N I la, Order No.5
Contract Title: SW Grady Way Overlay Project
Contractor: Lakeside Industries
Contract No.: CAG-14-151
Federal Aid No.: STPUL-1288(005)
® Ordered by Engineer
❑ Proposed by the Contractor(VECP)
❑ Unilateral
Amount Working Days
Original Contract: $847,338.5 30
Current Contract: $942,807.59 67
Estimated Net Change This Order: 0 0
New Contract: $942,807.59 67
Prepared By: Issue'. ;
t �L — 10/4 I //' �2//./
Res(derit n sneer ate E gineer(City of Renton Transportation ate
Design Manager)
Reviewed By: Consent By:
t'/l'Y
Engineer of Record Date Surety(Greater than 25%cost and/or 20% Date
time increase)
Reviewed By: Endorsed—� By:
( ,/, ((i i i (a) G �/i2 /6/20
City of Renton Pr ject Manager Date Contractor Date
Reviewed By: Executed By:
Pir /i'if/ ti 1/6/17
City Attorney(Compiles th 25ao2, Date City o Re jitd i blic Works at
Section 7.a) Administrator/Mayor
Change Order No. 5
Contract Title: SW Grady Way
Overlay
Contract No. CAG-14-151
Page 1 of 4
THE CONTRACT IS MODIFIED AS FOLLOWS:
Description of Change:
The following sections from the original contract do not apply to work performed under Change
Order No.3(CO3)and Change Order No.4(C04)as work to be completed under this change
orders is funded solely by the City of Renton with no federal funding,and DBE Utilization is not
required.
(a) Section 1-02.6 and 1-02.9,the requirement for the submittal of Disadvantaged Business
Enterprise(DBE)Utilization Certification.
(b) Section 1-04.4(2)A General. Requirement to provide for substitution for deleted or
reduced DBE Condition of Award Work,Apprentice Utilization and Training.
(c) 1-08.1 Subcontracting.Requirement to certify to the actual amounts paid to
Disadvantage,Minority,Woman or Small Business Enterprises firms that were used.
(d) 1-02.6 Preparation of Proposal.The fourth paragraph as revised in the special provisions
does not apply
(e) 1-02.13.h Irregular Proposals. Requirement to submit Disadvantage Business Enterprise
Certification.
(f) April 1,2013 WSDOT GSP—Disadvantage Business Enterprise Condition of Award
Participation
(g) Disadvantage Business Enterprise Condition of Award Participation
(h) Disadvantage Business Enterprise Utilization Certification FORM#272-056 EF
(i) Disadvantage Business Enterprise Written Confirmation Documents Form#422-031 EF
Section 1-06,Buy America,from the original contract special provisions do not apply to the
work performed under CO3 and C04.
All work performed under CO3 and C04 shall comply with current Washington State Prevailing
Wages in effect as of Oct 1,2019—attached.The following sections referring to the use of
Federal Wage rates do not apply.
(a) 1-07.9 Wages,supplement section referring to incorporation of federal wages rates
does not apply.
(b) April 2,2007 WSDOT GSP,application of Wage Rates for the Occupation of Landscape
Construction
(c) January 3,2014 WSDOT GSP
(d) 1-07.12 Federal Agency Inspection
(e) 1-08.0(1)Preconstruction Conference
Change Order No. 5
Contract Title: SW Grady Way
Overlay
Contract No. CAG-14-151
Page 2 of 4
Appendix B:Prevailing'Hourly Minimum Wage Rates is added to the contract.
Section 1-04.4. B.,Changes,from the Original Contract,does not apply to work performed
under CO3 and C04.There will be no adjustment to work In excess of 125 percent or below 75
percent from the quantity shown on Bid Schedule B.Final payment will be the acceptable units
of work completed multiplied by the unit price.
Section 1-09.9 of the Original Contract is supplemented to Include:
1. 5%retainage of each progress payment earned by Contractor or Subcontractor will be
withheld until Project Completion
If there is a conflict between these supplemental special provisions and the Contract
Documents,the provisions of these supplemental special provisions shall govern.
These changes shall apply to CO3,C04 and all remaining Work under the Contract unless
specifically reversed by future change order(s).
Reason for Change:
This change orders Is funded solely by the City of Renton with no federal funding.
Materials:
None
Adjustment:
None
Extension of Time:
None
Equitable Adjustment:
None
Change Order No. 5
Contract Title: SW Grady Way
Overlay
Contract No. CAG-14-151
Page 3 of 4
Sections 1-04.4 and 1-04.5 of the 2014 WSDOT/APWA Standard Specifications shall govern
this Change Order.The Work of the referenced Contract is modified to Include the changes
detailed herein.The payment provided for herein shall constitute the complete and final
settlement for all costs of labor,equipment,materials,overhead,profit,permit fees,and all
other claims that may be made by the Contractor as a result of this change.
Attachments:
Forms to he attached to Change Order
❑ Plans
▪ Field Directive
CI Change Order Quotation
O Estimated Change Order Cost
• Project Labor List
• Force Account Equipment Rate Request(DOT Form 422-010 EF)
▪ Equitable Adjustment Determination
Change Order No. 5
Contract Title: SW Grady Way
Overlay
Contract No. CAG-14-151