AMENDMENT NO. 1 TO AGREEMENT FOR THE RAINIER AVE N.
AND BENSON RD. S. CULVERT REPLACEMENT PROJECTS
CAG-18-271
THIS AMENDMENT, dated November 6, 2019, is by and between the City of Renton (the "City"),
a Washington municipal corporation, and CHS Engineers, LLC ("Consultant"), a Washington
Limited Liability Company. The City and the Consultant are referred to collectively in this
Amendment as the "Parties." Once fully executed by the Parties,this Amendment is effective as
of the last date signed by both parties.
Whereas, the City engaged the services of the Consultant under Agreement CAG-18-271, dated
December 20, 2018,to provide necessary services for the for the Rainier Ave N. and Benson Rd.
S. Culvert Replacement Projects (referred to herein as the"Agreement");
Whereas,the Parties wish to amend the Agreement to change the time for performance in order
to complete all the work for the project.
NOW THEREFORE, It is mutually agreed upon that CAG-18-271 is amended as follows:
1. Time of Performance: Section 3, Time of Performance, is amended to extend that all
Work shall be performed by no later than December 31, 2020.
2. All terms of the Agreement not explicitly modified herein shall remain in full force and
effect and such terms shall apply to Work performed according to this Amendment as if
fully set forth herein.
IN WITNESS WHEREOF,the Parties have voluntarily entered into this Agreement as of the date
last signed by the Parties below.
CITY OF RENTON CONSULTANT
By: P. , By:
Gregg Zimm a van Henke
PW Adminis ator Principal
/))0/q /K;
Date Date
Approved as to Legal Form
Shane Moloney
City Attorney