5:30 PM Meeting called to order and agenda reviewed by Marleen Mandt
5:35 PM Meeting minutes of November 18, 2014 were unanimously approved with one
change to note that Marleen Mandt was present at the beginning of the meeting.
5:37 PM Jonathan Wilson Introduced Pearson MacNaughton as the new Assistant Airport
Manager.
Pearson, J recently retired Marine, has moved his family here from Florida.
5:38 PM Neighborhood Communications - There were no comments from neighborhoods
regarding any issues brought up by the neighborhoods.
5:39 PM Old Business
Sustainability Report for 2013, presented by Mary Vigilante, Synergy
Consultants, Inc.
o Gave a brief overview of the Sustainability Plan and report for 2013
o Defined EONS of Sustainability (Economic, Operations, Natural
Environment, Society)
15Y annual report 2013 (summarizes progress during the year, actual
performance and reasons for changes, adjustments that are needed)
o Plan Do Check Act (adjust) process
o Airport Operations
o Airport Finances — AI Banholzer asked if lease rate increases register on
the chart/Answer — no not significant change, the graph shows major
grant funded projects.
Noise — membership discussion on what data is available from noise
complaint database. Complaints are logged by complainant, type of
aircraft, and type of disturbance.
o Insertion into the Master Plan
• Airport Master Plan Project Updates, presented by Ryan Hayes, Mead & Hunt
Renton Airport Administration Office
Clayton Scott Field and Will Rogers -Wiley Post Memorial Seaplane Base
616 West Perimeter Road, Unit A, Renton WA 98057 425-430-7471
o Brief overview of Master Plan process
o Public Outreach is ongoing throughout the process and comments on any
Chapter can be submitted throughout the process
■ Kennydale Neighborhood meeting was received well with
knowledgeable questions asked by residents
■ Follow-up neighborhood meetings towards the end of the
planning process
o Draft Forecast Chapter (Working Paper 2)
■ Airport operations forecast
• Matthew Devine suggested a change to what the
forecasted operations trendline is called because it is so
extreme.
• Question was raised on why floatplane operations are not
identified separately on the chart showing operations by
aircraft type/Answer — floatplane operations are not
reported separately from similar wheeled aircraft.
• Critical aircraft defined— B stands for approach speed of
aircraft, II stands for wingspan of aircraft; based on 737
forecasted operations will need to change to higher
standard requiring runway safety area extensions.
Summary of Operations
• Question was raised of how forecast of operations is
determined by type/Answer —percentage based on local
vs. itinerant operations
Based aircraft
■ FAA approves Forecast Chapter and Final Plan
o Next Steps
■ FAA Forecast Approval
■ Facility Needs Analysis
■ Preliminary Alternatives and Ancillary Alternatives
o Comments
Marleen commented on Working Papers and suggested several
items that need to be clarified.
Diane asked if the based aircraft will decrease in 2015/Answer- no
it will not decrease from current count. The based aircraft count
is taken in January each year and has already been established for
2015.
Matthew asked about operation growth forecast model. Mary
Vigilante answered that the forecasted numbers have
consequences that can be determined (how to accommodate
forecasted operations)
Renton Airport Administration Office
Clayton Scott Field and Will Rogers -Wiley Post Memorial Seaplane Base
616 West Perimeter Road, Unit A, Renton WA 98057 425-430-7471
• Ryan Hayes clarified the different forecasts on the General
Aviation Operations Forecast chart, and pointed out that the
recommendation of the Master Plan is the gray arrowed line.
6:50 PM Questions/comments on Airport Lines of Business
• Airport Business Management Update (see Page 6)
o Tower Closure — contracted through September 2015
o Comcast — working on design; Marcie asked if Preeti was involved in
project
o Boeing North Bridge —final year of project
• Airport Operations/Maintenance Update (see Page 8)
o Wildlife Hazard Assessment
o Airport badge standards
0 800 Building upgrades
o Tower Office remodel
• Airport Capital Projects Update (see Paje 10)
o WMATI continuing; 300 Building demolition in May 2015
o Shoreline Mitigation temporarily on hold
o River Hangar electrical upgrades temporarily on hold
o Blast Fence project nearing completion
o Restripe drive lane on Taxiway Alpha
6:57 PM Meeting process check and agenda inputs for next meeting
• Master Plan Working Paper 3
o Facility Requirement Chapter
o Public Outreach update
7:02 PM Meeting adjourned
RAAC Meeting Calendar — May 19, 2015
Renton Airport Administration Office
Clayton Scott Field and Will Rogers -Wiley Post Memorial Seaplane Base
616 West Perimeter Road, Unit A, Renton WA 98057 425-430-7471
3
Attendees Absentees
Kennydale
Marleen Mandt Mark Hancock
Highlands
Jeffrey Thomson
Harold (KC) Jones
Talbot Hill
Matthew Devine Jennifer Ann Rutkowski
South Renton
Neil Sheesley
Robert Moran
West Hill
Ken Williams Frederick Lund
Renton Hill/Monterey
David Basco
Melody Kroeger
North Renton
Lee Chicoine
Ben Johnson
Airport Leaseholders
Diane Paholke Chuck Kegley
Steve Beardslee
Bradly Donaldson for Gordon Alvord
Airport at Large
Kurt Boswell Mark Spiegelman
Todd Banks
Mike Johnson
Renton Airport Administration Office
Clayton Scott Field and Will Rogers -Wiley Post Memorial Seaplane Base
616 West Perimeter Road, Unit A, Renton WA 98057 425-430-7471
4
Attendees Absentees
Boeing
Blake Misenar
Valdis Martinsons
Pilots Association
Karen Stemwell Robert Dempster
WPA — Green River Chapter
Al Banholzer
Mercer Island
Mike Cero
Councilmembers
Marcie Palmer
City Staff
Jonathan Wilson
Pearson MacNaughton
Susan Campbell-Hehr
Guests
Ryan Hayes, Mead & Hunt
Brodie Ayers, Mead & Hunt
Mary Vigilante, FAA
Renton Airport Administration Office
Clayton Scott Field and Will Rogers -Wiley Post Memorial Seaplane Base
616 West Perimeter Road, Unit A, Renton WA 98057 425-430-7471
5
RAAC Meeting Tuesday, February 17, 2015
Airport Update for RAAC
Airport Business Management
1. Control Tower Closure Update - Ongoing
What: Funding for Federal Contract Towers (including Renton) might be cut in future federal
budgets.
Why: Sequestration at the federal level meant agencies needed to make difficult budget cuts.
One of the potential cuts was in the federal contract tower program administered by
the FAA.
How: Not applicable.
Status: Budget for the federal contract tower program has I?een allocated for FY2015. Tower
will be funded at least through the end of September 2015.
2. Comcast Lease —
What: Addition of cable line on Airport property.
Why: Requested by tenants in the southeast corner for high speed internet and television.
This is also a good infrastructure improvement for the remaining tenants.
How: Design and construction costs covered by Comcast.
Status: Comcast staff continues to design their conduit runs around the Airport after receiving
Airport feedback on the design. The agreement has been in Comcast's hands for several
months. No change or appreciable movement since August's meeting..
3. Airport Master Plan Update -
What: Update of the Airport's existing 1997 Master Plan. A Master Plan is a comprehensive
study of an Airport that identifies the short, medium, and long term development
alternatives to meet future aviation demand.
Why: Master Plans are typically updated every 20 years. The last Master Plan was completed
in 1997. The Airport completed an Airport Layout Plan update in 2009.
R
RAAC Meeting Tuesday, February 17, 2015
How: FAA grant funded at 90%. Airport revenues will cover 10% of the project costs. The
Airport has contracted with Mead and Hunt to assist in completing the project.
Status: Airport aerial survey has been mostly completed. The draft Inventory chapter has been
completed and discussed at the November 2014 RAAC meeting. The Forecast draft
chapter will be discussed at the February 2015 RAAC meeting.
4. Bosair Building Construction—
What: Construction of a new aviation maintenance hangar at 289 East Perimeter Road.
Why: Bosair has outgrown their existing buildings. The business requires a larger facility to
support their growing maintenance business.
How: Project is fully funded via Bosair. One of their two buildings has been demolished and a
new building is being erected in its place. All business activities have been conducted
I out of the other building during construction.
Status: Building is currently under construction. Much of the outer shell of the building has
been completed. Interior construction is underway. Building should be complete late
this Spring.
S. Boeing North Bridge Construction—
What: Construction of a new bridge at the northeast corner of the Airport. Bridge is used to
bring Boeing jets from private property onto Airport property.
Why: The existing bridge was seismically inadequate. This bridge is critical to Boeing logistical
operations.
How: Project is being fully funded by The Boeing Company.
Status: The new bridge is complete. Work this summer is expected to start on June 1. The
remaining work includes removing the temporary work bridge, landscaping, and general
site repairs. This is the last summer of work scheduled for this project.
7
RAAC Meeting Tuesday, February 17, 2015
Airport Operations and Maintenance
1. Taxiway Bravo System Rehabilitation — South Portion - Completed
What: A $10.5 million pavement and utility replacement and repair project on Taxiway Bravo.
Why: The pavement on this parallel taxiway had reached the end of its useful life and needed
to be strengthened and replaced. Additionally, utility lines in the area were replaced and
all connecting taxiways were renamed Al, A2, B1, B2 and so on from their current alpha
only designations. The airport also installed an emergency generator and LED lighting
along Taxiway Bravo.
How: The FAA is providing grant funding to help complete the project. Grant funding covered
90 percent of design and construction cost with the remaining 10 percent covered by
Airport generated revenue.
Status: All construction is now complbte.
2. Wildlife Hazard Assessment - In Progress
What: An FAA grant funded project to complete a Wildlife Hazard Assessment (WHA) at the
Airport. WHAs are completed to help airports formulate Wildlife Hazard Management
Plans. These plans help airports mitigate and reduce the effects of wildlife on airport
operations.
Why: Ever since the bird strikes that brought down the US Airways flight into the Hudson
River, the FAA has placed new emphasis on Airports completing Wildlife Hazard
Assessments. Historically, these were only done for Part 139 certificated airports, but
recently federal funding has been made available for certain non -certificated airports to
participate.
How: Federal grant funding of up to $150,000 (90%) and airport revenue up to $16,667 (10%).
Status: WH Pacific is complete with their surveys for the Wildlife Hazard Assessment and
currently in progress drafting their final report.
3. New Airport Badge Standards -In Progress
What: A new ID badge program for tenants and contractors who need to access the Airside of
the Airport.
E
RAAC Meeting
Tuesday, February 17, 2015
Why: The Airport currently has a badging system for tenants and contractors. Badges do not
have any identifying information on them. When someone is stopped by Airport
Operations, they might have a badge on them, but it is unknown whether it's their
badge and where on the Airport the driver should be.
How: The Airport has budgeted money to purchase a new ID badge system from HID. New
badges will have a photo, name, airport business (if applicable), airplane information (if
applicable), and expiration date. All badges will be valid for one year instead of the
current standard of up to five years (expires when the driver's license expires).
Status: All equipment has been installed and tested. The new card design has been created.
Instructions for office staff are being tweaked.
4. 800 Building —In Progress
What: Major maintenance of the building at 800 W Perimeter Road (800 Building) for future
tenant occupancy.
Why: The 800 Building it airport owned and operated. Upgrades include fixing numelrous roof
leaks, demolition of unnecessary roof structures, selected demolition of some interior
spaces and ducting, and installation of work bay heating.
How: Airport generated revenue will cover the cost of repairs.
Status: The Airport staff is working with Forma Construction, the City's Job Order Contractor
(JOC). The interior demolition is now complete and construction of new office wall
layout is in progress. The subcontractor has completed installation of the heating
system. Completion of the fire suppression system and roof work currently in progress.
Installation of a roll -up door for access to the maintenance bay is upcoming. The final
item is painting of the exterior of the building and that is scheduled for the Spring, 2015,
due to weather. Work should be complete by the RAAC meeting on August 18, 2015.
S. Tower First Floor Remodel — In Progress
What: Remodel of the first floor of the Control Tower
Why: The first floor is being remodeled to improve the functionality of the floor plan layout
and optimize operations.
How: Airport generated revenue will cover the cost of the remodel when the estimated cost is
determined.
Status: This project is currently in the initial design phase.
.11
RAAC Meeting Tuesday, February 17, 2015
Airport Capital Program
1. Washington Manufacturing Advanced Training Institute—
What: The Airport will be managing the construction of a new facility called the Washington
Manufacturing Advanced Training Institute (formerly Renton Aerospace Training
Center) located on the same site as the old Chamber of Commerce building.
Why: The project is to build a facility and provide equipment to help train critically needed
manufacturing workers in the aerospace, maritime, and medical industries. This facility
will be a resource to help meet the immediate need for trained workers in these
industries and be a long-term asset for the community.
How: The State legislature provided a $2.5 million grant in 2012 and an additional $9.5 million
aerospace grant in 2013 to build this facility in concert with industry and potential
tenant partners. SRG Partnership Inc. will design the project. The design re -started with
a recent recommendations report from the Aerospace Futures Alliance of Washington
(AFA) appointed committee headed by Laura Hopkins.
Status: Design has been restarted. Demolition of the existing structure should be completed
late Spring of 2015. Construction of the new facility is scheduled to begin late in 2015.
2. Shoreline Enhancement— On hold
What: As part of the permitting for the Maintenance Dredge project, the airport will make
improvements to the shoreline near the seaplane ramp. We will remove concrete
rubble and replace with rock to prevent erosion.
Why: This project is driven by permits issued for the seaplane base maintenance project that
was completed early this year.
How: The Airport will fund this project.
Status: Project has been placed on hold temporarily pending the hire of a new Airport Engineer.
3. Cedar River Hangar Building Electrical Upgrades— Building Electrical Upgrades - On hold
What: The Airport will update the electrical system in the hangars over the next four years.
Why: The electrical system in the Cedar River Hangars is outdated and insufficient for tenant
needs.
How: The Airport will fund the electrical upgrades. URS prepared construction plans for the
project. The design for electrical project is complete and the permit is ready to be picked
up.
Status: The electrical project is on hold while other larger capital projects are being completed.
project is also on hold pending the hire of a new Airport Engineer.
10
RAAC Meeting
4. Blast Wall Replacement—
Tuesday, February 17, 2015
What: The blast wall on the south end of the runway will be removed and replaced with a new
blast wall to meet FAA Part 77 standards. The project includes aesthetic treatments to
the Airport way side of the blast fence along with new landscaping.
Why: The existing blast fence has exceeded its useful life and is an obstruction to airspace per
the Airport Layout Plan (ALP).
How: This is an FAA grant project (90%) with the airport contributing 10% of the project cost.
Status: Construction is underway. The old blast wall has been demolished. The new blast wall
has been erected. Landscaping is underway. The original concept art for the south side
of the blast wall had to be modified due to budget. The flow vanes on either side of the
center art have been eliminated to meet budget. Some lighting has been removed to
preserve budget. Project should be complete in 90 days.
S. Restripe Drive Lane and Taxiway A— On hold
What: I The A Taxiway and the drive lane need to be repainted.!The project includes restriping
the existing markings and extending the drive lane north to the seaplane base.
Why: Taxiway Alpha and drive lane markings are faded and need to be repainted.
How: This is a pavement management plan project.
Status: On hold pending the hire of new Airport Engineer. Airport staff is considering hiring
outside engineering help to prepare bid documents.
11
70,000
80,000
90,000
100,000
110,000
120,000
130,000
140,000
150,000
160,000
170,000
180,000
190,000
200,000
210,000
Historical GA Operations
TAF
5 Year Trend
Scenario 1
Scenario 2
Scenario 3
Average