HomeMy WebLinkAboutCO 3 CAG-18-240, CO#3-20 afie _ Community Services Facilities Division CONTRACT NO: CAG-B18002996 CO NO. 3 CONTRACT CHANGE ORDER(CO) PROJECT TITLE: CITY OF RENTON PW-SIGN SHOP EXPANSION TO:OPTIMUS CONSTRUCTION (CONTRACTOR) The following mutually agreed to and Owner approved Change Order Proposals)are hereby incorporated by reference into the contract. Description Amount COP: GENERAL CONDITIONS-TIME CHANGE $ - $ CONTRACT SUM: ❑ NO CHANGE 0 INCREASE OF: $ _ ❑ DECREASE (WASHINGTON STATE SALES TAX INCLUDED) CONTRACT TIME: ❑ NO CHANGE O INCREASE OF: 301 ❑ DECREASE CALENDAR DAYS The foregoing amount covers everything required in connection with the change.All other provisions of the contract remain in full force and effect. CONTRACT SUMMARY(Internal Use Only) ORIGINAL CONTRACT SUM $ 627,386.03 PREVIOUS ADDITIONS/DELETIONS $ 11,465.30 PREVIOUS TOTAL $ 638,851.33 CHANGE AMOUNT THIS CHANGE ORDER $ REVISED CONTRACT TOTAL $ 638,851.33 PERCENT TOTAL CHANGE FROM ORIGINAL 1.83% NOTICE TO PROCEED DATE March 12,2019 PREVIOUS CONTRACT CALENDAR DAYS 120 PREVIOUS SUBSTANTIAL COMPLETION DATE July 10,2019 REVISED CONTRACT CALENDAR DAYS THIS CHANGE ORDER 150 fet; CURRENT SUBSTANTIA OMPLETIO Au st 9,2019 f- 70 p-so-,, Architect Acknowledgement Date' Contractor Acknowledgemen Date The City of Renton hereby accepts the foregoing Change Order Proposal(s).This formal acceptance constitutes a Change to the contract only when authorizing signature is affixed.Invoices incorporating this Change Order constitute acceptance by the Contractor as total reimbursement due in connection with this Change rder 7At) AUTHORIZING GNATU DATE vi PTIMUS C71^4'-">TRUCTION RNO DEVELOPMENT INC City of Renton -SIGN SHOP EXPANSION General Contractor Change Order Rquest Date 7.16.19 Project Name: City of Renton-Sign Shop Expansion COP# 3 PR# Project# 2019-01 RFI# Time Extention: This has been determined to create a total of 30 days in extention. Dates are from 7-8-19 to 8-7-19. LABOR COST (GC Work Force Only) Employee Name Hr Rate Hour Extension Description Journeyman Petr Chebotarev $81.93 $ $ - Journeyman Mikhail Balika $81.93 $ $ - Journeyman Scott Dietrich $81.93 $ $ - Supervisor Dick McCullough $84.38 $ $ - GC Labor Cost $ - P&022% $ - GC Labor Total Cost $ - MATERIAL COST Material Cost Suppliers Material Cost $ - EQUIPTMENT COST Rental Equipment Owned Equipment $0.00 Equipment Cost $ - Material&Equipment Const $ - OH&P@22% $ - Material&Equipment Total Cost $ - Backup documentation is Attached. Subcontractors Cost Name Item Sub-Profit Subs Cost Less Profit $0.00 $0.00 Subcontractor Cost(less profit) 0.00 Subcontractor Profit 0.00 Subcontract Cost Total 0.00 GC Labor, Material&Equipment Total Cost $ - GCOH& P@22% $ - Subcontractors Total Cost $ - GCOH &Pon Sub @7% $ - GC&Sub's Total Cost $ - Insurance @ 1% $ - Bond @ 2% $ - Total Cost $ -