Change Order No. 2
Contract Title: NE 31st St Bridge Replacement Project
Contractor: Hamilton Construction Co.
Contract No.: CAG 18-001
Federal Aid No. : BROS-1070(009)
ISI Ordered by Engineer
p Proposed by the Contractor(VECP)
❑ Unilateral
Original Contract Amount: $1,255,999.00 Original Contract Working Days: 80
Current Contract Amount: $1,256,699.00 Current Contract Working Days: 87*
Estimated Net Change This Order: -$5,300.00 Added Working Days: 0
New Contract Amount: $1,251,399.00 Total Contract Working Days: 87
!Note:Minor Change No 1 added 2 Working Days,Minor Change No.2 added 2 Working Days,Minor Change No.3 added 3 Working Days.
Prepared By: Issue y:
(Oz.,jz...
mghl
I Re ident Engineer Date ngineer(City o Renton Transportation Date
04) of tren.44•1 ProJa f MGAGJyer Design Manager)
Reviewed By: Consent By:
Engineer of Record Date Surety(Greater than 25%cost and/or 20% Date
time increase)
Rev ed By: Endorsed By:
f z-t—i /� 0 /1�
City of Renton Prejeet Manager Date Contractor Date'
Tfarls, Des% h Executed By:
Reviewed By:
10
City Attorney(Greater than$3s,o0D Date City Rent Public orks at
and/or change in scope) Admin trator/Mayor
Change Order No. 2
Contract Title: NE 31st St Bridge Replacement Project
Contract No. CAG-18-001 Page 1 of 3
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
• Delete the following bid item from the contract:
o Bid Item No. 40, FURNISHING CONC. PILING (24" DIA),
Quantity = 210 L.F., Unit Price =$100.00 per L.F.
• Add the following bid item to the contract:
o Bid Item No. 2-40, FURNISHING CONC. PILING (24" DIA),
Quantity= 111.08 L.F., Unit Price =$141.75 per L.F.
Reason for Change:
Stiff soil conditions were encountered while driving the hollow steel sections for the concrete
piles. The ultimate bearing resistance for the piles was achieved. However, the driven depth of
the hollow steel sections did not reach the minimum tip elevations specified in the contract
plans. As a result, the adjusted final quantity of the bid item FURNISHING CONC. PILING (24"
DIA) is at 53% of the original Bid quantity. Pursuant to Section 1-04.6, the Contractor is entitled
to an equitable adjustment since the adjusted final quantity is less than 75% of the original Bid
quantity.
TABLE OF QUANTITIES FOR FURNISHING CONC. PILING (24" DIA)
Pile Number Plan Quantity (L.F.) Field Measured (L.F.) Quantity included in
Bid Item?
Abutment 1
1A 35 23.42 No. Test Pile.
1B 35 18.08 Yes.
1C 35 18.25 Yes.
1D 35 17.92 Yes.
Abutment 2
2A 35 15.75 Yes.
2B 35 18 Yes.
2C 35 23.08 Yes.
2D 35 24.17 No. Test Pile.
Total = 210 111.08
Materials:
N/A
Change Order No. 2
Contract Title: NE 31st St Bridge Replacement Project
Contract No. CAG-18-001 Page 2 of 3
Plans:
No changes were made to the drawings.
Adjustment:
This Change Order includes a significant change, Type B, as defined in Section 1-04.4. The
adjustment shall be made with a new unit price for the bid item. The estimate is attached.
Extension of Time:
The Time for Completion is extended 0 non-compensable Working Days in accordance with
Section 1-08.8.
Equitable Adjustment:
This Change Order includes an equitable adjustment in the new unit price. The new unit price
for the bid item is as follows:
• Bid Item No. 2-40, FURNISHING CONC. PILING (24" DIA), Unit Price = $141.75 per L.F.
Sections 1-04.4 and 1-04.5 of the 2016 WSDOT/APWA Standard Specifications shall govern
this Change Order.The Work of the referenced Contract is modified to include the changes
detailed herein.The payment provided for herein shall constitute the complete and final
settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all
other claims that may be made by the Contractor as a result of this change.
Attachments:
Forms to be attached to Change Order
❑ Plans
❑ Field Directive
❑ Change Order Quotation
❑ Estimated Change Order Cost
❑ Project Labor List
❑ Force Account Equipment Rate Request (DOT Form 422-010 EF)
❑ Equitable Adjustment Determination
Change Order No. 2
Contract Title: NE 31st St Bridge Replacement Project
Contract No. CAG-18-001 Page 3 of 3
Estimated Change Order Cost Change Order No. 2
Bid Item No. Description Quantity Unit Unit Price Estimated Cost
Force Account
Item description
Labor Estimate $0.00
Labor Markup 29% $0.00
Equipment _ Estimate $0.00
Equipment Markup _ 21% $0.00
Materials Estimate $0.00
Materials Markup 21% $0.00
Services Estimate $0.00
Services Markup 21% $0.00
Mobilization Estimate $0.00
Subcontractor Work Estimate $0.00
Subcontractor Markup 12%, 10%,7% $0.00
Bid Item Change
40 _FURNISHING CONC.PILING(24"DIA) -210 L.F. $100.00 -$21,000.00
2-40 FURNISHING CONC. PILING(24" DIA) 111.08 L.F. $141.75 $15,745.59
Equitable Adjustment
Per attached determination Estimate $0.00
Calculated Cost -$5,254.41
Estimated Change Order Cost -$5,300.00
Page 1 of 1