CONTRACT: CAG-19-209 Rainier Ave North Culvert Improvement Project C.O.# 1
SWP-27-4031
CONTRACTOR: Nordvind Sewer Service, LLC.
SUMMARY OF PROPOSED CHANGE:
Extra Grout Concrete Mix $18,091.14
During project construction,a significant additional amount of grout concrete mix(1,266
gallons)was needed to repair the bottom of the existing 36"CMP Culvert prior to the
installation of the new Cure-In Place Pipe(CIPP).This was due to the existing CMP
culvert being in more deteriorated conditions than anticipated and the inability to •
completely CCTV prior to construction phase.The payment will be made in accordance
with the contractor's unit bid price.The work was performed on October 11,2019.
TOTAL CHANGE ORDER COST: $18,091.14
Additional Working Days added to the Contract for this Change Order: 1
ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE ESTIMATED CONTRACT
THIS ORDER TOTAL AFTER CHANGE
$106,75158 $106,751.58 $18,091.14 $124,842.72
SIGNATURES:
Contractor: I Date:
10/29/19
0 30 q
Project Manager: 1 /Date: fi/
Approved By: Date: 10/7/
RonEld Straka,U y Systems Di recto
Approved By: 9 cOf 3/0144/04_,
Date: l(l/1,/C(
Gregg Zimmet n,Prks Administrator !!
Approved By: Date:
Shane Moloney,City Attorn
•
H:\File Sys\SWP-Surface Water Projects\SWP-27-Surface Water Projects(CIP)\27-4031 Rainier&Benson Culvert Replacement\1600
Construction\Change Order\CO-1