,cs Facilities Division CONTRACT NO: CAG-18-073 CO NO. 3
CONTRACT CHANGE ORDER(CO) PROJECTTITLE: Renton City Hall Phase 1-HVAC Upgrades
TO:McKinstry Essention LLC (CONTRACTOR)
The following mutually agreed to and Owner approved Change Order Proposal(s)are hereby incorporated by reference into •
the contract.
Description Amount This Change Order corrects an amount
Revision to correct original contract amount $ 45,000.00 typo in the original contract and provides
for the correct contract balance going
$ forward including the amounts in
• $ - Change Order 1 and Change Order 2.
•
$ -
1
$ -
CONTRACT SUM:
❑NO CHANGE
❑INCREASE OF: Forty-Five Thousand_Dollars and Zero Cents I $ 45,000.00 l
❑DECREASE (WASHINGTON STATE SALES TAX INCLUDED)
{
CONTRACT TIME:
❑' NO CHANGE
❑INCREASE OF: I 01
❑DECREASE CALENDAR DAYS
The foregoing amount covers everything required in connection with the change.All other provisions of the contract remain in full force and
effect.
CONTRACT SUMMARY(Internal Use Only)
ORIGINAL CONTRACT SUM
$ 1,883,631.00
PREVIOUS ADDITIONS/DELETIONS $ 106,108.75
PREVIOUS TOTAL $ 1,989,739.75
CHANGE AMOUNT THIS CHANGE ORDER $ 45,000.00
REVISED CONTRACT TOTAL $ 2,034,739.75
PERCENT TOTAL CHANGE FROM ORIGINAL 8.02%
NOTICE TO PROCEED DATE December 13,2018
PREVIOUS CONTRACT CALENDAR DAYS 749
PREVIOUS SUBSTANTIAL COMPLETION DATE December31,2020
REVISED CONTRACT CALENDAR DAYS THIS CHANGE ORDER 749
CURRENT SUBSTANTIA OMPLETI DATE December 31,2020NA
DES Acknowledgement Date " a„�Contractor
I%tir4
'O`1,1,, Contractor Acknowledgelment Date
The City of Renton hereby accepts the foregoing Chaff Lae Pegsal(sNistfoRjial acceptance constitutes a Change to the contract only
when authorizing sig tureisaffixed.In icesincorg"tiBgthis a rd�cpn$ituteacceptancebytheContractorastotal
reimbursement due c nection wit is Order.7 { = o _ 1 )
Mayor Denis Law Y✓AE'S (� (I
ff yl CreYk—
• .. •