJs;.::T LUll> Ne-
~ • \..IA Qe,,5S"
KING COUNTY ASSESSOR'S ACCOUNT N'UMBER(S):
'301 I '1",0 IC"'~
311 '1ct 0 £> .. , 0
~"qqo~o, I
PROPOSED LAND USE(S): "TirMPo~~~
c-...~VGr"I 0"" ~I'" Go. ..L..:o.
EXImNG COMPREHENSIVE PLAN MAP DESIGNATION:
Rot'.I1L)L'rI·P .... "'IL" It.lFII.,L
PROPOSED CONPREHENSIIIE PLAN MAP DESIGNATION I
(llOIPPIbttIe): ~/4
EXISTING ZONING: FeM-F
SOUAREFOOTAGEOFROAOWAYSTOBEDfDICATED
FOR SUBOIIIISIONS OR PRIVATE STREETS SERVING
THRE" LOTS OR MORE (If appUcab!e): I.l/"
PROPOSED RESlDEHllAL DeNSITY IN UNll'S PER NET
ACRE or applicable): fll A'
NUMBER OF PROPOSED LOTS or 1!IlDfiCIb1e): I toJA.
NUMBER OF NeW DWEU,INO UNITS (~ apl'ftlable): "'/ A
03/11/2005 06:54 FAX
NUMIlER OF EXISTING DWELLING UNITS (W I!lP~I'ePbkl)'
t-J, 14.
SQUARS FOOTAGE OF PROPOSED RESIDENTIAl
. .DINGS (If appljc:abla); i.J /1>.
"'SQUARE FOOTAGe OP EXISTING RESIDENllAL
BUIlDINGS TO REMAl-,,, (of ~l: ~I A.
SQUARE FOOTAGE OF PROPOS~D NON·RESIDENTIAL
BUILDINGS (If appBCOble): IoI-LA
SQUARE FOOTAGE OF EXISTING NotHU:SIOENllAL
BUILOINGS TO REMAIN or~0); LJ fA
NET flOOR AREA OF NON-RESIDENTIAl. BUIWING8 (If
oppUcabl\!): ~1~
NUMBER OF EMPLOYEES TO Be EMPLOVEO av THE
NEW PROJECT Of oppIIerablo): '" J A
~004
.' PROJECT VALUE: . $1 £:I,IDeO
16 THE SITE LOCATED IN ANV TYPE OF
. ENVIRONMENTAU. Y CRITICAL. AREA. PLEASE INCLUDE
SQUARE FOOTAGE (lfllppUcable); ~cwe;:
Q AQUIFER PROTEOTION MEA ONe
Q AQUIFER PROTECTION AREA 1WO
Q FLOOD HAZARD AREA
Q GEOLOGIC HAZARD
a HABITAT CONSERVATION
til SHOREUNl! STREAMS AND LAKliS
Q WE1\ANDS
___ oq.a
___ 011.11.
---nq.Q.
___ oq,1I.
___ Ilq.ft.
SITUATE IN ll-IE Me' QUARTER OF SECTION ~ TOWNSHIP 'Z3, RANGE 5. IN THE erN
OF RENTON, KING couNtY, WASHINGTON.
List an land usa applications being applise! for:
1. 3. _____ _
---'------4. ____ _
Steff Will calculate appllo4hble fees and postage: $
AFfODAVBT OF OWNERSHIP
t> ________ ....,... __ _
f\IoIQryP\l!lllcI~cnd foI'".,81atoal'lOI'a' alP ~ I!.t;l ~ 6 j>;) ~
": ' ...... .
-NalDJII (PrInt)
Dev cLOPMf:NT PLANNING CITY OF RENTON
ABATEMENT AGREEMENT
TEMPORARY USE
City of Renton Development Services Division
1055 South Grady Way, Renton, WA 98055
Phone: 425-430-7200 Fax: 425-430-7231
MAR t t 2005
RECEIVED
I, __ -J",=,-",D:.LH:l.·",Ni-.ll-d1tf)::JIS"""s.t:"",,; ,"'JL-________ being the Applicant for the Temporary Use
Permit at the location of:
hereby authorize the City of Renton to summarily eliminate the Temporary Use and all evidence of the use if
. it has not been removed as required by the terms of the permit. I also agree to reimburse the City for any
expense incurred in ab 'ng th/,mpOrary Use,
Signature: /'L-
Print Name:
Date:
I I
STATE OF WASHINGTON )
ISS
COUNTY OF KING )
I certify that I know or have satisfactory evidence that <...-\c \-.I. w w. <J~" '> signed
this instrument and acknowledged it to be his/her/their free and voluntary act for the uses and purposes
mentioned in the instrument.
Dated:
Notary Public in and for e State of Washington
Notary: (print)~'<.$..V\ O, P\l. '?--J--..A--K:>
My appointment expires: l c.::::, I \ ~ l'!::::c, l
Q:IWEBIPW\DEVSERV\FonnslPlanningltempuse,doc09/05/03 9
Sunset Sewer Interceptor Phase II
Construction Staging Area
Project Narrative
The staging area will be used during the construction of the Sunset Sewer Interceptor Phase II
project. The site will be used to store pipe, manhole sections, backfill aggregates, construction
equipment, a job shack and other items nonnally associated with utility construction. This project
will use portions of three existing lots (King County Tax Parcels 3119900005, 31199000 I 0 and
31199000 II) located at 70 I Sunset Blvd NE for a construction materials staging area. The
staging area will utilize approximately 17,000 square feet of the 3 parcels 39,225 square footage.
All construction material will be removed and the site reseeded at the end of constnlction. The
staging area will be in operation from April 2005 through November, 2005.
, 'h ' '
1 '\,:'
CITY OF·RENTON····· .' , .. ', ,'" " , ' ..
\. " DEVELOPMENT SERVI<;:ES'PIVISION '.: .' ' .. . .
" '.,
DEVELOPMENT PLANNING CITY OF RENTON
R 1 .1 2005
RECEIVED . .
.ENVIRONMENTAL CHECKl~ST
PURPOSE OF CHECKLIST:
The State Environmental Policy Act (SEPA). Chapter 43.21C RCW, requires all governmental agencies to
consider the environmental impacts of a proposal before making decisions. An Environmental Impact
Statement (EIS) must be prepared for all proposals with probable significant adverse impacts on the
quality of the environment. The purpose of this checklist is to provide information to help you and the
agency identify impacts from your proposal (and to reduce or avoid impacts from the proposal, if it can be
done) and to help the agency decide whether an EIS is required.
INSTRUCTIONS FOR APPLICANTS:
This environmental checklist asks you to describe some basic information about your proposal.
Governmental agencies use this checklist to determine whether the environmental impacts of your
proposal are significant, requiring preparation of an EIS. Answer the questions briefly, with the most
precise information known, or give the best description you can.
You must answer each question accurately and carefully, to the best of your knowledge. In most cases,
you should be able to answer the questions from your own observations or project plans without the need
to hire experts. If you really do not know the answer or if a question does not apply to your proposal, write
"do not know" or "does not apply". Complete answers to the questions now may avoid unnecessary
delays later.
Some questions ask about governmental regulations, such as zoning, shoreline, and landmark
designations. Answer these questions if you can. If you have problems, the governmental agencies can
assist you.
The checklist questions apply to all parts of your proposal, even if you plan to do them over a period of
time or on different parcels of land. Attach any additional information that will help describe your proposal
or its environmental effects. The agency to which you submit this checklist may ask you to explain your
answers or provide additional information reasonably related to determining if there may be significant
adverse impact.
USE OF CHECKLIST FOR NONPROJECT PROPOSALS:
Complete this checklist for nonproject proposals, even though questions may be answered "does not
apply." IN ADDITION, complete the SUPPLEMENTAL SHEET FOR NONPROJECT ACTIONS (part D).
For nonproject actions (actions involving decisions on policies, plans and programs), the references in the
checklist to the words "project," "applicant," and "property or site" should be read as "proposal,"
"proposer," and "affected geographic area," respectively.
Sunset Sewer Interceptor Phase II Em/. .mental Checklist
A. BACKGROUND
1. Name of proposed project, if applicable:
Sunset Sewer Interceptor Phase II Construction Staging Area
2. Name of applicant:
City of Renton -Wastewater Utility
3. Address and phone number of applicant and contact person:
1055 South Grady Way
Renton, WA 98055
Contact: John Hobson -(425) 430-7279
4. Date checklist prepared:
March 7, 2005
5. Agency requesting checklist:
City of Renton
6. Proposed timing or schedule (including phasing, if applicable):
Begin Staging
End Staging
April,2005
November, 2005
7. Do you have any plans for future additions, expansion, or further activity related to or connected
with this proposal? If yes, explain.
No
8. List any environmental information you know about that has been prepared, or will be prepared,
directly related to this proposal.
None
9. Do you know whether applications are pending for governmental approvals of other proposals
directly affecting the property covered by your proposal? If yes, explain.
None
10. List any governmental approvals or permits that will be needed for your proposal, if known.
None
W:\WWP-27-3IS0 Sunset Interceptor Ph ]J\Tcmp Use\TEMP-USE-SUNSET2.DOC -2-
Sunset Sewer Interceptor Phase II Em., .mental Checklist
11. Give brief, complete description of your proposal, including the proposed uses and the size of the
project and site.
The proposal calls for staging sewer line construction materials and equipment on King
County Tax Lots 3319900005, 3119900010 and 3119900011 (701 Sunset Blvd NE). Although
the three lot total 39, 225 square feet, the contractor will only utilize approximately 17,000
square feet. The area will be used as a staging area from approximately late April, 2005
through November, 2005.
12. Location of the proposal. Give sufficient information for a person to understand the precise
location of your proposed project, including a street address, if any, and section, township, and
range if known. If a proposal would occur over a range of area, provide the range or boundaries
of the site(s). Provide a legal description, site plan, vicinity map, and topographic map, if
reasonably available. While you should submit any plans required by the agency, you are not
required to duplicate maps or detailed plans submitted with any permit applications related to this
checklist.
The site is located in the NE quarter of Section 8, Township 23, Range 5 E on King County
Tax Lots 3319900005, 3119900010 and 3119900011 (701 Sunset Blvd NE).
B. ENVIRONMENTAL ELEMENTS
1. EARTH
a. General description of the site (circle one); flat, rolling, !!.!.!!y, steep slopes, mountainous,
other _____ _
The site slopes from Sunset Blvd NE westerly to the '·405 right·of-way.
b. What is the steepest slope on the site (approximate percent slope?)
6.5%
c. What general types of soils are found on the site (for example, clay, sand, gravel, peat,
muck)? If you know the classification of agricultural soils, specify them and note any
prime farmland.
Outwash sand and gravel overlying discontinuous till.
d. Are there surface indications or history of unstable soils in the immediate vicinity? If so,
describe.
No.
e. Describe the purpose, type, and approximate quantities of any filling or grading proposed.
Indicate source of fill.
The staging area will not require grading or filling of the site
W:\WWP-27-JJ50 Sunset Interceptor Ph II\Tcmp Usc\TEMP-USE-SUNSET2.DOC -3-
Sunset Sewer Interceptor Phase II Env,. 11ental Checklist
f. Could erosion occur as a result of clearing, construction, or use? If so, generally
describe.
Yes. Construction equipment will probably wear away the existing grass.
g. About what percent of the site will be covered with impervious surfaces after project
construction (for example, asphalt or buildings)?
There will not be any new impervious surfaces resulting from this project.
h. Proposed measures to reduce or control erosion, or other impacts to the earth, if any:
2. AIR
Standard City of Renton sedimentation and erosion control measures will be
employed during the use of the site.
a. What types of emissions to the air would result from the proposal (i.e., dust, automobile,
odors, industrial wood smoke) during construction and when the project is completed? If
any, generally describe and give approximate quantities if known.
During construction, on-site emissions will consist of fugitive dust and emissions
from construction equipment. These are anticipated to be minor and largely
confined near the site.
b. Are there any off-site sources of emission or odor that may affect your proposal? If so,
generally describe.
No.
c. Proposed measures to reduce or control emissions or other impacts to air, if any:
Equipment and construction of this project shall meet federal, state, and local
emissions requirements. A water truck will be employed to minimize dust.
3. WATER
a. Surface Water:
1) Is there any surface water body on or in the immediate vicinity of the site (including year-
round and seasonal streams, saltwater, lakes, ponds, wetlands)? If yes, describe type
and provide names. If appropriate, state what stream or river it flows into.
None
2) Will the project require any work over, in or adjacent to (within 200 feet) the described
waters? If yes, please describe and attach available plans.
N/A
W:\WWP·27-3150 Sunset Interceptor Ph I1\Temp Use\TEMP·USE·SUNSET2.DOC -4-
Sunset Sewer Interceptor Phase" Env. .mental Checklist
3) Estimate the amount of fill and dredge material that would be placed in or removed from
surface water or wetlands and indicate the area of the site that would be affected.
Indicate the source of fill material.
N/A
4) Will the proposal require surface water withdrawals or diversions? Give general
description, purpose, and approximate quantities if known.
No
5) Does the proposal lie within a 1 DO-year flood plain? If so, note location on the site plan.
No
6) Does the proposal involve any discharges of waste materials to surface waters? If so,
describe the type of waste and anticipated volume of discharge.
No.
b. Ground Water:
1) Will ground water be withdrawn, or will water be discharged to ground water? Give
general description, purpose, and approximate quantities if known.
No.
2) Describe waste material that will be discharged into the ground from septic tanks or other
sources, if any (for example: Domestic sewage; industrial, containing the following
chemicals, agricultural; etc.). Describe the general size of the system, the number of
such systems, the number of houses to be served (if applicable), or the number of
animals or humans the system(s) are expected to serve.
None.
c. Water Runoff (including storm water):
1) Describe the source of runoff (including storm water) and method of collection and
disposal, if any (include quantities, if known). Where will this water flow? Will this water
flow into other waters, If so, describe?
The construction staging area will not cause any changes in the runoff pattern.
2) Could waste material enter ground or surface waters? If so, generally describe.
No.
d. Proposed measures to reduce or control surface, ground, and runoff water impacts, if
any:
N/A
W:\WWP-27-31S0 Sunset Interceptor Ph II\Temp Use\TEMP-USE-SUNSET2.DOC -5-
Sunset Sewer Interceptor Phase II En..... ,mental Checklist
4. PLANTS
a. Check or circle types of vegetation found on the site:
deciduous tree: alder, maple, aspen, other
evergreen tree: fir, cedar, pine, other
shrubs
_X __ grass
pasture
crop or grain
__ wet soil plants: cattail, buttercup, bullrush, skunk cabbage, other
water plants: water lily, eel grass, milfoil, other
other types of vegetation
b. What kind and amount of vegetation will be removed or altered?
The existing grass will be damaged during the use of the site.
c. List threatened or endangered species known to be on or near the site.
None known.
d. Proposed landscaping, use of native plants, or other measures to preserve or enhance
vegetation on the site, if any:
The site will be reseeded following construction.
5. ANIMALS
a. Circle any birds and animals which have been observed on or near the site or are known
to be on or near the site:
Birds: hawk, heron, eagle, songbirds, other~ misc. scavenger birds (i.e. crows)
Mammals: deer, bear, elk, beaver, other misc. small mammals (i.e. squirrels)
Fish: bass, salmon, trout, herring, shellfish, other ___ _
b. List any threatened or endangered species known to be on or near the site.
None known
c. Is the site part of a migration route? If so, explain
None known.
W:\WWP·27-3JSO Sunset Interceptor Ph I!\Temp Use\TEMP-USE-SUNSET2.DOC -6-
Sunset Sewer Interceptor Phase II En...... _ ,mental Checklist
d. Proposed measures to preserve or enhance wildlife. if any:
None.
6. ENERGY AND NATURAL RESOURCES
a. What kinds of energy (electric, natural gas. oil. wood stove, solar) will be used to meet the
completed project's energy needs? Describe whether it will be used for heating,
manufacturing, etc.
None.
b. Would your project affect the potential use of solar energy by adjacent properties? If so,
generally describe.
No.
c. What kinds of energy conservation features are included in the plans of this proposal?
List other proposed measures to reduce or control energy impacts, if any:
NIA
7. ENVIRONMENTAL HEALTH
a. Are there any environmental health hazards, including exposure to toxic chemicals, risk
of fire and explosion, spill, or hazardous waste that could occur as a result of this
proposal? If so, describe.
With the exception of potential fuel spills from construction equipment, no
hazardous chemicals or other health hazard risks are anticipated.
1) Describe special emergency services that might be required.
The only anticipated emergency needs during construction would be ambulance wi
paramedical personnel (in the event of a construction related accident), fire
suppression equipment (in the event of a fire, or the emergency spill response
team (in the event of a major fuel spill).
2) Proposed measures to reduce or control environmental health hazards, if any:
Refueling areas will be equipped with appropriate equipment to comply with spill
prevention and cleanup procedures as required by federal, state and local laws.
b. Noise
1) What types of noise exist in the area which may affect your project (for example: traffic,
equipment, operation, other)?
None.
W:\WWP-27-3150 Sunset Interceptor Ph lI\Temp Use\TEMP-USE-SUNSET2.DOC -7-
Sunset Sewer Interceptor Phase II En ........ mental Checklist
2) What types and levels of noise would be created by or associated with the project on a
short-term or a long-term basis (for example: traffic, construction, operation, other)?
Indicate what hours noise would come from the site.
Short-term noise from construction equipment would occur between 7:00 AM and
5:00 PM.
3) Proposed measures to reduce or control noise impacts, if any:
All construction equipment shall meet all federal, state and local laws for noise
restrictions.
8. LAND AND SHORELINE USE
a. What is the current use of the site and adjacent properties?
The site currently includes one vacant, single-story, former real estate office and
grass field. The existing structure will not be disturbed by the project. Adjacent
sites include single-family residential, multi-family residential.
b. Has the site been used for agriculture? If so, describe.
No
c. Describe any structures on the site.
None
d. Will any structures be demolished? If so, what?
No
e. What is the current zoning classification of the site?
Residential Multi-Family Infill (RM-I).
f. What is the current comprehensive plan designation of the site?
Residential Multi-Family Infill.
g. If applicable. what is the current shoreline master program designation of the site?
N/A
h. Has any part of the site been classified as an "environmentally sensitive" area? If so.
specify.
No
i. Approximately how many people would reside or work in the completed project?
None.
W:\WWP-27-3 J 50 Sunset Interceptor Ph II\Temp Use\TEMP-USE-SUNSET2.DOC -8-
Sunset Sewer Interceptor Phase II Env ...• mental Checklist
j. Approximately how many people would the completed project displace?
None.
k. Proposed measures to avoid or reduce displacement impacts, if any:
N/A
I. Proposed measures to ensure the proposal is compatible with existing and projected land
uses and plans, if any:
N/A
9. HOUSING
a. Approximately how many units would be provided, if any? Indicate whether high, middle,
or low-income housing.
None.
b. Approximately how many units, if any, would be eliminated? Indicate whether high,
middle, or low-income housing.
None.
c. Proposed measures to reduce or control housing impacts, if any:
N/A
10. AESTHETICS
a. What is the tallest height of any proposed structure(s), not including antennas; what is the
principal exterior building material(s) proposed.
N/A
b. What views in the immediate vicinity would be altered or obstructed?
None
c. Proposed measures to reduce or control aesthetic impacts, if any:
N/A
11. LIGHT AND GLARE
a. What type of light or glare will the proposal produce? What time of day would it mainly
occur?
None.
b. Could light or glare from the finished project be a safety hazard or interfere with views?
No.
W:\WWp·27·3150 Sunset interceptor Ph J]\Temp Use\TEMP·USE·SUNSET2.DOC -9-
Sunset Sewer Interceptor Phase II Env.. ,mental Checklist
c. What existing off-site sources of light or glare may affect your proposal?
None.
d. Proposed measures to reduce or control light and glare impacts, if any:
N/A
12. RECREATION
a. What designated and informal recreational opportunities are in the immediate vicinity?
None
b. Would the proposed project displace any existing recreational uses? If so, describe.
No
c. Proposed measures to reduce or control impacts on recreation, including recreation
opportunities to be provided by the project or applicant, if any:
N/A
13. HISTORIC AND CULTURAL PRESERVATION
a. Are there any places or objects listed on, or proposed for, national state, or local
preservation registers known to be on or next to the site? If so, generally describe.
None
b. Generally describe any landmarks or evidence of historic, archaeological, scientific, or
cultural importance known to be on or next to the site.
None known.
c. Proposed measures to reduce or control impacts, if any:
N/A
14. TRANSPORTATION
a. Identify public streets and highways serving the site, and describe proposed access to the
existing street system. Show on site plans, if any.
The site will be accessed from Sunset Blvd NE.
b. Is site currently served by public transit? If not, what is the approximate distance to the
nearest transit stop?
N/A
c. How many parking spaces would the completed project have? How many would the
project eliminate?
None.
W:\WWP-27-3150 Sunset Interceptor Ph II\Temp Use\TEMP-USE-SUNSET2.DOC -10-
Sunset Sewer Interceptor Phase II En",. _.lmental Checklist
d. Will the proposal require any new roads or streets, or improvements to existing roads or
streets, not including driveways? If so, generally describe (indicate whether public or
private?
No.
e. Will the project use (or occur in the immediate vicinity of) water, rail, or air transportation?
If so, generally describe.
No.
f. How many vehicular trips per day would be generated by the completed project? If
known, indicate when peak volumes would occur.
None.
g. Proposed measures to reduce or control transportation impacts, if any:
During construction, proper traffic control and detour routing will be used.
15, PUBLIC SERVICES
a. Would the project result in an increased need for public services (for example: fire
protection, police protection, health care, schools, other)? If so, generally describe.
No.
b. Proposed measures to reduce or control direct impacts on public services, if any.
N/A
16. UTILITIES
a. Circle utilities currently available at the site: The following utilities are currently
available: electricity, natural gas, water, refuse service, telephone, sanitary sewer,
cable, storm drainage facilities
b. Describe the utilities that are proposed for the project, the utility providing the service, and
the general construction activities on the site or in the immediate vicinity which might be
needed.
There are no new utilities proposed for the site.
W:\WWP-27-315D Sunset Interceptor Ph I1\Tcmp Use\TEMP·USE-SUNSET2.DOC -11-
;
Sunset Sewer Interceptor Phase II Em .. Imental Checklist
C. SIGNATURE
I, the undersigned, state that to the best of my knowledge the above information is true and
complete. It is understood that the lead agency may withdraw any declaration of non-significance
that it might issue in reliance upon this checklist should there be any willful misrepresentation or
willful lack of full disci n my part.
Proponent:
Name Printed: John Hobson, City of Renton Wastewater Utility
Date: March 9, 2005
W:\WWP-27-31so Sunset Interceptor Ph I!\Temp Use\TEMP-USE-SUNSET2.DOC -12-
~. \ \ \ , -\ -~ \""\--~.~=-r----7-
\ \. \ \ i
\ '. \ ! I
\ \ " : , , /)' .
I I'
/
\\ I
I
~
I
I
U4~~ __ I
~ 2 I
~ 1 a5~}
til
(/)
2
SUNSET SEWER INTERCEPTOR PHASE II
CONSTRUCTION STAGING AREAvELoPMENTPLA SITE MAP C/TYOFRENTo~N
MAR 112005
RECEIVED SCALE 1"=40'
/