AMENDMENT NO. 2 TO AGREEMENT FOR DOWNTOWN UTILITY
IMPROVEMENT PROJECT - PHASE 2: PRELIMINARY
ENGINEERING AND DESIGN CAG-18-154
THIS AMENDMENT, dated August 12, 2019, is by and between the City of Renton (the "City"), a
Washington municipal corporation, and Murraysmith, Inc. ("Consultant"), an Oregon
Corporation. The City and the Consultant are referred to collectively in this Amendment as the
"Parties." Once fully executed by the Parties, this Amendment is effective as of the last date
signed by both parties.
Whereas, the City engaged the services of the Consultant under Agreement CAG-18-154, dated
August 20, 2018, to provide necessary services for the Downtown Utility Improvement Project-
Phase 2: Preliminary Engineering and Design (referred to herein as the "Agreement");
Whereas,the Parties wish to amend the Agreement to change the time for performance,in order
to allow the consultant to complete all current scoped items of work in a timely manner.
NOW THEREFORE, It is mutually agreed upon that CAG-18-154 is amended as follows:
1. Time of Performance: Section 3, Time of Performance, is amended pursuant to the
schedule(s)set forth in Exhibit B-2.All Work shall be performed by no later than October
31, 2019.
2. All terms of the Agreement not explicitly modified herein shall remain in full force and
effect and such terms shall apply to Work performed according to this Amendment as if
fully set forth herein.
IN WITNESS WHEREOF,the Parties have voluntarily entered into this Agreement as of the date
last signed by the Parties below.
CITY OF RENTON CONSULTANT
y `1 r"l/� m1 y.
Gregg Zigh er an, P. Jeffrey S. s el, P.
Administrator Principal Engineer
g 122 12-O l /
Date Date
Approved as to Legal Form
By�!`l--fie
Shane Moloney
Renton City Attorney
Contract Template Updated 03/12/2019
0
PAGE 2 OF 2
EXHIBIT B-2
TIME SCHEDULE OF COMPLETION
DOWNTOWN UTILITY IMPROVEMENT PROJECT -- PHASE 2:
PRELIMINARY ENGINEERING AND DESIGN
CITY OF RENTON
Preliminary Estimate Schedule
Murraysmith shall begin work immediately upon receipt of Notice to Proceed from the City and
proceed according to the preliminary estimated schedule presented below. However,the
schedule may change due to factors beyond Murraysmith's control.
Preliminary Design Tasks Estimated Completion
Phase 2 Notice to Proceed Early August 2018
Task 101 -Project Management August 2018—March 2019
Task 102- Project Meetings and Coordination August 2018—March 2019
Task 201—Field Survey& Base Map Development August 2018—October 2018
Task 202—Potholing October 2018—December
2018
Task 300-Horizontal Alignment Analysis& Preliminary Layout(30%) October 2018—January
2019
Task 400- Preliminary Design (50%) January 2019—March 2019
Task 501- Public Involvement August 2018—March 2019
Task 601- Phase 3 Final Design Scope Development January 2019—March 2019
Phase 2 Amended Final Completion October 31, 2019
City of Renton MURRAYSMITH DUIP—Phase 2
June 2018 1