HomeMy WebLinkAboutCO 6 CAG-14-151 , .CO #6- 20 \1 Y 04, 4)F � "T° Change Order No.6 Contract Title: SW Grady Way Overlay Project Contractor: Lakeside Industries Contract No. : CAG-14-151 Federal Aid No. : STPUL-1288(004) ® Ordered by Engineer ❑ Proposed by the Contractor(VECP) ❑ Unilateral Amount Working Days Original Contract: $847,338.5 30 Current Contract: $942,807.59 67 Estimated Net Change This Order: $2,206.33 0 _ New Contract: $945,013.92 67 Pre fredi B Issued /07 Resid t ngineer Date -Engineer(City of Renton Transportation Date Design Manager) Reviewed By: Consent By: / ,Z./9./�j Engineer of Record Date Surety(Greater than 25%cost and/or 20% Date time Increase) Revie ed Endorsed By: ity of Renton Project na er Date Contractor Date Reviewed By: Executed By: zo City Attorney(Comer with 2so-o2, Date City of Re tt ublic ors Dl Section 7.4) Administra or/Mayor Change Order No. 6 Contract Title: SW Grady Way Overlay Contract No. CAG-14-151 Page 1 of 5 • THE CONTRACT IS MODIFIED AS FOLLOWS: Description of Change: Force account work to cover the following items: Added thickness of concrete sidewalk which was 12-inches in the field, instead of 4-inches shown in plans and details.This covers both the added labor to remove the 12-inch-thick panel and the additional concrete to replace the concrete back at 12-inches due to truck traffic at SE Lind. Installation of cold patch asphalt ramps at the NW corner of Oaksdale to allow temporary pedestrian access during construction and overnight. Work to be completed under this change order shall be subject to current state prevailing wage rates.The Contractor and any new or returning subcontractors shall submit new Intent to Pay Prevailing Wage forms to Labor and Industries for this current work. Reason for Change: Match as-built conditions at SE Lind. Provide temporary pedestrian access due November elections. Materials: None Plans: None Change Order No. 6 Contract Title: SW Grady Way Overlay Contract No. CAG-14-151 Page 2of5 Adjustment: Bid item B-20 "Minor Work Items" is added to cover additional force account work items in the lump sum amount of$2,206.33. Bid Item I No. Description Unit Quantity Unit Price Total Amount B-20 Minor Work items LS 1 $ 2,206.33 $ 2,206.33 TOTAL THIS CHANGE ORDER = $ 2,206.33 With this Change Order, Bid Schedule B is revised to read as shown on the following page. Extension of Time: None Equitable Adjustment: This Change Order includes an equitable adjustment per Section 1-09.4 of the 2014 WSDOT/APWA Standard Specifications and included in the unit process in this change order. The Equitable Adjustment lump sum amount was determined using the force account method as shown in the attached force account tracking sheets. See attached force account sheets. Change Order No. 6 Contract Title: SW Grady Way Overlay Contract No. CAG-14-151 Page 3 of 5 BID SCHEDULE B—SW Grady Way Curb Ramp Replacements Bid Item No. Description Unit Quantity Unit Price Total Amount B-1 SPCC Plan LS 1 $ 150.00 $ 150.00 B-2 Mobilization LS 1 $ 5,000.00 $ 5,000.00 Project Temporary Traffic B-3 Control LS 1 $ 49,000.00 $ 49,000.00 B-4 Roadside Cleanup EST 1 $ 2,500.00 $ 2,500.00 Remove Cement B-5 Concrete Sidewalk SY 270 $ 77.00 $ 20,790.00 Cement Conc.Sawcutting B-6 and Grinding EST 1 $ 5,000.00 $ 5,000.00 B-7 Remove Curb and Gutter LF 280 $ 45.00 $ 12,600.00 Crushed Surfacing Top B-8 Course TON 30 $ 30.00 $ 900.00 B-9 Inlet Protection EA 23 $ 65.00 $ 1,495.00 Erosion/Water Pollution B-10 Control EST 1 $ 1,000.00 $ 1,000.00 Cement Conc.Traffic B-11 Curb and Gutter LF 180 $ 50.00 $ 9,000.00 Cement Conc.Traffic B-12 Curb LF 60 $ 45.00 $ 2,700.00 Cement Conc. Pedestrian B-13 Curb LF 100 $ 45.00 $ 4,500.00 B-14 Cement Conc.Sidewalk SY 270 $ 100.00 $ 27,000.00 Detectable Warning B-15 Surface SF 210 $ 22.00 $ 4,620.00 Apply Non-Skid to Utility B-16 Cover EA 2 $ 850.00 $ 1,700.00 Remove Asphalt Concrete B-17 Pavement SY 60 $ 40.00 $ 2,400.00 B-18 HMA CI 1/2" PG 52H TON 25 $ 85.00 $ 2,125.00 Traffic Signal System B-19 Modifications, Complete LS 1 $ 20,000.00 $ 20,000.00 8-20 Minor Work Items LS 1 $ 2,206.33 $ 2,206.33 TOTAL BID SCHEDULE B= $ 174,686.33 Change Order No. 6 Contract Title: SW Grady Way Overlay Contract No. CAG-14-151 Page 4 of 5 Sections 1-04.4 and 1-04.5 of the 2014 WSDOT/APWA Standard Specifications shall govern this Change Order.The Work of the referenced Contract is modified to include the changes detailed herein.The payment provided for herein shall constitute the complete and final settlement for all costs of labor, equipment, materials, overhead, profit, permit fees, and all other claims that may be made by the Contractor as a result of this change. Attachments: Forms to be attached to Change Order ❑ Plans ❑ Field Directive ® Change Order Quotation ❑ Estimated Change Order Cost ❑ Project Labor List ❑ Force Account Equipment Rate Request (DOT Form 422-010 EF) • Equitable Adjustment Determination Change Order No. 6 Contract Title: SW Grady Way Overlay Contract No. CAG-14-151 Page 5 of 5