HomeMy WebLinkAboutAdden 1 � Washington State cAG-19-333 , Adden #1-20
VI/ Department of Transportation
Supplemental Agreement Organization and Address
Number I Gray&Osborne, Inc.
Original Agreement Number 1130 Rainier Avenue South, Suite 300
Seattle, WA 98144
CAG-19-333
Phone: (206)284-0860
Project Number Execution Date Completion Date
11/26/2019 December 31,2022
•
Project Title New Maximum Amount Payable
2020 Street Patch and Overlay $78,355.45
Description of Work
In continuation of the City of Renton annual Street Overlay Program,this project will resurface and repair local streets,collector
streets, and alleyways at various locations in the City. The 2019-2020 Curb Ramps for Overlay project is under a separate
agreement.
The Local Agency of City of Renton
desires to supplement the agreement entered in to with Gray&Osborne;Inc.
and executed on November 26,2019 and identified as Agreement No. CAG-19-333
All provisions in the basic agreement remain in effect except as expressly modified by this supplement.
The changes to the agreement are described as follows:
Section 1, SCOPE OF WORK, is hereby changed to read:
The Scope of Work described in the original agreement is amended to add the additional work and costs as set forth in Supplement
Agreement 1 Exhibit B attached and incorporated by reference.
II
Section IV, TIME FOR BEGINNING AND COMPLETION, is amended to change the number of calendar days
for completion of the work to read: No Change.
III
Section V, PAYMENT, shall be amended as follows:
As set forth in Supplement Agreement 1, Exhibit A attached and incorporated by reference adding$54,790.29. Basic Agreement
$23,565.16+Supplement Agreement 1 $54,790.29=$78,355.45.
,`oo1111111 /14
as set forth in the attached Exhibit A, and by this reference made a part of this supplement,cF 4aENr®°''.,
If you concur with this supplement and agree to the changes as s ted above, please sig ki •e Appropgiate%,
spaces below and return to this office for final action. =v � �� •
By: Michael B.Johnson. P.E., President By; 5c,•.�
Ma Ar n o
ATTESTS: _ r RpgRn;FOs���•
onsultant Signature J a s n . S e h, City"O 1le' 1
•
ae
DOT Form 140-063
Revised 09/2005
EXHIBIT A
Summary of Payments
Basic
Agreement Supplement No. 1 Total
Direct Salary Cost $7,412.80 $16,981.55 $24,394.35
Overhead
(Including Payroll Additives) $13,939.03 $31,932.11 $45,871.14
Direct Non-Salary Costs $137.75 $1,121.80 $1,259.55
Fixed Fee $2,075.58 _ $4,754.83 $6,830.41
Total $23,565.16 $54,790.29 $78,355.45
Exhibit A-i
Project Name: 2020 STREET PATCH AND OVERLAY
Budget Estimate
Employee Brian Sourwine Tani Stafford . Brian Bollen Darla Foley Michael Ballard' Rick Bond Jason Dell Brian Schulkin Phil Marshall Ron Albrecht Zack tiebowita
Function/Title Principal/PM PrincioaVPM Civil Engr Technician Engineer in Training Prof licensed Surveyor Surveyor Surveyor' Technician Surveyor Surveyor Contract Contract
Employee Rate $52.10 552.50 537.75 520.50 52650 54535 $33.50 $34.00 $37.25 534D0 $25D0 Totals . Hours
Task. Description hrs hrs hrs S hrs S hrs 5 hrs S hrs S hrs $ hrs $ hrs s hrs S
4 Project Management-Final Design. 50.00 14 5735.00 $0.00 $0.00 - 50.00 50.00 " $ODD $0-00 50.00 $0.00 $0.00 5735.00 14.0
5 Prepare 90tiP5&3 -- 50.00 38 51,995.00 94 53,54850 -:2 541.00 "16 5424.00 - - ' S0D0 "- $O0D 50.00 "110 54.09750 50.00 ' ' S0.00 510,106.00 260.0
6 Prepare Bid Does `-' 50.00 '10 5525.00 '36 S 359D0 '2 541.110 "'-8 $2121:10 '-1 545.25 -'- 5000 ' S0.00 70,32.60750 50.00 ` 50.00 54,789.75 127D
7 0A/CC -8 $41680 8 S420D0 - 6 S302D0 SaDO E 5212D0 ' S0 D0 S0D0 . 50.00 - • $0.00 - : $0.00 ' $0.00 51,35080 32.
Hourly Subtotals 0. 541680 70 $3,675.00 138 55,20950 4 58200 32' 584800 1 545.25 0 SODD 0 50D0 1E0 56,705.00 ' 0 50.00 0 $0.00 $16,981.55 433.0
Mgt Res-Old Services -
$0.00 $0.00' 50.00 ' $0.00 SOLO t • S000. 50D0 1 50.00 50.00, 1 50.00` 5000 50.00
Hourly Totals 8 541680 70 53,675.00 138 55,20950 4 .582.00 32 584800 1 545.25 0 $0D0 0 50.00 180 58705.00 0 50,00 0 50.00 516,98155
Direct labor 516,98155
Fee 0.28 54.15483
Overhead 18804 53193211
Expenses , 51,121.80'
Subcensultants
Total 554,790.29
EXHIBIT B
SCOPE OF WORK
CITY OF RENTON
2020 STREET PATCH AND OVERLAY
AGREEMENT NO. CAG-19-333 (SUPPLEMENT 1)
Gray and Osborne (Consultant) shall provide additional professional engineering services
to the City of Renton(Agency) for the 2020 Street Patch and Overlay project. The
additional work includes developing the 30 percent design to the final bid documents.
ADDITIONAL ENGINEERING SERVICES
The Consultant will provide the following tasks:
Task 4—Project Management—Final Design
Provide overall project management and oversight of the project by the
Principal-in-Charge, for the new development of the design from 30 percent to final bid
documents.
A. Provide overall project management and oversight services to include:
1. Procure sufficient internal staff resources to dedicate to the project.
2. Prepare a project schedule in XLS format
3. Manage project budget and schedule.
4. Provide monthly progress report spreadsheets and invoices.
B. Hold project coordination meetings between the Agency and the
Consultant.
Deliverables (Notice to Proceed (NTP) and.Ongoing to.1 Year following NTP)
• Invoices/Reports
• Coordination Meeting Minutes
Assumptions
• A total of two meetings will be held between the Agency and the
Consultant during the project at the Agency's office.
G&O 1119668 Page 1 of 3
Task 5—Prepare 90 Percent PS&E
Prepare 90 percent design plans, specifications, and cost estimates for Agency review.
A. The Contract Provisions will incorporate the 2020 WSDOT Standard
Specifications and City of Renton Standards.
B. The plans will include sawcut limits, site preparation/TESC plans, paving
and permanent channelization plans, traffic control plans (site specific for
Talbot Road South only), City of Renton Standard Details, and project-
specific details and survey control.
C. Prepare the estimate based on the 90 percent design level quantities and
recent bid tab information for unit prices.
D. Coordinate proposed improvements with utility companies and King
County Metro Transit.
E. Review the 90 percent design with Agency staff.
Deliverables (3 Months Post=NTP to 3.5 Months Post-NTP)
• Up to 29 plan sheets will be included in the preliminary plan set including:
o Cover and Vicinity Map (one sheet)
o Legend and Sheet Index and General Notes (one sheet)
o Site Preparation Plans (nine sheets) showing Planing, Sawcutting,
Subgrade Repair/TESC
o Paving Plans and Channelization and Signing Plan (six sheets)
o Alley Storm Plan/Profile (three sheets)
o Typical Details for Planing, Overlay, Subgrade Repair, Casting
Adjustment, Catch Basins, Storm Trench Backfill, and Monument
Details (five sheets)
o General Traffic Control Plans (non-site specific) (three sheets)
o Site Specific Traffic Control Plans for Talbot Road South(one
sheets)
Task 6—Prepare Bid Documents
Prepare final design plans, specifications, and cost estimates for use as bid documents
suitable for bidding, award, and construction of the project.
A. Prepare final bid/construction plans in Agency-approved format to include
title sheet, legend, vicinity and location map, plan sheets, special notes,
special details, etc.
G&O f{19668 Page 2 of 3
B. Prepare final Contract Provisions in WSDOT format to include proposal,
contract, bonding documents, and technical specifications. Incorporate
any revisions from the Agency.
C. Prepare final quantity takeoff and construction level construction cost
estimate.
Deliverables (3.5 Months Post-NTP to 4 Month Post-NTP)
• Signed Bid Documents (two hard copies, one PDF, one ACAD, and one
Word DOC file)
• Signed Engineer's Estimate (one PDF and one XLS file)
Task 7—Quality Assurance/Quality Control
A. Oversee one in-house QA/QC meeting at the Consultant's office during
the course of the design project. The meetings will include senior project
staff, selected design team members, and Agency staff(as desired).
Meetings are to take place at the following levels:
1. Prefinal Design
B. Ensure incorporation of relevant recommendations and suggestions into
bid/construction documents resulting from QA/QC reviews.
Deliverables (Ongoing to 4 Months Post-NTP)
• Memo of Review Comments after the Review.
c&so#19668 Page 3 of 3