Department of Transportation
Supplemental Agreement Organization and Address
Number 4 KPG,PS, 3131 Elliott Avenue Suite 400 Seattle WA
Original Agreement Number 98121
CAG-17-149 Phone: 253-627-0720
Project Number Execution Date Completion Date
10/24/2017 12/31/20
Project Title New Maximum Amount Payable
Williams Ave S and Wells Ave S(Conversion) $1,295,042.18 + $49,876.00 =$1,344,918.18
Description of Work
Design of additional storm drainage and water main improvements,provide a more detailed technical
information report(TIR), as well as updating the current construction plans, quantities and cost estimate.
The Local Agency of City of Renton
desires to supplement the agreement entered in to with KPG, P.S.
and executed on 10/24/2017 and identified as Agreement No. CAG-17-149
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section 1, SCOPE OF WORK, is hereby changed to read:
The General Scope of Work of the Original Agreement is supplemented to include the attached Exhibit A.
II
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days
for completion of the work to read: Remains unchanged- 12/31/20
III
Section V, PAYMENT, shall be amended as follows:
See attached Exhibits A&D.
as set forth in the attached Exhibit A, and by this reference made a part of this supplement.
If you concur with this supplement and agree to the changes a tated above, lease sign in thG,AIkepI i'atq
spaces below and return to this office for final action. .���OV\9 ��lbd,a��i,�/
By: _----Jason rrtz , KPG By:
Denis L w, Mayor IfV
C -� ATTEST: � �{O ds=
ultant gnature ili � 'sx�
Jaso A. Seth, it , )5,,,,,� rj
to
DOT Form 140-063
Revised 09/2005
EXHIBIT A
CITY OF RENTON
WILLIAMS AVENUE S AND WELLS AVENUE S CONVERSION PROJECT
SUPPLEMENT 4—HOUSER WAY/BNSF ADDITIONAL UTILITY IMPROVEMENTS
CAG 17-149
SCOPE OF WORK
September 16, 2019
A. PROJECT BACKGROUND/DESCRIPTION
During the Final Design phase of the Williams Avenue S and Wells Avenue S Conversion Project
— Houser Way/BNSF Improvements, the City of Renton ("City") determined that additional
storm drainage and water main improvements should be constructed as part of that project,
beyond what was included in Supplement 2. In addition, based on the City's review of the 60%
submittal, a more detailed surface water technical information report (TIR) document will be
required, beyond the abbreviated technical memorandum included in Task 22.2.
The City has requested that KPG ("Consultant")enter into a supplemental agreement to design
these additional facilities, add additional plan sheets, and make revisions to the current plans,
quantities, and estimates.
B. KPG DELIVERABLES
Deliverables prepared by the Consultant are identified at the end of each Work Element (WE).
C. CITY OF RENTON PROVIDED ITEMS:
The City of Renton will be responsible for the following:
❑ Submittal reviews, comments, and approvals (1 to 2 sets of comments per submittal)
❑ Meeting room arrangements
WORK ELEMENT 28—MANAGEMENT/COORDINATION/ADMINISTRATION
The Estimated project duration is 1.5 additional months.
28.1 The Consultant will provide continuous project management for the project duration
(estimate additional 1.5 month).The Consultant will prepare monthly progress reports
identifying work completed in the previous month, work in progress, upcoming work
City of Renton
Wells/Williams Conversion Project(CAG 17-149)
SUPPLEMENT 4—HOUSER WAY/BNSF ADDITIONAL UTLITY IMPROVEMENTS KPG
Project Number: 16125 1 September 2019
elements, and reporting of any delays, problems, or additional information needs.
These reports will be submitted with the Consultant invoices.
28.2 The Consultant will provide internal quality assurance/quality control (QA/QC) reviews
of all major deliverables prior to submittal to the City.
Work Element 25 Deliverables:
■ Monthly progress reports(2 months)
D. SCOPE OF WORK
WORK ELEMENT 29—ADDITIONAL UTILITY DESIGN—BNSF/HOUSER
The Consultant will coordinate with private utilities affected by the proposed design revisions.
Efforts included under this WE are as follows:
29.1 Design water main improvement on Williams Avenue S, including an encased crossing
below BNSF tracks. The following sheets will be added to the plan set:
u 1 Water Plan
❑ 1 Water Profiles
o 1 Water Details
29.2 Design storm drainage improvements on Williams Avenue S and Wells Avenue S.
Existing 8-inch storm drain pipe crossings below BNSF tracks will not be replaced. The
following sheets will be added to the plan set:
o 1 Storm Profiles
29.3 Consultant will revise specifications, quantities and cost estimates in support of the
100% Design changes.
Work Element 29 Deliverables:
• All revisions to the Plans, Quantities, and Estimates will be included in the 100%Deliverable
in WE 24.
• Pothole Data Sheets
Work Element 29 Assumptions:
• Existing 8-inch diameter storm drains beneath BNSF railroad tracks will remain in service.
WORK ELEMENT 30—STORMWATER TECHNICAL INFORMATION REPORT
The Consultant shall revise and expand the stormwater technical memorandum dated
4/30/2109 into a Technical Information Report (TIR) per the requirements of Section 2.3.1 of
City of Renton
Wells/Williams Conversion Project(CAG 17-149)
SUPPLEMENT 4—HOUSER WAY/BNSF ADDITIONAL UTLITY IMPROVEMENTS KPG
Project Number: 16125 2 September 2019
the 2017 Renton Surface Water Design Manual (RSWDM),as required by the City's stormwater
reviewer.The original scope of work for this memorandum (Task 22)assumed a brief technical
memorandum would be sufficient because the project area and impacts are minimal.
30.1 Consultant will prepare a surface water TIR to include the following information
required by RSWDM 2.3.1:
❑ Construction stormwater pollution prevention analysis and design
❑ Offsite analysis
❑ Existing project areas map
❑ Conveyance calculations (if required)
Work Element 30 Deliverables:
■ Draft TIR,pdf
■ Final TIR, pdf
ADDITIONAL SERVICES
The City may require additional services of the Consultant. The scope of these services will be
determined based on the unanticipated project needs or other considerations at the sole
discretion of the City. These services will be authorized under a future contract supplement if
necessary. At the time these services are required, the Consultant shall provide a detailed
scope of work and an estimate of costs. The Consultant shall not proceed with the work until
the City has authorized the work and issued a notice to proceed.
City of Renton
Wells/Williams Conversion Project(CAG 17-149)
SUPPLEMENT 4—HOUSER WAY/BNSF ADDITIONAL UTLITY IMPROVEMENTS KPG
Project Number: 16125 3 September 2019
EXHIBIT D
PRIME CONSULTANT COST COMPUTATIONS
Client City of Renton ICES G
Project Williams Ave Sand Wells Ave S Conversion Project-Houser WayfEINSF Additional Utility Improvements-Sapp 4 Interdisciplinary Design
11PG PROJECT NUMBER:16125
P rY 9
DATE: September,2019
' Labor Hour Estimate
- Total Hours and Labor Fes
PrincipalEngineering Sr.Engineer Construction Sr.Trs W nsp. Project Design Architecture Survey Engineering Emate by Teak
•
. Mgr Mgr Planner Engineer Engineer Technician II Technician Technician Survey Crawl Survey Crew II Office AdMn
•
Sr.Coast Mgr Aviation Mgr urban Design Sr.Architect Project Resident Project LA CAD Architecture Construction
Mgr Surveyor Engineer Technician Technician Admih
WE No. WE Description Survey Mgr- Archdtttura CADMgr
Construction Documentation' Landscape - Construction
Mgr Office Eng Specialist Architect Technician
nspmtation
Sr.Inspector Sr.Admin ha Plermer Technician
• Inspector
$ 225610 $ 202.00, $ 184.00 $ 163.00 $ 156.00 $ 141.00 3 123.00 $ 111.00 $ 112.00 $ 104.00 $ 185.00 $ 21540 $ 9200 Noun Fee
WE 28-Additional Utility Design-BNSF/Houser .
28.1 Coordination and Project Management 1 2 3 $ 428.00
28.2 OA/CC 8 8 8 24 $ 4,218.00
Task Total 0 9 8 0 o a 0 0 2 0 0 0 0 27 $ 8842.00 .
WE 28-Additional Utility Design-BNSF/Houser .
28.1 Design Water Main Improvements 2 12 38 8 60 $ 8,866.00
•
28.2 Design Storm Drainage Improvements 2 8 24 34 $ 4,946.00
28.3 Revise Specifications,Quantities and Estimates 2 4 4 e 2 18 $ 2,894.00
Task Total 0 0 24 4 0 44 28 0 a 0 0 0 0 112 $ 18,708.00
WE 29-Stonrtwater Technolal Information Repoli .. .
29.1 [Prepare TIR 1 4 20 8 31 $ 4,526.00
Task Total 0 1 4 0 0 20 a 0 0 0 8 0 0 31 $ 8528.00
Total Labor Hours and Fee 0 7 28 4 0 - 64 32 0 8 0 0 0 0 143 $ 25,876.00.
- Subconsuitants -
Potholing-24(5100R$ 2y000.00
Subtotal E 24,000.00
Total Subeoneultant Expense$ 24,000.00
' - Reimbursable Direct Non-Salary Costs
Mile at current IRS rate$
Reproduction Allowance $ -
' Total Reimbursable Expanse$ -
7otal Estimated Budget $ 49,878.00
FEE ESTIMATE 9/18/2019
•
February 21, 2019
Keith Woolley
City of Renton
Public Works-5`h Floor
1055 S Grady Way
Renton,WA 98057
Re: KPG Project Team Commitment—Houser Way/BNSF Complete Streets
Dear Mr.Woolley:
KPG is committing for the duration of the project the discipline leads listed below. These professionals
will not be replaced without advance notification and subsequent authorization from the City.
Employees Title
Sessyle Asato CIA/QC Manager
Jason Fritzler Project Manager
Olivia Paraschiv Engineering Lead
Kirk Smith Stormwater Lead
Ray Edralin Stormwater Engineer
Jan Ciganik Signal/Illumination/ITS Lead
Elizabeth Gibson Landscape/Irrigation Lead
Phuong Nguyen Urban Design Lead
Coreen Schmidt LA
Hidemi Tsuru Signal/Lighting Engineer
George Hilen Lighting Engineer
Justin Wu Roadway Engineer
Judy Johnson Landscape Tech
Danielle Winklemann Admin
Terri Simms Admin
Michelle Torres Admin
Vonnie Stockman CAD Tech
Daniel Clark CM Lead
Sincerely,
Jason Fritzler, PM KPG •
L