HomeMy WebLinkAboutCM_Construction_Mitigation_FFCC_v1
September 5, 2019
Family First Community Center
PROPOSED CONSTRUCTION MITIGATION DESCRIPTION
Proposed Construction Dates
May 2020 – July 2021
Haul Routes
A construction plan indicating haul routes and hours, construction hours, and a traffic control plan will be
submitted to the Development Services Division for approval.
Haul Hours
Haul hours shall be restricted to the hours between eight-thirty (8:30) a.m. and three-thirty (3:30) p.m.,
Monday through Friday unless otherwise approved in advance by the Development Services Division.
Permitted Work Hours in or Near Residential Areas
Construction activities for the project shall be restricted to the following hours:
b. Construction activities shall be restricted to the hours between seven o’clock (7:00) a.m. and eight
o’clock (8:00) p.m., Monday through Friday. Work on Saturdays shall be restricted to the hours
between nine o’clock (9:00) a.m. and eight o’clock (8:00) p.m. No work shall be permitted on
Sundays.
Emergency Extensions to Permitted Work Hours
The Development Services Division Director is authorized to grant an extension of working time during an
emergency. An emergency shall include but is not limited to natural and manmade disasters.
Temporary Erosion Control
Temporary erosion control must be installed and maintained for the duration of the project. This work will
comply with the Surface Water Design Manual and must be approved by the Renton Development Services
Division. (Ord. 5526, 2-1-2010)
Hydroseeding Required:
a. Within thirty (30) days of completion of grading work, the applicant shall hydroseed or plant an
appropriate ground cover over any portion of the site that is graded or cleared of vegetation and
where no further construction work will occur within ninety (90) days.
b. Alternative measures to hydroseeding such as mulch, sodding, or plastic covering as specified in
the Surface Water Design Manual may be proposed between the dates of October 1st and April
30th of each year. Plastic covering may be used for soil protection for soils that will be utilized as
structural or fill materials only; provided, that soils that are to be reused for other purposes shall
be covered for no more than fourteen (14) days.
Family First Community Center
September 5, 2019
Page 2 of 2
c. The Development Services Division’s approval of this work is required prior to final inspection and
approval of the permit. (Ord. 5526, 2-1-2010; Ord. 5828, 12-12-2016)
Construction Debris
Construction debris, such as concrete, lumber, etc., will be removed and not buried on site.
Preliminary Traffic Control Plan
A traffic control plan will be submitted for review and approval by City of Renton after the General Contractor
is selected.