HomeMy WebLinkAboutCO 1 CITY OF RENTON Public Works Department CAG-19-152 , Co #1-19 CONTRACT CHANGE ORDER AGREEMENT CONTRACT: Lake Youngs Ct SE Storm&Water Improvement Project CAG-19-152 C.O.# 1 ..CONTRACTOR: Oceanside Construction, Inc. SUMMARY OF PROPOSED CHANGE: Provide all labor,equipment,subcontracting, bonding, insurance for the complete work required for the extra • work as outlined below and shown in the contractor's proposal: ITEM Alteration Under This Change Order Unit Qty. Unit Price Total Price Field Work NEW ITEM: LS 1 $2,041.56 $2,041.56 Directive#5 See attached for Field Work Directive#5 and associated Force Account-5. Field Work NEW ITEM: LS 1 $2,006.87 $2,006.87 Directive#6 See attached for Field Work Directive#6 and associated Force Account-6. Total $4,048.43 ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE ESTIMATED CONTRACT THIS ORDER TOTAL AFTER CHANGE $501,986.60 $501,986.60 $4,048.43 $506,035.03 SIGNATURES: Date: 91 r Contractor:Project Engineer: A....0)./ /hp �'RI" I p Date: � � 1 Approved By: Date: v(2��� Ron S aka,Utility Systems Director( O ' a AN Approved �'h ok RC1n- Approved By: k P� )110,9 r Date: Greg Zimmer an PW Ad istr Approved B• Date: Shane Moloney,Renton City Atto y Attest; Date: Jason Seth,City Clerk H:\File Sys\SWP-Surface Water Projects\SWP-27-Surface Water Projects(CIP)\27-4017 2617 Lake Youngs CT SE\1600 Construction\1606a-Change Orders\CO#1\CO#1-Oceanside Construction.doc\JHmc • • • • �f I Lake Youngs Ct SE Storm &Water Project Name: Improvement Project CAG- 19- 152 Contractor: Oceanside Construction, Inc. _ Removal of Possible Concrete Duct Subject: Bank Date: 8/01/2019 Scope: On July 29th, 2019,while laying the proposed storm between EX. CB#3 and EX. MH#1, Oceanside Construction, Inc. ran into a conflict with what appears to be a concrete duct bank above the existing gas. There was concern that the concrete duct was encasing an existing utility. Prior to removing the concrete duct bank a utility locate was required. PSE came out to the site on July 29th, 2019 and verified that they did not have any active utilities within the concrete. On July 30th, 2019 a utility locate was performed. No utility claimed that any active service was contained within the concrete. At this time,the City of Renton is directing Oceanside Construction, Inc.to move forward with removing the concrete in conflict with the proposed storm as necessary. If an active utility is impacted please contact the inspector for further instruction. Attachment(s): N/A Contractor Acknowledgement: By: Contractor Signature Date Title ICJ '"T J 08/O 1/19 By: JARED MCDONALD, PE Signature Date City of Renton Project Manager THIS FIELD WORK DIRECTIVE DOES NOT PROVIDE FOR EITHER A TIME EXTENSION OR A CHANGE IN THE CONTRACT PRICE. LABOR, EQUIPMENT,AND/OR MATERIAL OUTLINED IN THIS FIELD WORK DIRECTIVE SHALL BE PAID BY BID ITEM(S)OR A CHANGE ORDER SHALL BE DEVELOPED FOR TIME EXTENSION OR CONTRACT PRICE INCREASES. ANY PROTEST TO THE FIELD WORK DIRECTIVE SHALL FOLLOW 1-04.5 OF THE WSDOT STANDARD SPECIFICATIONS. NO EXCEPTIONS TAKEN. -JM,COR,8/07/19 r �� _ Oceanside Construction Inc. �l. �, ,1;r" 1511 Mt. Baker Hwy Bellingham, WA. 98226 Phone 360-933-1728 Fax 360-93 -4152 Force Account 201903 — Lake Youngs Ct. SE Storm Et Water Subject: Removal of CDF from in Front of Ex. Improvements CB#3 To Jared McDonald Number: FA-5 City of Renton Revision No. : 0 1055 South Grady Way, 5th Floor Date: 8/5/2019 Renton, Washington 98057 Field Work Order / Work Type: 425-430-7293 T>*M Days Valid: 5 Return To Auden Schilder Oceanside Construction Inc (360) 933-1728 asatosc@yahoo.com Scope Of Work / Time Extension Request Due to unforeseen conditions within the intersection while installing the 8"C900 storm pipe, Oceanside was requested to remove CDF duct bank in front of Ex. CB#3 per FWD#5. Details £. 3 + a Z xP , '+ ,�`" r }.. b r 1,Mv' � k kid . - r`.e � t�`v+ a°`",`��4�'a'• a2�F Line Igo Code.` Desc ption t Type l Ra e ' �' / Hrs Workers Ex A-8-201903 Shovel , Excavator, 2.50 - MINOR Backhoe, Tractors Labor $73.25 1.00 $183.13 001 CHANGE i Under 15 TN sit Hrs Cory A-8-201903 - MINOR Loader, Overhead 2.50 Labor $73.81 1.00 $184.53 002 CHANGE Under 6 Yards Hrs Steve �/ A-8-201903 - MINOR TCS Labor $51.55 2.50 1.00 $128.88 003 CHANGE Hrs Kris ,f� `F��a. ?r�r y `kS v t ,»r; .ix#'emu x`�* Lek 0J xr=14: .3 a ✓n g ," + u.'',+ a 4irgp,,r-: ' . ` w ; ,t' 1 ;: "f SA,X :' - ',1'" .€4*,', +'f-1: ',t '- i'' '4'«x. ''S1 .Y.O. COS -'''' Q 'p,�,. F '+. 'a' > d i 1 O� ,COde� . Des'rlp re ft �3, £ *ate 4 40 r ,, Or ;f r.,:?Pjie: .�x: es 't °.,+:�"�„a, aid. '�r.'r a..*-,- >n3, ..v,e 'n;Aft ,k, s. & —b s, �'.v. .c.._ ,. :,�i�;`a x.�': A-8-201903 - MINOR Flagger v Labor $48.33 2.50 1.00 $120.83 004 CHANGE V Y Drew A-8-201903 2.50 - MINOR Dump Truck Solo Labor $66.51 �s 2.00 $332.55 005 CHANGE Tom / Ty A-8-201903 - MINOR General Laborer Labor $56.65 .0 1.00 $141.63 006 CHANGE John W A-8 201903 Kubota KX121-3 with 007 - MINOR Equipment $43.75 2.50 $109.38 CHANGE bucket A-8-201903 - MINOR 2007 Hitachi ZX135 Equipment $68.18 2.50 - $170.45 008 CHANGE Standby A-8-201903 - MINOR 2002 Mack Dump' Equipment $61.23 2.50 - $153.08 009 CHANGE Truck `/ Standby A-8-201903 010 - MINOR 2015 Chev 3500 with Equipment $36.25 2.50 - $90.63 CHANGE tools Breakout Labor : $1,091.54 Gross Margin Percent @ 29%: $316.55 V Equipment : $523.53 Gross Margin Percent @ 21%: $109.94 Total: $2,041.56 Signed By: Dated: 8/5/2019 Auden Schilder Project Manager Lake Youngs Ct SE Storm &Water Project Name: Improvement Project CAG- 19- 152 Contractor: Oceanside Construction, Inc. Subject: CO#4 and CO#5 Date: 8/07/2019 Scope: After discussing with City of Renton Maintenance and Oceanside Construction, Inc. it has been agreed that both CO#4 and CO#5 are not required and will not be installed. Instead only a tee connection will be provided. It was also noted that the "insert-a-tee" connection that the contractor planned to use at CO#4 was not an effective connection. Please provide a tee connection and replace the corresponding 8" PPP with an 8" HDPE as submitted on by the contractor on 8/7/19. Please bill new materials via a Force Account. Attachment(s): N/A Contractor Acknowledgement: By: Contractor Signature Date Title � / '/4 11 08/07/19 By: JARED MCDONALD, PE Signature Date City of Renton Project Manager THIS FIELD WORK DIRECTIVE DOES NOT PROVIDE FOR EITHER A TIME EXTENSION OR A CHANGE IN THE CONTRACT PRICE. LABOR, EQUIPMENT,AND/OR MATERIAL OUTLINED IN THIS FIELD WORK DIRECTIVE SHALL BE PAID BY BID ITEM(S)OR A CHANGE ORDER SHALL BE DEVELOPED FOR TIME EXTENSION OR CONTRACT PRICE INCREASES. ANY PROTEST TO THE FIELD WORK DIRECTIVE SHALL FOLLOW 1-04.5 OF THE WSDOT STANDARD SPECIFICATIONS. I' NO EXCEPTIONS TAKEN. -JM,COR,8/20/1 9 0: %' • Oceanside Construction Inc. _`�` �''�;- 1511 Mt. Baker Hwy Bellingham, Wa4. 9'$22'6 Phone 36Q-933-1728 Fax 390-933-4152 Force Account 201903 — Lake Youngs Ct. SE Storm Ft Water Improvements Subject: Work Per FWD #6 To Jared McDonald Number: FA-6 City of Renton Revision No. : 2 1055 South Grady Way, 5th Floor Date: 8/7/2019 Renton, Washington 98057 Field Work Order / Work Type: Tam425-430-7293 Days Valid: 5 Return To Auden Schilder Oceanside Construction Inc (360) 933-1728 asatosc@yahoo.com Scope Of Work / Time Extension Request Due to unforeseen conditions on this day, Oceanside has tracked the work required to complete FWD#6. This is the latest revision per email from Jared McDonald on 8/12/19. Note that FA-7 also occurred on this date. Details `a" "y Line Not Code x Descri t n 4 Type}` /R e / Hers ' FWorke s Ezt A-8-201903 Shovel , Excavator, 2.00 - MINOR Backhoe, Tractors Labor $73.25V Hrs 2.00 $293.00 001 CHANGE Under 15 TN Cory / Steve A-8-201903 2.00 - MINOR Dump Truck Solo Labor $66.51 Hrs 1.00 $133.07� 002 CHANGE John W A-8-201903 003 MINOR Pipe Layer Labor $57.67 2.00 1.00 $115.34 Hrs CHANGE x ; s,z ta.*.tiY��; a yx°;-�- z�t�k �7�5 �. ,, c t� 'lei` �'=� t� ; ar �,."'e ss� ': "s, t ' ''- '�-f�`. it 2^ F mom, a e. ; ,�M<A 5 ii s�'�€-u �, i x, a Yz.ra. >.+ad'cd, a14 i". " a k �,r -,r YM _„.i. :',a"X,t i f sY r`t i a i L ilia' ,a'a A »#COst''1 i,'§'`r.: -- 4 S'. C.� �'� -.� '�'y ��#^ .C., f� .� y.r.`'" �vs..r"^2' j 3'+ ;'�k� �h�F;s��^��i,� az�.> v � , r� - �""'�.t� �� � n Line No ri Co a Descr pt o �, kiSip ,< i'_3.°t ,,a.Baas L _y i sib Vs orkers `f` E tp Drew A-8-201903 - MINOR TCS Labor $51.55, 2.00 1.00 $103.10 004 CHANGE V Hrs Kris A-8-201903 - MINOR 2007 Hitachi ZX135 Equipment $68.18 2.00 - $136.36 005 CHANGE V Standby A-8-201903 2002 Mack Dump - MINOR Equipment $61.23 2.00 - $122.46 006 CHANGE Truck V Standby A-8-201903 - MINOR 2011 Hitachi ZX120-3 Equipment $65.77 2.00 - $131.54� 007 CHANGE Standby A-8-201903 - MINOR 2015 Chev 3500 with Equipment E ui $29.00 2.00 - $58.00 008 tools q p CHANGE Standby A-8-201903 - MINOR JD 085 Excavator Equipment $35.00 2.00 - $70.00 009 CHANGE Standby A-8-201903 - MINOR 2006 Chev Silverado Equipment $20.00 2.00 - $40.00 010 CHANGE Standby A-8-201903 1990 Peterbuilt 12 CY - MINOR Equipment $61.23 2.00 - $122.46 011 CHANGE Dump Truck Standby Iv 1.00 012 Tee and HDPE Material $290.69 - $290.6� EACH % „, C g .s 2 a x �'htiAry1. �� G , y`G� .d ETYX�'�' � : 'Fk �.��� �o- �3{y�'`"z"` :. `� ��K�.� �;, �'.�� ���:. s� $ �'k 4�' A�'�iys�� .s�*'*�`�'.1 �"3� L1rie No code; Descrt 1«io � x +Type fi` l Ra a { sfi k oY Wor ers Ext •, `. .�.. i,_s r_, r_,�_.�- ... .�.a_,...:.n t�,... .,. ....�,._ n�..�.F� _ ,_...»s.,a�a.fN.=a. .. l ,;. ,..._.,&.k.e<,urn,.=,. u� '�aa?"z. .. .,.x„ ....,. See Invoice Breakout Labor : $644.46 Gross Margin Percent @ 29%: $186.89 Equipment : $680.82 Gross Margin Percent @ 21%: $142.97V Material : $290.69 St Gross Margin Percent @ 21%: $61.04 Total: $2,006.87 st Signed By: az4co,t....„. Dated: 8/7/2019 Auden Schilder Project Manager ORDER CONFIRMATION Customer: Order No :06392739 OCEANSIDE CONSTRUCTION INC Order Date : 08/07/19 HD Fowler Company - Bellevue Due Date : 08/08/19 13440 SE 30th St Ord Writer :Todd Lewis BELLEVUE WA 98005 Warehouse :Bellevue Warehouse Salesperson :Todd Lewis Project: Carrier :WILL CALL LAKE YOUNGS CT SE Customer Reference: Line Order B/0 UoM Item/ Unit Extended T qty qty Description Price Price x 12 X 8 TEE 1 1 EA HPT53WT 188 . 090 188 . 09 12" X 8" ADS 1262WT INJECTION MOLDED WATER-TIGHT TEE WITH 3 GASKETS FOR "A" PROFILE 2 20 FT HPSL10 . 83 5 . 130 102 . 60 8"X 20 ' ADS BLUE-SEAL SOLID, WATER-TIGHT , AASHTO M252, TESTABLE, TYPE "S" ,DUAL WALL, 08650020IB Sub Total 290 .69 Freight Tax 0 . 00 Grand Total 290 .69