CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: Cedar River Maintenance Dredge Project-Vegetation Management C.O.# 2
CAG-18-155
CONTRACTOR: Applied Ecology, LLC
SUMMARY OF PROPOSED CHANGE:
Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra
work as outlined below and shown in the contractor's proposal:
ITEM Alteration Under This Change Order Unit Qty. Unit Price Total Price
Trees REVISED ITEM: EACH -24 -$0.005 $0.12
Correct unit price of trees in Change Order#1 from$28.33 to$28.325
as agreed upon in the original contract.
Trees REVISED ITEM: EACH 21 $28.325 $594.82
Increased total number of trees to be installed from 36 to 57.
Shrubs REVISED ITEM: EACH 60 -$0.005 -$0.30
Correct unit price of shrubs in Change Order#1 from$18.33 to
$18.325 as agreed upon in the original contract.
Shrubs REVISED ITEM: EACH 600 $18.325 $10,995.00
Increased total number of trees to be installed from 710 to 1310.
Hydroseed REVISED ITEM: SF -7,340 $0.0005 -$3.67
Correct unit price of hydroseed in Change Order#1 from$0.20 to
$0.2005 as agreed upon in the original contract.
Hydroseed REVISED ITEM: SF 12,660 $0.2005 $2,538.33
Increased amount of hydroseed from 12,660sf to 25,320sf.
Live Stake REVISED ITEM: EACH 500 $7.50 $3,750.00
Increased amount of live stake from 65 to 565.
Invasive Species REVISED ITEM: Per 8 $7,200 $57,600.00
Control Increased number of monthly treatments from 6 to 14. treatment
H:\File Sys\SWP-Surface Water Projects\SWP-27-Surface Water Projects(CIP)\27-3634 Cedar River Maintenance Dredge\1604
Vegetation Management\2019\Change Order\CO#2\CO#2-Applied Ecology.doc
Term of REVISED ITEM:
Agreement Contract CAG-18-155 Term of Agreement(page 1,paragraph 4)shall
be extended from March 30,2020 to March 31,2022.
Sub Total $75,474.30
Sales Tax (10.0%) $7,547.43
Total $83,021.73
ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE ESTIMATED CONTRACT
THIS ORDER TOTAL AFTER CHANGE
$80,804.63 •.45 $83,021.73 $163,292.18
SIGNATURES:
Contractor: Justin How II Date: 12/4/19
Project Engineer: drAMI 4 • 4 Date: ia/1/If
Approved By: i' Date: 1'21tI ((q
Ron Straka,Utility Srs Director
Approved By: Date:
Gregg immerman,P ministrator
Approved B>C: OSe Date:
Sha( oloney,Rento Ci Attor y
Approved By: i �{i1 Date: _
1z l6
De is Law, r
Attest: Date:
/X�`�J
Jason S ,City Clerk
(-)a
* o
.47
�04,p TED Sip\•��
'''
�!luunllua\a
H:\File Sys\SWP-Surface Water Projects\SWP-27-Surface Water Projects(CIP)\27-3634 Cedar River Maintenance Dredge\1604
Vegetation Management\2019\Change Order\CO#2\CO#2-Applied Ecology.doc