HomeMy WebLinkAboutMFP20000288.pdfDEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Minor Franchise Permit: MFP20000288
IVR Number: 20000288
Permit Informaon
Permit Name:Puget Sound Energy - Electric
Address/Locaon :01/15/2020Application Date:3342103466Parcel Number:1610 NE 30TH ST
Permit Type:01/29/2020Issue Date:Franchise
Permit Work Class:01/28/2021Expiration Date:Minor Utility
Job Number:101124170Franchise Type:Electric
Description:At V01 dig work pit and trench 18' at V01. Replace existing 25KVA transformer at V01 and install (1) 35' long sch80
PVC conduit in trench. Install (1) run of 350 UG TPX at V01. Restoration per City of Renton standards.
APPROVED WITH COMMENTS OR REDLINES
Contacts
Name Address PhoneTypeBilling
Corrie Rydberg
Puget Sound Energy
6905 S 228TH St
KENT, WA 98032
C: (425) 892-0416Applicant
Marita Bond
Puget Sound Energy Billing
6905 S 228 St
Kent, WA 98032
B: (253) 395-6346Contact
Vicki Henson
Potelco Inc
8001 212th St S
Kent, WA 98032
B: (253) 863-0484Contractor
Business License Number: 5109Electrical Contractor: POTELI*344O4
Construction Contractor: POTELI*227PL
SCHLOREDT GREEN JENNIFER 17825 3RD AVE NE
SHORELINE , WA 98155
Owner
Marita Bond
Puget Sound Energy Billing
6905 S 228 St
Kent, WA 98032
B: (253) 395-6346Specialized
Billing
X
General Condions & Signature
Permission is hereby given for the work described on this permit according to the conditions hereon and according to the
approved plans and specifications pertaining thereto, subject to compliance with the Ordinance of the City of Renton.
This permit and plans must be posted at the job site at all times.
I hereby certify that no work is to be done except as described above and in approved plans, and that work is to conform to
Renton Trench Restoration and Street Overlay Requirements.
Call 425.430.7203 or go to: https://permitting.rentonwa.gov one working day in advance to schedule an inspections and for ANY
work in the Right of Way.
Call 8 1 1 to locate underground utilities at least two full business days prior to any excavation.
In accordance with RCW 19.122.033(4) the permit holder is required to contact (Williams Northwest Pipeline at 425.868.1010)
(Olympic Pipeline at 206.510.0575) (Puget Sound Energy at 425.375.3397) to request a consultation with the transmission
pipeline company prior to performing any construction or excavation activities. This requirement to consult with the
transmission pipeline company is in addition to the requirement to Call before You Dig as required in RCW 19.122.
(Date)(Signature)
Page 1 of 1THIS PERMIT AND PLANS MUST BE POSTED AT THE JOB SITE AT ALL TIMES
DEPARTMENT OF COMMUNITY
AND ECONOMIC DEVELOPMENT
Page 1 of 1 | Published: 1/2/2019
Planning Division | 1055 South Grady Way, 6th Floor | Renton, WA 98057 | 425-430-7200
Email: franchisepermits@rentonwa.gov Website: rentonwa.gov
FRANCHISE PERMIT APPLICATION
Published: 1/2/2019
TO THE APPLICANT: Submit an electronic copy of the plans with the Franchise Permit Application and the Site
Specific Traffic Control Application to franchisepermits@rentonwa.gov. Permit cost is $630.00. Inspection fee
for trenching more than 60 lineal feet or installation of 6 or more poles will be billed at $60.00 per hour.
Franchise Agency:
Franchise Job Number: Phone:
Contact Name: Email:
Job Site Address: Project Name:
Description of Work:
Please check all that apply:
տ New Construction տ Repair/Relocate տ Underground տ Overhead տ Sidewalk տ Street
տ Open Trench տ Bore # of feet:
Contractor Name: Phone:
State Contractors License #: City of Renton Business License #:
“I certify that I am the owner or applicant’s authorized agent and do hereby agree to abide to the terms and conditions set forth
under this permit and shall comply with the City of Renton’s Trench Restoration and Street Overlay Requirements. ”
Signature Date
INSPECTIONS SHALL BE REQUESTED 24 HOURS PRIOR TO COMMENCEMENT OF ALL WORK BY CALLING THE
INSPECTION LINE AT 425-430-7203 OR BY GOING TO MYBUILDINGPERMIT.COM
Jobs are required to be called in for job start, re-inspection and project final. Re-inspection fees are billed at
$125/hour. All Pre-Construction meetings shall be scheduled at a maximum of 14 days prior to the job start date.
Plan Review/Development Engineering Date Approved as submitted
Pre-Construction Meeting required
Site Construction Inspector Date Approved with comments or redlines
Camera inspection of utilities required
Development Engineering Manager Date
PUGET SOUND ENERGY - ELECTRIC
101124170
CORRIE RYDBERG
425-892-0416
CORRIE.RYDBERG@PSE.COM
1610 NE 30TH ST
AT V01(319235-166345) CUSTOMER TO DIG 4X4 WORK PIT AND TRENCH 18' AT V01 (319235-166345)
POTELCO CREW TO REPLACE EXISTING 25KVA TRANSFORMER AT V01(319235-166345) AND INSTALL (1) 35' LONG SCH80 PVC CONDUIT
IN CUSTOMER PROVIDED TRENCH. INSTALL (1) RUN OF 350 UG TPX AT V01(319235-166345). PLEASE SEE ATTACHED
✔✔✔
✔18'X2'X3.5'
POTELCO, INC. 425-892-0416
POTELI#227PL BL005109
Corrie Rydberg Digitally signed by Corrie Rydberg Date: 2020.01.15 12:56:59 -08'00'01/05/2020
MFP20000288
Scott Warlick
Holly Powers 1/29/2020
1/29/2020
DEPARTMENT OF PUBLIC WORKS
Note: The Applicant is responsible for compliance with all codes and regulations, whether or not described in this document.
Page 1 of 2 | Published: 1ϭ/Ϯϱ/2019
Transportation Division | 1055 South Grady Way, 5th Floor | Renton, WA 98057 | 425-430-7380
Website: rentonwa.gov
TRAFFIC CONTROL PLAN (TCP) APPLICATION
Published: 1ϭ/Ϯϱ/2019
TRAFFIC CONTROL PLAN (TCP) MUST BE SUBMITTED TO PUBLIC WORKS TRANSPORTATION DIVISION
FOR REVIEW/APPROVAL NO LATER THAN FIVE (5) WORKING DAYS BEFORE THE DATE OF WORK.
The City of Renton requires any contractor, firm, corporation, or other public/private agency to prepare a TCP and
obtain City of Renton's approval of that plan when construction, repair, or maintenance work is to be conducted
within the city's right-of-way.
TO THE APPLICANT: Submit the TCP application form and required submittal documents to
TCP@rentonwa.gov with the subject line “TCP Application – [Project Name]” or the above address.
The following items, electronic copies preferred, are all required for submittal of the TCP Application:
1.܆ A copy of the Traffic Control Plan (TCP) Application form.
2.܆ A copy of the required TCP layout, preferred 11” X 17” paper size format, which shall:
܆ Include map(s) showing the location of the project and work area.
܆ Be legible lettering and clear, contrasting, symbols of viewing or printing.
܆ Must indicate street names, and north arrow and scale.
܆ All signs and detour routes shall conform to the MUTCD, WSDOT TCPs, and the Washington State
Traffic Control Flagger Certification handbook, by the Evergreen Safety Council.
܆ Types of plans required:
܆ Work hour plan – show all mobility impacts during construction hours.
܆ Non-work plan - show all mobility impacts after work hours when limited or no work is
happening in the right-of-way (ROW), if applicable.
܆ Changing construction phases – show construction sequence and each construction phase
change even if the traffic control is not modified, if applicable.
܆ Pedestrian access/detour plan, if applicable.
Project Name: ______________________________________________ Permit #: _____________________
Project Address: ____________________________________________________________________________
Work Date: From _____________ To _____________ Work Time: Start ______________ End ______________
Description of Work, Work Schedule, Equipment Used: _____________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
Construction Company: ________________________________________ Phone/Cell: (_____) _____-________
Applicant Name: _________________________________ Email: ______________________________________
Business Address: _________________________________ City/State: __________________ Zip: __________
Approved By: _______________________________________________ Date: ________________________
Transportation Operations Engineering
✔
✔
✔
✔
1610 NE 30TH ST
TBD TBD TBD TBD
AT V01(319235-166345) CUSTOMER TO DIG 4X4 WORK PIT AND TRENCH
18' AT V01 (319235-166345) POTELCO CREW TO REPLACE EXISTING 25KVA TRANSFORMER AT V01(319235-166345) AND INSTALL (1) 35' LONG
SCH80 PVC CONDUIT IN CUSTOMER PROVIDED TRENCH. INSTALL (1) RUN OF 350 UG TPX AT V01(319235-166345). PLEASE SEE ATTACHED
POTELCO, INC. 425 892 0416
KHADER GOUESSE KHADER.GOUESSE@PSE.COM
6905 S 228TH ST KENT, WA 98032
01/05/2020
MFP20000288
Monday - Friday 9:00am - 2:30pm
Scott Warlick C.E.D 1/28/2020
Note: The Applicant is responsible for compliance with all codes and regulations, whether or not described in this document.
Page 2 of 2 | Published: 1ϭ/Ϯϱ/2019
APPLICANT AGREES TO ALL THE FOLLOWING:
x TCP must be approved prior to commencing the work, and all permit conditions shall be met.
x Existing pedestrian access shall be maintained. The work on pedestrian facilities shall be limited to one corner
at a time, with the least possible inconvenience or delay to pedestrians.
x Signage shall be used to warn motorcyclists/bicyclists of the potential hazards on any uneven surfaced or
slippery road conditions during work and non-work hours.
x The start of Work Time begins when any street or travel lane is fully/partially closed or impacts the follow of
traffic. This includes set up within the traveled way or immediately adjacent to the roadway.
x Emergency services (253-852-2121) shall be notified twenty-four (24) hours before any street or lane closures.
x Contractor or entity must call Renton School District (425-204-4455) or any public/private agency, including
public transit, to be affected by a temporary lane or road closure.
x TCP for all street and/or lane closures shall be implemented and performed in compliance with the Manual on
Uniform Traffic Control Devices (MUTCD) and/or State of Washington Department of Transportation (WSDOT)
and all traffic regulations of the City of Renton and Revised Code of Washington (RCW).
x Any lane or street closures not in conformance with the approved traffic control plan and/or without
notification of emergency services may result in receiving a citation for violation of RCW 47.36.200 Signs or
Flaggers at thoroughfare work sites and RCW 9A.36.050 Reckless Endangerment, and other applicable State
and City codes.
x Indemnify and hold harmless the City of Renton from any and all claims, actions, and judgments, including all
costs of defense and attorney’s fees incurred in defending against same, arising from and related to
implementation of the approved traffic control plans including claims arising from towing of private vehicles
and the acts of the Applicant’s agents and employees.
x The City of Renton shall be entitled, in its reasonable discretion, to settle claims prior to suit or judgment, and
in such event shall indemnify and hold harmless the City for any such claims paid, including the City’s
reasonable attorney’s fees and litigation costs incurred resulting from such claim.
x In the event any claim or suit is brought against the City within the scope of this Agreement, Applicant will pay
for legal counsel chosen by the City to defend against same.
x Flagger and sign placement are subject to revision by the City Inspector on site, if needed to address traffic or
pedestrian safety or travel.
x Total road closure lasting more than twenty-four (24) hours is subject to the approval by the City Council.
x Approved Temporary TCP must be at the work site during work hours.
x Complete assistance and accommodation shall be provided to all kinds of pedestrian traffic when sidewalk or
walkway is impeded to safely redirect pedestrians around a work zone.
x Any vehicle, equipment, barricade, or portable tow-away sign used within the work area must display a
company logo or any legally acceptable sign showing the company name, address, and telephone number at a
conspicuous place on the vehicle or equipment.
In the case of Temporary No Parking Zones, all the following apply in addition to previous:
x Contractor must complete form to show limits of Temporary No Parking Zone identifying barricade locations
for vacate parking or curb lane usage.
x Contractor must post notice of dates and time of Temporary No Parking Zone with at least two signs per block
seventy-two (72) hours in advance of effective date and time.
x The cover sheet of this TCP form must be attached to each Temporary No Parking Sign on the project site.
x Temporary traffic control devices must be removed immediately when work is done or no construction
activities are going on. If deemed abandoned, City crews will remove and store them at the City’s maintenance
shop (3555 NE 2nd Street; 425-430-7423).
_______________________________ _______________________________ _______________________
Applicant’s Signature Print Name Date
Corrie Rydberg Digitally signed by Corrie Rydberg Date: 2020.01.15 12:57:11 -08'00'CORRIE RYDBERG 01/15/2020
11 11 11
1616 NE 30th St Renton WA 98056 USAKennydale Elementary School1700 NE 28th StRenton, WA 98056HH2V01HH1INTERSTATE405INTERSTATE405KENNEWICK PL NENE 29TH
STI-405 ON RAMPI-405 OFF RAMPONE WAY ONE WAY ONLYBUSBUSSTOP12
ONLY
M6-2
RIGHT
KEEP
R4-7BRIGHTKEEPR4-7BONLYR3-5RROADWORKAHEADW20-1100'100'100'RIGH
T
L
ANECLOS
EDAHEAD
W20-5R
W4-2L CENTER LANECLOSEDAHEADW9-3ROADWORKAHEADW20-1W4-2RX'X'X'111111ROADWORKAHEADW20-1 X'X'X'PLACE W20-1 SIGNS ON ALLADJACENT STREETS WITHIN FEET OF WORK AREAROADWORKAHEADW20-1 ROADWORKAHEADW20-1300USE MAXIMUM AVAILABLESPACE FOR SIGNSAHEADUSE OTHER SIDESIDEWALK CLOSEDS/WCLOSEDR9-9S/WC
L
O
S
E
D
R9-9THE CREW SHALL CEASEWORK FOR A FLAGGER/SPOTTERTO ESCORT PEDESTRIANSAROUND THE WORK AREANPSEPUGETSOUNDENERGYJOB1011241701610 NE 30th St, Renton, WA1/3/2020Yuriy.Bashtovoy@pse.com(425)424-6603SHEET 1 of 2TEMPORARY TRAFFIC CONTROL PLANPuget Sound EnergyTraffic Control Supervisor:Yuriy S. BashtovoyCard No. 011687Card Exp. 06/30/2022Yuriy.Bashtovoy@pse.com(425)424-6603PRINT ON 11 X 17SHEETS ONLYNotes:1. All signs and spacing to conform to theMUTCD and City of Renton standards.2. All sidewalks, driveways, exits and egressesshall be completely clear unless otherwise indicated.3. Channelizing devices are 28" traffic cones.Use traffic drums (barrels) with steady burningType C lights on all State State Routes and Hwys.4. Sign size can be a minimum of 36" x 36" andshall not obstruct pedestrian access.5. Crew is required to leave a minimum of 11' fortraveling lane width.6. Alert affected residents and businesses.7. Work to take place between 9 a.m. and 4 p.munless otherwise specified. All work for arterialsand major roadways will be from 9 a.m. to 3 p.m.8. See sheet 2 for WSDOT Notes and Tables.0'80'40'CHANNELIZATIONDEVICE SPACINGMPH55/7035/4525/30TAPER403020TANGENT80604055 +60/6545/5535/403025SIGN SPACING"X"800500'350'200'100'MINIMUM TAPER LENGTH=L (FT.)LANEWIDTH101112207075802510511512530150165180352052252454027029532045475495540POSTED SPEED (MPH)505005506005555060566060-66072065--78070--84028" TRAFFIC CONETRAFFIC FLOWSIGN LOCATIONLEGENDVAULTVaultCHEVRONARROW BOARDWORK VEHICLE/FLASHING LIGHTSRIGHT OF WAYMFP20000288Sidewalk closed sign
PSEPUGETSOUNDENERGYJOB1011241701610 NE 30th St, Renton, WA1/3/2020Yuriy.Bashtovoy@pse.com(425)424-6603SHEET 2 of 2WSDOT NOTES & TABLESPuget Sound EnergyTraffic Control Supervisor:Yuriy S. BashtovoyCard No. 011687Card Exp. 06/30/2022Yuriy.Bashtovoy@pse.com(425)424-6603PRINT ON 11 X 17SHEETS ONLY””–MFP20000288
1616
ROW60'NE 30TH ST
1610
319236-166340
112.5 kVA 120/208V (ABC)
319235-166345
25 kVA 120/240V (A)
25 kVA 120/240V (A)
319235-166342
319233-166341
319229-166341
PARCEL#
3342103466 CUSTOMER OWNED, INSTALLED &
MAINTAINED 1-RUN 3/0 SVC
BRUSH CLEARING
REQUIRED
J
HIG
15
319235-166345
25 kVA 120/240V (A)
25 kVA 120/240V (A)
4' X 4' WORK PIT
CUSTOMER SUPPLIED
CUSTOMER SUPPLIED
5'6" X 4'5" WORK PIT
PSE INST. 1-RUN 350 UG TPX ± 50'
PSE SUPPLIED & INSTALLED1-3" SCH'L 80 CONTINUOUS PVC CONDUIT ± 35'
W/ 2.37 CUBIC YARD OF SOIL DISPLACEMENT
4.67 CUBIC YARD OF SOIL DISPLACEMENT
IN CUSTOMER PROVIDED TRENCH
P P P P P P P
P
P
P
P
P
P
P
P
P
P
P
P P P P P P
P
P
P
P
P
P
P
P
P
P
P
NE 30TH ST
ROW80'8'8'40'E
O
P
SI
D
E
W
A
L
K
319235-166345
25 kVA 120/240V (A)
25 kVA 120/240V (A)
319233-166341
E
O
P
SI
D
E
W
A
L
K
J EXISTING
FIRE HYDRANT
9'1'2'7.04 CUBIC YARD OF SOIL DISPLACEMENT TOTAL
7.04 CUBIC YARD OF SOIL DISPLACEMENT TOTAL
00 1"2"
00 50'100'
SITE PLAN
SCALE: 1" = 50'
JOB SITE
CUSTOMER DEVELOPMENT NOTES:
A PRE CONSTRUCTION MEETING IS REQUIRED WITH YOUR PROJECT MANAGER PRIOR TO STARTING ANY SITE
WORK.
CUSTOMER IS RESPONSIBLE FOR ALL TRENCHING, SELECT BACKFILL, COMPACTION & RESTORATION PER PUGET
SOUND ENERGY STANDARDS & LOCAL MUNICIPALITY.
**DEVELOPER NEEDS TO FOLLOW ALL TRENCH DETAILS ON SELECT BACKFILL**
CUSTOMER IS RESPONSIBLE FOR THE FOLLOWING:
CROSSING/BORING.
-BORING FOR CROSSINGS IS ONLY ALLOWED PER LOCAL MUNICIPALITY PERMIT REQUIREMENTS.
-CROSSINGS IN RIGHT OF WAY MUST BE SCHEDULED WITH PROJECT MANAGER PRIOR TO
CONSTRUCTION.
-PROJECT MANAGER OR DESIGNATED REPRESENTATIVE MUST BE ON SITE DURING CONSTRUCTION
WORK IN RIGHT OF WAY.
-EXCAVATION CONTRACTOR MUST BE LICENSED AND BONDED TO PERFORM WORK IN RIGHT OF WAY.
VAULTS & WORK PITS.
-REQUIRED TO PROVIDE 4' X 4' WORK PIT AT V01
-REQUIRED TO PROVIDE 5'6" X 4'5" WORK PIT AT HH2
TRENCHING.
-REQUIRED TO TRENCH FROM V01 TO HH2
JOB SITE READINESS.
-JOB SITE NEEDS TO BE 100% READY FOR INSPECTION 5 BUSINESS DAYS PRIOR TO
CONSTRUCTION DATE.
-ALL WORK IN RIGHT OF WAY MUST BE COORDINATED WITH PROJECT MANAGER AND LOCAL
MUNICIPALITY.
-ALL TRENCH, AND LOCAL ELECTRICAL MUNICIPALITIES AKA "L&I, CITY", INSPECTIONS MUST BE
COMPLETED 5 BUSINESS DAYS PRIOR TO SCHEDULED CONSTRUCTION DATE.
-REQUIRED TO OPERATE AND PROVIDE EQUIPMENT TO PUMP OUT WATER FOR WORK PITS, VAULTS &
TRENCH AT ALL TIMES.
-REQUIRED TO HAVE EXCAVATION EQUIPMENT AND BE ON SITE THE DAY OF CONSTRUCTION TO COMPLETE
BACKFILLING.
- IF A SECOND INSPECTION IS REQUIRED, ADDITIONAL FEE'S WILL BE APPLIED.
-PLEASE REVIEW THE CITY OR KING COUNTY TRENCHING REQUIREMENTS UNDER THE PERMIT.
-IF A PRE-CON IS REQUIRED BY THE CITY, COUNTY OR W.S. DOT A PSE PROJECT MANAGER WILL SET-UP AND
SCHEDULE A MEETING WITH THE MUNICIPALITY BEFORE ANY EXCAVATION OR INSTALLATION BEGINS .
N
Vicinity Map
N/A
ARE TO BE INSTALLED, CROSS SECTION DETAILS OF THE TYPICAL EROSION
STRUCTURES, & SPECIAL REQUIREMENTS FOR WORK IN SENSITIVE AREAS.)
EROSION & SEDIMENT CONTROL REQUIREMENTS
NOTES DETAILING WHERE EROSION OR SEDIMENT CONTROL STRUCTURES
(LOCAL JURISDICTIONS MAY HAVE ADDITIONAL REQUIREMENTS INCLUDING
0150.3200 TECHNIQUES FOR TEMPORARY EROSION & SEDIMENT CONTROL
EROSION & SEDIMENT CONTROL SHALL BE PER PSE STANDARD PRACTICE
& ANY ADDITIONAL LOCAL JURISDICTION REQUIREMENTS.
FOREMAN (CHECK BOX WHEN COMPLETED)
PSE Equipment LOCKED/SECURED & Work Area left in CLEAN/SAFE Condition.
Grid, Cable, and Switch numbers INSTALLED & VERIFIED.
Field Changes RED-LINED on As-built.
Indicate correct FUSE SIZE on As-built & VERIFY proper PHASE.
Foreman's Signature _______________________________________________
Print Name ___________________________________ Date ______________
Material VERIFIED and CHANGES noted on Paperwork.
Total PRIMARY Cable noted on As-built.
Company ID#'s RECORDED in correct location on As-built.
Deviations noted on the As-built and their reason.
I certify that the work performed meets PSE's standards and procedures
and that all quality requirements are met.
JOB SITE
ASPLUNDH CONSTRUCTION CORP. - QA/QC E. HOUSER
PSE
No
No
No
Yes
Yes
Yes
No
YesDeveloper
"Flagging Required"
"Outages Required"
"Locates Required"THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES
CALL 811 TWO BUSINESS DAYS BEFORE YOU DIG
For contacts below dial 1-888-CALL PSE (225-5773)
NEW CABLE & CONDUIT DIAGRAM
NOT TO SCALE
PARTIAL PLAN DETAIL
SCALE: 1" = 20'
NEROW 80'
CL
SW
NOT TO SCALE
CROSS SECTION - NE 30TH ST
LOOKING NORTHWEST
SITE SPECIFIC NOTES
AT V01: 319235-166345
-EXISTING STRUCTURE TO REMAIN
-REMOVE (1) EX. BO 25kVA 120/240v TRF
-INSTALL (1) 25KVA PADMOUNT TRF (MID: 6247000)
-INSTALL (1) 12kV ELBOW KIT PER STD 6041.1000 (ELB10J)
-INSTALL (1) DUST CAP (MID: 7630600)
-INSTALL (1) #6-350 KCMIL SECONDARY CONNECTION BLOCKS (MID: 4842002)
AT HH1:
-EXISTING STRUCTURE TO REMAIN
-REPLACE EXISTING LID WITH (1) 1730 REPLACEMENT COVER (MID: 7654400)
AT HH2:
-INSTALL (1) 17"x30" PE SECONDARY HAND HOLE PER STD 6050.2000 (HH16350)
-INSTALL (3) 6-POS FARGOS BARS
-CONNECT CUSTOMER OWNED, INSTALLED & MAINTAINED 1-RUN 3/0 SVC
AT M01:
-INSTALL 200A METER
___
SPAN SPECIFIC NOTES
V01 TO HH2:
-INSTALL 1-3" CONTINUOUS GREY SCH'L 80 CONDUIT, ± 35' ___' ACTUAL
-INSTALL 1-RUN 350 UG TPX, ± 50’ ___' ACTUAL
___
___
UTILITIES
CONTACT
PHONE#
COUNTY
1/4 SEC
U-MAP NO (POWER)
OP MAP
Emer Sect Gas Wk Ctr POWER WK CTR
PLAT MAP
JOINT FACILITIES ARRANGEMENTS
DRAWN BY
CHECKED BY
APPROVED BY
FOREMAN #1
FOREMAN #2
MAPPING
INCIDENT MAOP
Gas Order Elect Order
SCALE PAGE
ENGR - POWER
ENGR - GAS
FUNCTION
PROJECT MGR
PERMITREAL ESTATE/EASEMENT
2
1
REV#
3
DATE DESCRIPTIONBY
CONTACT PHONE NO DATE
OH CKT MAP CIRCUIT NOUG CKT MAP
K. GOUESSE 253-254-2896 10/29/19
K. GOUESSE 253-254-2896 10/29/19
E. SCHOTT 714-893-2405 10/29/19
REQUIRED RENTON
KENNYDALE ELEMENTARY CELL SITE
SEC L/E
1610 NE 30TH STREET, RENTON, WA 98056
N/A N/A
N/A 101124170
AS NOTED 1 OF 1
KING N/A N/A CSPSKEIN
SW 32-24N-05E N/A N/A
2405E127 2405E136 2405E127 HIG-15
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A N/A N/A
N/A N/A N/A
N/A N/A N/A
E-Mail:
Cell Phone:
Project Manager Contact Information:
Manager:KHADER GOUESSE
253-254-2896
KHADER.GOUESSE@PSE.COM
GAS
PHONE
CABLE TV
PROJECT PHASE
PWR
NOTIF#ORDER#
508417391
507423871
3000382503
104320751
5941311271
584044929
101124171
101124170
Service
Dist UG Maint
Dist UG Operations
Dist Improvement
Superior 101124170SCALE: 6" = 1 MILE
OVERHEAD CIRCUIT MAP 2405E136
Owner / Developer Contact Info
officeATTN:
VERIZON WIRELESS- ZEB BRITTSAN
M/S 3846 PO BOX 2375
SPOKANE, WA 99210
ZEB BRITTSAN 503-791-7600
CIRCUIT FEET ADDED:
SQ. FOOTAGE:
PANEL SIZE:
HEAT TYPE:
EST. DEMAND:
LRC:
% V. DROP:
% FLICKER:
0'
100 SQ FT
200A
ELECTRIC
20kW
65A
2.7%
1.8%
CIRCUIT LOADING TABLE
AS OF
EXIST. PEAK LOAD
EST. NEW LOAD
TOTAL
CIRCUIT:
A PHASE B PHASE C PHASE
HIG-15
05/2019
148.00 124.00 114.00
2.92 0.00 0.00
150.92 124.00 114.00
Removed at site:
Grid Number:
kVA Rating:
Foreman to redline the following information
TRANSFORMER REMOVAL
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
V01
319235-166345
25kVA
Installed at site:
Grid Number:
kVA Rating:
Foreman to redline the following information
TRANSFORMER INSTALLATION
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
Material ID#:
V01
319235-166345
25kVA
6247000
TV & TEL Electric Service Cable in Conduit
3" Schedule 40 Grey PVC
Excavated Dirt Pile
Final Grade
24" Min
24" Min
to
36" Max
Cover
Backfill for Conduit
Free of rocks
larger than 8"
in diameter
Separation
12" Min
in Conduit
Schedule 40 Yellow PVC
Gas Service Line
32" Typical
(Power, Gas,
Phone & Cable)
Separation
12" Min
12" Min
Separation
36" MINIMUM COVER
IN RIGHT OF WAY
JOINT TRENCH DETAIL
Joint Service Line in Conduit (NTS)
To Excavated Dirt Pile
Backfill for In Conduit - The backfill layer shall be soil that is free from construction debris,
glass, sharp rocks, frozen clods, and rocks larger than 8" in diameter.PSE 1730 POLYETHELYNE HANDHOLE PLAN VIEW
2"
APPROX30"
APPROX
17"ELECTRIC
4' - 5"
PENTABOLTLOCK COVER
5' - 6"
18"
SIDE VIEW4" X 4"
KNOCKOUT
(2 PLACES)
APPROX 27"APPROX 40"20"
CONDUITS ENTER FROM BENEATH
AT ONE END OF HANDHOLE
SINGLE PHASE SECONDARY HANDHOLE EXCAVATION DETAIL
Not to scale
FLOW DIRECTION
LAY 8" BOTTOM SKIRT ON TOP OF NATIVE SOIL,
SECURE WITH PEA GRAVEL BAGS.
6'
3'
8"
TECHNIQUES FOR EROSION AND SEDIMENT CONTROL
SILT FENCE DETAIL
Not to Scale 0150.3200
POWER GENERAL NOTES - COMMERCIAL PROJECT
8.
EXCAVATION: The customer is to provide all trenching, backfill, vault excavations, compaction and
restoration per this sketch and per PSE standards. A minimum protective cover of 36" is required over
PSE's primary voltage equipment and 24" is required of PSE's secondary voltage equipment. The customer
will provide any and all shoring or they will side slope the trench to 1:1.
All materials to be installed in accordance with Puget Sound Energy's (PSE) standards. Any deviation from
this work sketch must be AUTHORIZED by PSE's Project Manager and NOTED on the Foremans' Copy.
All switching arrangements and/or outage arrangements are to be made with the Project Manager at least
three (3) working days in advance.
Contact the Utilities Underground Location Center (1-800-424-5555) at least 48 hours prior to commencing
work to get the underground facilities located.
STAKING: The customer will provide all staking (transformer, handhole, trench, grade, lot, pole, sidewalk,
etc.). See sketch and details for locations. Equipment locations must be approved by the Project Manager.
SITE PREPARATION: The work area will be at or near finished grade, clear of trench spoils or construction
materials which would restrict construction and/or equipment access, before work can begin.
Roads shall be paved or have a compacted , crushed rock base in place.
CLEARANCES: Transformers require a minimum of 6 feet from fire fighting equipment, 10 feet from
combustible walls, overhangs, doors, and windows, and a minimum of 5 feet from the back of curb (or guard
posts will be required per PSE standards). All conduits and vaults are to be at least 5 feet away from water,
storm and sewer lines when paralleling them in the right of way, and at least 1 foot when crossing them, or
as required by your local municipality.
All work is to be done in accordance with local municipal and county permit requirements as applicable.
Customer/Developer is responsible to provide, install and maintain all secondary service cables, conduits
and crossings from the individual unit's meter base to the designated connection point on private property.
Inclement weather conditions may cause delays in construction times and dates.
1.
2.
3.
4.
5.
6.
7.
9.
11.
10.
MFP20000288