HomeMy WebLinkAbout20191230104742.pdfEarth
�S�itution
NAV!
Earth Solutions NW, LLC
LETTER OF TRANSMITTAL
To: RJ Development Date: December 30, 2019
401 Central Street SE ESNW No.: ES -
Olympia, WA 98501 _._ Project: Weatherly Inr
Attn: Mr. Duane Meyer
Email: duane@accrete.build
No. of
Uoples Uate Description
1 12/23-12/24/19 Daily Field Report(s) # 100 & 101
Comments:
895.06
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G,-
1805 — 136"' PI NE, Suite 201 Bellevue, WA 98005
(425) 284-3300 FAX (425) 449-4711 Toll Free (866) 336-8710
CC:
1:
2:
3:
4:
5:
John Wilson
Mark Richardson
Jeff Brain
Jennifer Vo ele
Jonathan Chavez
ATTN:
ATTN:
ATTN:
ATTN:
ATTN
_lohnw[arrinocon.com
mark accrete. build
Jeffaccrete. build
jenniferQaccrete. build
jchavez rentonwa. gov
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G,-
1805 — 136"' PI NE, Suite 201 Bellevue, WA 98005
(425) 284-3300 FAX (425) 449-4711 Toll Free (866) 336-8710
Earth Solutions NWLLC
15365 NE 90`h Street, Suite 100
t Redmond, WA 98052
ESNW Rep.
I AK
Time On Site
Project No
0895.06
Time Off Site
Page
1/2
Report No.
100
Date
Day of Week
Main (425) 449-4704 1 Fax (425) 449-4711
Monday
www esnw com
11:45 AM
1:15 PM
12/23/19
DAILY FIELD REPORT
Travel Time
-
Weather
1.25 Hr. RT
40s°F, Overcast
Project Name
Job Location
Client/Owner
Weatherly Inn
4500 Talbot Rd. S., Renton, WA
RJ Development, LLC
Contractor #1
Rino Construction
Contact
Mike
Field Supervisor
LAC
Reviewed
j+ I�%Z°1
Contractor #2
Contact
Project Manager
Reviewed
Ray
Are approved plans/permits on site? Project No
Permit No
Supplementary Report:
At the client's request, ESNW rep was onsite to observe or test
pH of stormwater, footing excavations and
earthwork activities.
Test pH of Stormwater
While onsite, rep took pH tests to determine the acidity of stormwater. Rep took pH tests at the east end of the
quarry spall entrance and observed a pH level of 6.5/7 pH. At the west of the quarry spall entrance stormwater
(temporary) collection pit and observed a pH level of 9 pH. On the street, north and south of the west entrance,
rep took a pH tests and observed stormwater to be a 6.5/7 pH. Rep tested banker tanks with stormwater and
observed that contractor had added dry ice as recommended by ESNW. Rep tested a 6.5/7 pH in both baker
tanks which is compliant with required pH levels for sewer discharge. Rep observed that pH level was contained
onsite and that stormwater pH level in street was in compliance of required pH level at 6.5/7 pH.
Footing Excavations
Rep observed contractor removing form boards for the footings. Rep observed east slopes of the excavation to
be near vertical Rep observed that the east slopes of the excavation were near a 0.75:1 (H -.V) slope. Although
over -steepened, slopes are stable in current configuration and stable to work within. The contractor is responsible
for providing all safety measures in accordance with state and federal regulation. Rep observed that contractor
had sloped the southeast corner of the footing excavation to a 1:1 (H:V).
Midway at the east footings to —30' north of the corner, rep observed that material had sloughed. Rep observed
a seam and recommended that contractor excavate and remove excess material above the seam in the bank.
Rep observed using a medium sized excavator to remove the material above the footings in that designated
location. (See Image) Rep also observed contractor pumping stormwater that had been collecting in the footing
excavations to the baker tanks and the stormwater vault onsite. Rep discussed recommendations with Accrete
representatives onsite.
Rep recommended that contractor add crushed rock to continue to berm the toe of the lock and load wall in the
footing excavation.
ESNW rep will return to observe earthwork activities when requested by client
4-1-S �_
Andrew Kimn, Senior Technician, 206-430-9183
" Earth Solutions NWLLC
ESNW Rep.
Report No.
AK
15365 NE 90" Street, Suite 100
100
i Redmond, WA 98052
Time On Site
Main (425) 449-4704 1 Fax (425) 449-4711
www esnw.com
11:45 AM
DAILY FIELD REPORT
12/23/19
Travel Time
1.25 Hr. RT
Project Name
Weatherly Inn
Contractor #1
Rino Construction
Contractor #2
Project No.
Page
Report No.
0895.06
2/2
100
Time Off Site
Date
Day of Week
Monday
1:15 PM
12/23/19
Weather
40s°F, Overcast
Job Location
4500 Talbot Rd. S., Renton, WA
Contact
Mike
Contact
Client/Owner
RJ Development, LLC
Field Supervisor Reviewed
LAC
Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No- Permit No
Earth Solutions NWLLC ESNW Rep. Project No. Page Report No,
15365 NE 90'h Street, Suite 100 AK 0895.06 1/2 101
t Redmond, WA 98052 Time On Site Time Off Site Date Day of Week
Main (425) 449-4704 1 Fax (425) 449-4711 Tuesday
www.esnw.com 10:30 AM 1215 PM 12/24/19
DAILY FIELD REPORT rT,avel Time Weather
.25 Hr. RT 40s0F, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 14500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No Permit No
Supplementary Report:
At the client's request, ESNW rep was onsite to observe or test water line backfill, test pH of stormwater, sewer
discharge and earthwork activities.
Water Line Backfill
Rep observed contractor use a medium sized excavator to excavate and install the water line south of the
stormwater vault.
Rep observed contractor install a 10" ductile iron pipe at the toe of the excavation (W4'xD4') embedded in a 12"
lift pea gravel Rep observed contractor place brown silty sand with gravel material in loose 12"-18" lifts and
compacting with a hoe pack. Rep took compaction tests on backfill and observed material to be adequate of at
least 95% of its maximum dry density (130.7 lbs./cu. ft.).
Test pH of Stormwater
Rep took pH tests to determine the acidity of stormwater. Rep took pH tests at the east end of the quarry spall
entrance and observed a pH level of 6.5/7 pH. At the west of the quarry spall entrance stormwater (temporary)
collection pit and observed a pH level of 9 pH. On the street, north and south of the west entrance, rep took a pH
tests and observed stormwater to be a 6.5/7 pH. Rep tested banker tanks with stormwater and observed that
contractor had added dry ice as recommended by ESNW. Rep tested a 6.5/7 pH in both baker tanks which is
compliant with required pH levels for sewer discharge. Rep observed that pH level was contained onsite and that
stormwater pH level in street was in compliance of required pH level at 6.5/7 pH
Sewer Discharge
Rep used IMHOFF cone to test baker tank sewer water discharge. Rep used IMHOFF cone and found sediment
(<3 ml) after testing water for one hour. Rep took PH test and found water suitable for discharge at a PH level of
6.5.
ESNW rep will return to observe earthwork activities when requested by client.
.1 . , J
;nior Technician, 206-430-9183
Earth Solutions NWLLc
` t 15365 NE 90"' Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 1 Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Project Name
Weatherly Inn
Contractor #1
Rino Construction
Contractor #2
ESNW Rep.
Project No
AK
0895.06
Time On Site
Time Off Site
10:30 AM
1215 PM
Travel Time
1.25 Hr. RT
Job Location
4500 Talbot Rd. S., Renton, WA
Contact
Mike
Contact
Page 2/2 Report No.
101
Date Day of Week
12/24/19 Tuesday
Weather
40s°F, Overcast
Client/Owner
RJ Development, LLC
Field Supervisor Reviewed
LAC
Project Manager Reviewed
Ray
Are approved plans/permits on site?
Project No
Permit No.
Test Test Location
Reference Maximum
Fill
Test % of
Number (See
Elevation
Compaction Dry Density
Moisture
Dry Density Maximum
Curve (pcf)
(%)
(pcf) Dry Density
105 See map for approximate loca ion SG
1 130.7
12,1
124.8 96
Supplementary Report:
jo
105..
. z�
y