Loading...
HomeMy WebLinkAboutCO 2 CAG-18-155, CO #2-19 CITY OF RENTON Public Works Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: Cedar River Maintenance Dredge Project-Vegetation Management C.O.# 2 CAG-18-155 CONTRACTOR: Applied Ecology, LLC SUMMARY OF PROPOSED CHANGE: Provide all labor, equipment, subcontracting, bonding, insurance for the complete work required for the extra work as outlined below and shown in the contractor's proposal: ITEM Alteration Under This Change Order Unit Qty. Unit Price Total Price Trees REVISED ITEM: EACH -24 -$0.005 $0.12 Correct unit price of trees in Change Order#1 from$28.33 to$28.325 as agreed upon in the original contract. Trees REVISED ITEM: EACH 21 $28.325 $594.82 Increased total number of trees to be installed from 36 to 57. Shrubs REVISED ITEM: EACH 60 -$0.005 -$0.30 Correct unit price of shrubs in Change Order#1 from$18.33 to $18.325 as agreed upon in the original contract. Shrubs REVISED ITEM: EACH 600 $18.325 $10,995.00 Increased total number of trees to be installed from 710 to 1310. Hydroseed REVISED ITEM: SF -7,340 $0.0005 -$3.67 Correct unit price of hydroseed in Change Order#1 from$0.20 to $0.2005 as agreed upon in the original contract. Hydroseed REVISED ITEM: SF 12,660 $0.2005 $2,538.33 Increased amount of hydroseed from 12,660sf to 25,320sf. Live Stake REVISED ITEM: EACH 500 $7.50 $3,750.00 Increased amount of live stake from 65 to 565. Invasive Species REVISED ITEM: Per 8 $7,200 $57,600.00 Control Increased number of monthly treatments from 6 to 14. treatment H:\File Sys\SWP-Surface Water Projects\SWP-27-Surface Water Projects(CIP)\27-3634 Cedar River Maintenance Dredge\1604 Vegetation Management\2019\Change Order\CO#2\CO#2-Applied Ecology.doc Term of REVISED ITEM: Agreement Contract CAG-18-155 Term of Agreement(page 1,paragraph 4)shall be extended from March 30,2020 to March 31,2022. Sub Total $75,474.30 Sales Tax (10.0%) $7,547.43 Total $83,021.73 ORIGINAL CONTRACT AMOUNT CURRENT CONTRACT AMOUNT ESTIMATED NET CHANGE ESTIMATED CONTRACT THIS ORDER TOTAL AFTER CHANGE $80,804.63 •.45 $83,021.73 $163,292.18 SIGNATURES: Contractor: Justin How II Date: 12/4/19 Project Engineer: drAMI 4 • 4 Date: ia/1/If Approved By: i' Date: 1'21tI ((q Ron Straka,Utility Srs Director Approved By: Date: Gregg immerman,P ministrator Approved B>C: OSe Date: Sha( oloney,Rento Ci Attor y Approved By: i �{i1 Date: _ 1z l6 De is Law, r Attest: Date: /X�`�J Jason S ,City Clerk (-)a * o .47 �04,p TED Sip\•�� ''' �!luunllua\a H:\File Sys\SWP-Surface Water Projects\SWP-27-Surface Water Projects(CIP)\27-3634 Cedar River Maintenance Dredge\1604 Vegetation Management\2019\Change Order\CO#2\CO#2-Applied Ecology.doc