HomeMy WebLinkAbout20191014155009.pdfE.a rth
Solution
MV11t,
Earth Solutions NW, LLC
LETTER OF TRANSMITTAL
To: RJ Development
401 Central Street SE
Olympia, WA 98501
Attn: Mr. Duane Meyer
Email: duane accrete.build
No. of
Date: 10/14/19
ESNW No.: ES -
Project: Weatherly Int.
Comments:
No -
1:
John Wilson
ATTN:
_johnw@rinocon.com
2:
Mark Richardson
ATTN:
mark accrete build
3:
Jeff Brain
ATTN:
eff accrete.build
4:
Jennifer Vociele
ATTN:
ennifer accrete. build
5:
Jonathan Chavez
ATTN:
'chavez rentonwa. ov
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
1805 — 13 6t' PI NE, Suite 201 Bellevue, WA 98005
(425) 284-3300 FAX (425) 449-4711 Toll Free (866) 336-8710
Earth Solutions NWLLC Field Rep
AK
t i 1805 136"' Place NE, FAX: Time On Site
6L NWac I Suite 201 (425) 449-4711
Bellevue, WA 98005 TOLL FREE:
(425)449-4704 (866)366-8710 2:30 PM
DAILY FIELD REPORT Travel Time
1.25 Hr. RT
Project Name Job Location
Weatherly Inn 4500 Talbot Rd. S., Renton, WA
General Contractor General Contractor's Superintendent
LGrading Contractor Grading Foreman
Rino Construction I Rod
Are approved Plans/Permits onsite F� YES ❑ NO Project No.
Test Test Location (Storm Backfill)
Number
39 See map for approximate location
40 See map for approximate location
Elevation
Project No.
0895.06
Page of
1/2
Report No.
46
Time Off Site
Date
Day of Week
3:30 PM
10/7/19
Weather
Monday
60s°F, Clear
Client / Owner
RJ Development, LLC
Received Onsite By
Checked By
Permit No
Reference Maximum Fill Test Dry % of
Compaction Dry Density Moisture Density Maximum
Curve lbs./cu.ft. % lbs./cu.ft. Dry Density
-2' 1 130.7P11.7
2.8 124.8 96
SG j 1 130.7 125.2 96
At the client's request, ESNW rep was onsite to observe and test storm line backfill, storm water discharge, vault
excavation and earthwork activities.
Storm Line Backfill
While onsite, rep observed contractor use a large excavator to excavate a storm line (W3'xD5'). Rep observed
contractor place a 12" corrugated pipe at the toe of the trench. Rep observed contractor bedding the pipe in a 12" lift
of pea gravel. Rep observed contractor place brown silty sand with gravel material in loose 12"-18" lifts and compacting
with a hoe pack. Rep took compaction tests on backfill and observed material to be adequate of at least 95% of its
maximum dry density (130.7 lbs./cu. ft.).
Vault Excavation
Rep observed contractor grading the vault excavation to design elevation with a large excavator. Rep observed the
south slope to be near vertical, the east and north slope to be 1:1 (H:V) to a near 7' vertical toe, and the west slope to
be (H:V) to a near 3' vertical toe. Although over -steepened, slopes are stable in current configuration and stable to
work within. The contractor is responsible for providing all safety measures in accordance with state and federal
regulation.
ESNW rep will return to observe earthwork activities when requested by client.
Andrew Kimn, Field Technician, 206-430-9183
COPY TO: CONTINUED ON NEXT PAGE
Grading Contractor
Rino Construction
Grading Foreman
Rod
Project No.
Earth Solutions NW«C
Field Rep.
1 2/2
Time Off Site
AK
Sol t
1805 136"' Place NE, FAX:
Time On Site
Suite 201 (425) 449-4711
61L
Bellevue, WA 98005 TOLL FREE:
2:30 PM
(425)449-4704 (866)366-8710
Travel Time
DAILY FIELD REPORT
1.25 Hr. RT
Project Name
Job Location
Weatherly Inn
4500 Talbot Rd. S., Renton, WA
General Contractor
General Contractor's Superintendent
Grading Contractor
Rino Construction
Grading Foreman
Rod
Project No.
Page of
0895
1 2/2
Time Off Site
Date
3:30 PM
10/7/19
Weather
60s°F, Clear
Client / Owner
RJ Development, LLC
Received Onsite By
Checked By
Are approved Plans/Permits onsite f-1 YES F] NO Project No, Permit No.
COPY TO:
Report No.
46
Day of Week
Monday
CONTINUED ON NEXT PAGE
u�
Earth Solutions NW«C Field Rep
AK
Solutions 1805136 th Place NE, FAX: Time On Site
NWLLc Suite 201 (425) 449-4711
Bellevue, WA 98005 TOLL FREE:
(425) 449-4704 (866) 366-8710 11:00 AM
DAILY FIELD REPORT Travel Time
1.25 Hr. RT
Project Name
Weatherly Inn
General Contractor
Job Location
4500 Talbot Rd. S., Renton, WA
General Contractor's Superintendent
Grading Contractor Grading Foreman
Rino Construction I Rod
Are approved Plans/Permits onsite ❑ YES ❑ NO Project No.
Project No Page of Report No.
0895.06 1/1 47
Time Off Site Date Day of Week
12:30 PM 1 10/8/19 Tuesday
Weather
50s°F, Rain
Client / Owner
RJ Development, LLC
Received Onsite By
Checked By
Permit No.
L4, 1 a), 3 I
At the client's request, ESNW rep was onsite to observe and test storm line backfill, storm water discharge, rockeries,
vault excavation and earthwork activities.
Storm Line Backfill
While onsite, rep observed contractor use a large excavator to excavate a storm line (W3'xD5'). Rep observed
contractor place a 12" corrugated pipe at the toe of the trench. Rep observed contractor bedding the pipe in a 12" lift
of pea gravel. Rep will return tomorrow, Wednesday, October 9, 2019, to observe and test storm line backfill as
needed.
Storm Water Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment (<3
ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a PH level of 6.5.
Contractor expressed plans to build pump and meter before pumping water out of baker tanks.
Rockeries
Rep observed rockery contractor excavating and cutting the keyway for the first-tier rockery located in the southeast
corner of the site. Rep observed contractor use a large excavator for the excavation.
Vault Excavation
Rep observed contractor grading the vault excavation to design elevation with a large excavator. Rep observed the
south slope to be near vertical, the east and north slope to be 1:1 (H:V) to a near 7' vertical toe, and the west slope to
be (H:V) to a near 3' vertical toe. Although over -steepened, slopes are stable in current configuration and stable to
work within. The contractor is responsible for providing all safety measures in accordance with state and federal
regulation.
ESNW rep will return to observe earthwork activities when requested by client.
4-1-11 �_
Andrew Kimn, Senior Field Technician, 206-430-9183
COPY TO:
CONTINUED ON NEXT PAGE
Earth Solutions NWLLC
t 1805 136" Place NE, FAX:
Suite 201 (425) 449-4711
Bellevue, WA 98005 TOLL FREE:
(425)449-4704 (866)366-8710
DAILY FIELD REPORT
Project Name
Weatherly Inn
General Contractor
Grading Contractor
Rino Construction
Field Rep-
AK
Project No
0895.06
Page of
1/1
Report No.
48
Time On Site Time Off Site
Date
Day of Week
11:45 AM 12:45 PM
10/9/19
Wed
Travel Time
Weather
1.25 Hr. RT
60s°F, Clear
Job Location Client / Owner
4500 Talbot Rd. S., Renton, WA RJ Development, LLC
General Contractor's Superintendent Received Onsite By
Grading Foreman
Rod
Are approved Plans/Permits onsite ❑ YES ❑ NO Project No.
Checked By
I6't�
Permit No
At the client's request, ESNW rep was onsite to observe and test sewer line backfill, rockeries, vault excavation and
earthwork activities.
Sewer Line Backfill
While onsite, rep observed contractor use a large excavator to excavate a sewer line. Contractor expressed plans to
continue working on sewer line excavation and backfill tomorrow, Thursday, October 10, 2019. Rep will return to
observe and test the backfill as needed.
Rockeries
Rep observed rockery contractor excavating and cutting the keyway for the first-tier
rockery located in the southeast corner of the site. Rep observed contractor use a
large excavator for the excavation. Rep used a '/2" steel t -probe and observed the
keyway for the rockery located at the southeast quadrant of the site. Rep observed
the keyway to be very dense, firm, unyielding, and suitable for support of the
proposed rockery. Rep observed contractor place a few courses of rocks. Rep
observed contractor place a 4" perforated drain pipe behind the first course of the
rockery, embed the pipe in an 18" lift of 1"-2" wash rock, geotextile, then backfill over
the geotextile with 2"-4" quarry spalls.
Vault Excavation
Rep observed contractor grading the vault excavation to design elevation with a
large excavator. Rep observed the south slope to be near vertical, the east and
north slope to be 1:1 (H:V) to a near 7' vertical toe, and the west slope to be (H:V)
to a near 3' vertical toe. Although over -steepened, slopes are stable in current
configuration and stable to work within. The contractor is responsible for providing
all safety measures in accordance with state and federal regulation.
ESNW rep will return to observe earthwork activities when requested by client.
Andrew Kimn, Senior Field Technician, 206-430-9183
COPY TO:
-'k t4
$,
L��'- Sh � if•E•iM, ate..
CONTINUED ON NEXT PAGE U
{
At the client's request, ESNW rep was onsite to observe and test sewer line backfill, rockeries, storm water discharge,
vault excavation and earthwork activities.
Sewer Line Backfill
While onsite, rep observed contractor use a large excavator to excavate a sewer line. Contractor expressed plans to
continue working on sewer line excavation tomorrow, Friday, October 11, 2019. Rep will return to observe and test
the backfill as needed.
Rockeries
Rep observed rockery contractor excavating and cutting the keyway for the first-tier rockery located in the southeast
corner of the site. Rep observed contractor use a large excavator for the excavation. Rep used a '/z" steel t -probe
and observed the keyway for the rockery located at the southeast quadrant of the site. Rep observed the keyway to
be very dense, firm, unyielding, and suitable for support of the proposed rockery. Rep observed contractor place a
few courses of rocks. Rep observed contractor place a 4" perforated drain pipe behind the first course of the rockery,
embed the pipe in an 18" lift of 1 "-2" wash rock, geotextile, then backfill over the geotextile with 2"-4" quarry spalls.
Storm Water Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment (<3
ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a PH level of 6.5.
Vault Excavation
Rep observed contractor grading the vault excavation to design elevation with a large excavator. Rep observed the
south slope to be near vertical, the east and north slope to be 1:1 (H:V) to a near 7' vertical toe, and the west slope to
be (H:V) to a near 3' vertical toe. Although over -steepened, slopes are stable in current configuration and stable to
work within. The contractor is responsible for providing all safety measures in accordance with state and federal
regulation.
ESNW rep will return to observe earthwork activities when requested by client.
Andrew Kimn, Senior Field Technician, 206-430-9183
COPY TO:
CONTINUED ON NEXT PAGE U
Earth Solutions NWLLC
Field Rep,
Project No. Page of
Report No.
AK
0895.06 1/1
49
t
1805136 1h Place NE, FAX:
Time On Site
Time Off Site Date
Day of Week
Suite 201 (425) 449-4711
Bellevue, WA 98005 TOLL FREE:
12:00 PM
1:30 PM 10/10/19
Thursday
(425)449-4704 (866)366-8710
DAILY FIELD REPORT
Travel Time
Weather
1.25 Hr. RT
60s°F, Clear
Project Name
Job Location
Client / Owner
Weatherly Inn
4500 Talbot Rd. S., Renton, WA
RJ Development, LLC
General Contractor
General Contractor's Superintendent
Received Onsite By
Grading Contractor
Grading Foreman
Checked By
��/ 1�
Rino Construction
Rod
Are approved Plans/Permits
onsite ❑ YES ❑ NO Project No.
Permit No
At the client's request, ESNW rep was onsite to observe and test sewer line backfill, rockeries, storm water discharge,
vault excavation and earthwork activities.
Sewer Line Backfill
While onsite, rep observed contractor use a large excavator to excavate a sewer line. Contractor expressed plans to
continue working on sewer line excavation tomorrow, Friday, October 11, 2019. Rep will return to observe and test
the backfill as needed.
Rockeries
Rep observed rockery contractor excavating and cutting the keyway for the first-tier rockery located in the southeast
corner of the site. Rep observed contractor use a large excavator for the excavation. Rep used a '/z" steel t -probe
and observed the keyway for the rockery located at the southeast quadrant of the site. Rep observed the keyway to
be very dense, firm, unyielding, and suitable for support of the proposed rockery. Rep observed contractor place a
few courses of rocks. Rep observed contractor place a 4" perforated drain pipe behind the first course of the rockery,
embed the pipe in an 18" lift of 1 "-2" wash rock, geotextile, then backfill over the geotextile with 2"-4" quarry spalls.
Storm Water Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment (<3
ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a PH level of 6.5.
Vault Excavation
Rep observed contractor grading the vault excavation to design elevation with a large excavator. Rep observed the
south slope to be near vertical, the east and north slope to be 1:1 (H:V) to a near 7' vertical toe, and the west slope to
be (H:V) to a near 3' vertical toe. Although over -steepened, slopes are stable in current configuration and stable to
work within. The contractor is responsible for providing all safety measures in accordance with state and federal
regulation.
ESNW rep will return to observe earthwork activities when requested by client.
Andrew Kimn, Senior Field Technician, 206-430-9183
COPY TO:
CONTINUED ON NEXT PAGE U
Earth Solutions NW«C
~ 1805 13611 Place NE, FAX:
Suite 201 (425) 449-4711
Bellevue, WA 98005 TOLL FREE:
(425) 449-4704 (866) 366-8710
DAILY FIELD REPORT
Project Name
Weatherly Inn
General Contractor
Grading Contractor
Rino Construction
Field Rep.
AK
Project No
0895.06
Page of
1/1
Report No.
50
Time On Site
Time Off Site
Date
Day of Week
10:30 AM
12:00 PM
10/11/19
Friday
Travel Time
Weather
1.25 Hr. RT
Job Location
4500 Talbot Rd. S., Renton, WA
General Contractor's Superintendent
Grading Foreman
Rod
Are approved Plans/Permits onsite ❑ YES ❑ NO Project No.
J 60s°F, Clear
Client / Owner
RJ Development, LLC
Received Onsite By
Checked By vT I ,�I
1 `�),
Permit No.
At the client's request, ESNW rep was onsite to observe and test rockeries, storm water discharge, vault excavation
and earthwork activities.
Rockeries
Rep observed rockery contractor excavating and cutting the keyway for the first-tier rockery located in the southeast
corner of the site. Rep observed contractor use a large excavator for the excavation. Rep used a '/2" steel t -probe
and observed the keyway for the rockery located at the southeast quadrant of the site. Rep observed the keyway to
be very dense, firm, unyielding, and suitable for support of the proposed rockery. Rep observed contractor place a
few courses of rocks. Rep observed contractor place a 4" perforated drain pipe behind the first course of the rockery,
embed the pipe in an 18" lift of 1"-2" wash rock, geotextile, then backfill over the geotextile with 2"-4" quarry spalls.
Storm Water Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment (<3
ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a PH level of 6.5.
Vault Excavation
Rep observed contractor grading the vault excavation to design elevation with a large excavator. Rep observed the
south slope to be near vertical, the east and north slope to be 1:1 (H:V) to a near 7' vertical toe, and the west slope to
be (H:V) to a near 3' vertical toe. Although over -steepened, slopes are stable in current configuration and stable to
work within. The contractor is responsible for providing all safety measures in accordance with state and federal
regulation.
ESNW rep will return to observe earthwork activities when requested by client.
f
Andrew Kimn, Senior Field Technician, 206-430-9183
f
COPY TO.
CONTINUED ON NEXT PAGE ❑