HomeMy WebLinkAboutCO 1 CITY OF RENTON
Public Works Department CAG-19-152 , Co #1-19
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: Lake Youngs Ct SE Storm&Water Improvement Project CAG-19-152 C.O.# 1
..CONTRACTOR: Oceanside Construction, Inc.
SUMMARY OF PROPOSED CHANGE:
Provide all labor,equipment,subcontracting, bonding, insurance for the complete work required for the extra •
work as outlined below and shown in the contractor's proposal:
ITEM Alteration Under This Change Order Unit Qty. Unit Price Total Price
Field Work NEW ITEM: LS 1 $2,041.56 $2,041.56
Directive#5 See attached for Field Work Directive#5 and associated Force Account-5.
Field Work NEW ITEM: LS 1 $2,006.87 $2,006.87
Directive#6 See attached for Field Work Directive#6 and associated Force Account-6.
Total $4,048.43
ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE ESTIMATED CONTRACT
THIS ORDER TOTAL AFTER CHANGE
$501,986.60 $501,986.60 $4,048.43 $506,035.03
SIGNATURES:
Date: 91 r
Contractor:Project Engineer: A....0)./
/hp
�'RI" I p Date: � � 1
Approved By: Date: v(2���
Ron S aka,Utility Systems Director( O ' a AN
Approved �'h ok RC1n-
Approved By: k P� )110,9 r Date:
Greg Zimmer an PW Ad istr
Approved B• Date:
Shane Moloney,Renton City Atto y
Attest; Date:
Jason Seth,City Clerk
H:\File Sys\SWP-Surface Water Projects\SWP-27-Surface Water Projects(CIP)\27-4017 2617 Lake Youngs CT SE\1600
Construction\1606a-Change Orders\CO#1\CO#1-Oceanside Construction.doc\JHmc
•
•
• • �f I
Lake Youngs Ct SE Storm &Water
Project Name: Improvement Project CAG- 19- 152
Contractor: Oceanside Construction, Inc. _
Removal of Possible Concrete Duct
Subject: Bank Date: 8/01/2019
Scope:
On July 29th, 2019,while laying the proposed storm between EX. CB#3 and EX. MH#1, Oceanside
Construction, Inc. ran into a conflict with what appears to be a concrete duct bank above the existing gas.
There was concern that the concrete duct was encasing an existing utility. Prior to removing the concrete
duct bank a utility locate was required. PSE came out to the site on July 29th, 2019 and verified that they
did not have any active utilities within the concrete. On July 30th, 2019 a utility locate was performed. No
utility claimed that any active service was contained within the concrete.
At this time,the City of Renton is directing Oceanside Construction, Inc.to move forward with removing
the concrete in conflict with the proposed storm as necessary. If an active utility is impacted please
contact the inspector for further instruction.
Attachment(s):
N/A
Contractor Acknowledgement:
By:
Contractor Signature Date
Title ICJ
'"T J 08/O 1/19
By:
JARED MCDONALD, PE
Signature Date
City of Renton Project Manager
THIS FIELD WORK DIRECTIVE DOES NOT PROVIDE FOR EITHER A TIME EXTENSION OR A CHANGE IN THE CONTRACT
PRICE. LABOR, EQUIPMENT,AND/OR MATERIAL OUTLINED IN THIS FIELD WORK DIRECTIVE SHALL BE PAID BY BID
ITEM(S)OR A CHANGE ORDER SHALL BE DEVELOPED FOR TIME EXTENSION OR CONTRACT PRICE INCREASES. ANY
PROTEST TO THE FIELD WORK DIRECTIVE SHALL FOLLOW 1-04.5 OF THE WSDOT STANDARD SPECIFICATIONS.
NO EXCEPTIONS TAKEN.
-JM,COR,8/07/19
r �� _ Oceanside Construction Inc.
�l.
�, ,1;r" 1511 Mt. Baker Hwy Bellingham, WA. 98226
Phone 360-933-1728 Fax 360-93 -4152
Force Account
201903 — Lake Youngs Ct. SE Storm Et Water Subject: Removal of CDF from in Front of Ex.
Improvements CB#3
To Jared McDonald Number: FA-5
City of Renton Revision No. : 0
1055 South Grady Way, 5th Floor Date: 8/5/2019
Renton, Washington 98057 Field Work Order /
Work Type:
425-430-7293 T>*M
Days Valid: 5
Return To Auden Schilder
Oceanside Construction Inc
(360) 933-1728
asatosc@yahoo.com
Scope Of Work / Time Extension Request
Due to unforeseen conditions within the intersection while installing the 8"C900 storm pipe, Oceanside was requested
to remove CDF duct bank in front of Ex. CB#3 per FWD#5.
Details
£. 3 + a Z xP , '+ ,�`" r }.. b r
1,Mv' � k kid . - r`.e � t�`v+ a°`",`��4�'a'• a2�F
Line Igo Code.` Desc ption t Type l Ra e ' �' / Hrs Workers Ex
A-8-201903 Shovel , Excavator,
2.50
- MINOR Backhoe, Tractors Labor $73.25 1.00 $183.13
001 CHANGE i Under 15 TN sit Hrs
Cory
A-8-201903
- MINOR Loader, Overhead 2.50
Labor $73.81 1.00 $184.53
002 CHANGE Under 6 Yards Hrs
Steve �/
A-8-201903
- MINOR TCS Labor $51.55 2.50 1.00 $128.88
003 CHANGE Hrs
Kris
,f�
`F��a. ?r�r y `kS v t ,»r; .ix#'emu x`�* Lek 0J xr=14: .3 a ✓n g ," + u.'',+ a 4irgp,,r-: ' . ` w ;
,t' 1 ;: "f SA,X :' - ',1'" .€4*,', +'f-1: ',t '- i'' '4'«x. ''S1 .Y.O. COS -'''' Q 'p,�,. F '+. 'a' > d i
1 O� ,COde� . Des'rlp re ft �3, £ *ate 4 40 r ,, Or ;f
r.,:?Pjie: .�x: es 't °.,+:�"�„a, aid. '�r.'r a..*-,- >n3, ..v,e 'n;Aft ,k, s. & —b s, �'.v. .c.._ ,. :,�i�;`a x.�':
A-8-201903
- MINOR Flagger v Labor $48.33 2.50 1.00 $120.83
004 CHANGE V Y
Drew
A-8-201903
2.50
- MINOR Dump Truck Solo Labor $66.51 �s 2.00 $332.55
005 CHANGE
Tom / Ty
A-8-201903
- MINOR General Laborer Labor $56.65 .0 1.00 $141.63
006 CHANGE
John W
A-8 201903 Kubota KX121-3 with
007 - MINOR Equipment $43.75 2.50 $109.38
CHANGE bucket
A-8-201903
- MINOR 2007 Hitachi ZX135 Equipment $68.18 2.50 - $170.45
008 CHANGE
Standby
A-8-201903
- MINOR 2002 Mack Dump' Equipment $61.23 2.50 - $153.08
009 CHANGE Truck `/
Standby
A-8-201903
010 - MINOR 2015 Chev 3500 with Equipment $36.25 2.50 - $90.63
CHANGE tools
Breakout
Labor : $1,091.54
Gross Margin Percent @ 29%: $316.55 V
Equipment : $523.53
Gross Margin Percent @ 21%: $109.94
Total: $2,041.56
Signed By: Dated: 8/5/2019
Auden Schilder
Project Manager
Lake Youngs Ct SE Storm &Water
Project Name: Improvement Project CAG- 19- 152
Contractor: Oceanside Construction, Inc.
Subject: CO#4 and CO#5 Date: 8/07/2019
Scope:
After discussing with City of Renton Maintenance and Oceanside Construction, Inc. it has been agreed that
both CO#4 and CO#5 are not required and will not be installed. Instead only a tee connection will be
provided.
It was also noted that the "insert-a-tee" connection that the contractor planned to use at CO#4 was not an
effective connection. Please provide a tee connection and replace the corresponding 8" PPP with an 8"
HDPE as submitted on by the contractor on 8/7/19.
Please bill new materials via a Force Account.
Attachment(s):
N/A
Contractor Acknowledgement:
By:
Contractor Signature Date
Title �
/ '/4 11 08/07/19
By:
JARED MCDONALD, PE
Signature Date
City of Renton Project Manager
THIS FIELD WORK DIRECTIVE DOES NOT PROVIDE FOR EITHER A TIME EXTENSION OR A CHANGE IN THE CONTRACT
PRICE. LABOR, EQUIPMENT,AND/OR MATERIAL OUTLINED IN THIS FIELD WORK DIRECTIVE SHALL BE PAID BY BID
ITEM(S)OR A CHANGE ORDER SHALL BE DEVELOPED FOR TIME EXTENSION OR CONTRACT PRICE INCREASES. ANY
PROTEST TO THE FIELD WORK DIRECTIVE SHALL FOLLOW 1-04.5 OF THE WSDOT STANDARD SPECIFICATIONS.
I'
NO EXCEPTIONS TAKEN.
-JM,COR,8/20/1 9
0: %' • Oceanside Construction Inc.
_`�` �''�;- 1511 Mt. Baker Hwy Bellingham, Wa4. 9'$22'6
Phone 36Q-933-1728 Fax 390-933-4152
Force Account
201903 — Lake Youngs Ct. SE Storm Ft Water Improvements Subject: Work Per FWD #6
To Jared McDonald Number: FA-6
City of Renton Revision No. : 2
1055 South Grady Way, 5th Floor Date: 8/7/2019
Renton, Washington 98057 Field Work Order /
Work Type: Tam425-430-7293
Days Valid: 5
Return To Auden Schilder
Oceanside Construction Inc
(360) 933-1728
asatosc@yahoo.com
Scope Of Work / Time Extension Request
Due to unforeseen conditions on this day, Oceanside has tracked the work required to complete FWD#6. This is the
latest revision per email from Jared McDonald on 8/12/19.
Note that FA-7 also occurred on this date.
Details
`a" "y
Line Not Code x Descri t n 4 Type}` /R e / Hers ' FWorke s Ezt
A-8-201903 Shovel , Excavator,
2.00
- MINOR Backhoe, Tractors Labor $73.25V Hrs 2.00 $293.00
001 CHANGE Under 15 TN
Cory / Steve
A-8-201903
2.00
- MINOR Dump Truck Solo Labor $66.51 Hrs 1.00 $133.07�
002 CHANGE
John W
A-8-201903
003 MINOR Pipe Layer Labor $57.67 2.00 1.00 $115.34
Hrs
CHANGE
x ; s,z ta.*.tiY��; a yx°;-�- z�t�k �7�5 �. ,, c t� 'lei` �'=� t� ; ar �,."'e ss� ': "s,
t ' ''- '�-f�`. it 2^ F mom, a e. ; ,�M<A 5 ii s�'�€-u �, i x, a Yz.ra. >.+ad'cd, a14 i". " a
k �,r -,r YM _„.i. :',a"X,t i f sY r`t i a i L ilia' ,a'a A »#COst''1 i,'§'`r.: -- 4 S'. C.�
�'� -.� '�'y ��#^ .C., f� .� y.r.`'" �vs..r"^2' j 3'+ ;'�k� �h�F;s��^��i,� az�.> v � , r� - �""'�.t� �� � n
Line No ri Co a Descr pt o �, kiSip ,< i'_3.°t ,,a.Baas L _y i sib Vs orkers `f` E tp
Drew
A-8-201903
- MINOR TCS Labor $51.55, 2.00
1.00 $103.10
004 CHANGE V Hrs
Kris
A-8-201903
- MINOR 2007 Hitachi ZX135 Equipment $68.18 2.00 - $136.36
005 CHANGE V
Standby
A-8-201903
2002 Mack Dump
- MINOR Equipment $61.23 2.00 - $122.46
006 CHANGE Truck V
Standby
A-8-201903
- MINOR 2011 Hitachi ZX120-3 Equipment $65.77 2.00 - $131.54�
007 CHANGE
Standby
A-8-201903
- MINOR 2015 Chev 3500 with Equipment E ui $29.00 2.00 - $58.00
008 tools q p
CHANGE
Standby
A-8-201903
- MINOR JD 085 Excavator Equipment $35.00 2.00 - $70.00
009 CHANGE
Standby
A-8-201903
- MINOR 2006 Chev Silverado Equipment $20.00 2.00 - $40.00
010 CHANGE
Standby
A-8-201903
1990 Peterbuilt 12 CY
- MINOR Equipment $61.23 2.00 - $122.46
011 CHANGE Dump Truck
Standby
Iv 1.00
012 Tee and HDPE Material $290.69 - $290.6�
EACH
%
„, C g .s 2 a x
�'htiAry1. �� G , y`G� .d ETYX�'�' � : 'Fk
�.��� �o- �3{y�'`"z"` :. `� ��K�.� �;, �'.�� ���:. s� $ �'k 4�' A�'�iys�� .s�*'*�`�'.1 �"3�
L1rie No code; Descrt 1«io � x +Type fi` l Ra a { sfi k oY Wor ers Ext
•, `. .�.. i,_s r_, r_,�_.�- ... .�.a_,...:.n t�,... .,. ....�,._ n�..�.F� _ ,_...»s.,a�a.fN.=a. .. l ,;. ,..._.,&.k.e<,urn,.=,. u� '�aa?"z. .. .,.x„ ....,.
See Invoice
Breakout
Labor : $644.46
Gross Margin Percent @ 29%: $186.89
Equipment : $680.82
Gross Margin Percent @ 21%: $142.97V
Material : $290.69 St
Gross Margin Percent @ 21%: $61.04
Total: $2,006.87 st
Signed By: az4co,t....„.
Dated: 8/7/2019
Auden Schilder
Project Manager
ORDER CONFIRMATION
Customer: Order No :06392739
OCEANSIDE CONSTRUCTION INC Order Date : 08/07/19
HD Fowler Company - Bellevue Due Date : 08/08/19
13440 SE 30th St Ord Writer :Todd Lewis
BELLEVUE WA 98005 Warehouse :Bellevue Warehouse
Salesperson :Todd Lewis
Project: Carrier :WILL CALL
LAKE YOUNGS CT SE
Customer Reference:
Line Order B/0 UoM Item/ Unit Extended T
qty qty Description Price Price x
12 X 8 TEE
1 1 EA HPT53WT 188 . 090 188 . 09
12" X 8" ADS 1262WT INJECTION
MOLDED WATER-TIGHT TEE WITH 3
GASKETS FOR "A" PROFILE
2 20 FT HPSL10 . 83 5 . 130 102 . 60
8"X 20 ' ADS BLUE-SEAL SOLID,
WATER-TIGHT , AASHTO
M252, TESTABLE, TYPE "S" ,DUAL
WALL, 08650020IB
Sub Total 290 .69
Freight
Tax 0 . 00
Grand Total 290 .69