CONTRACT: Surveillance System City of Renton-Evidence Storage Building
CAG-19-364
CONTRACTOR: ABSCO Solutions
CHANGE ORDER: 1
SUMMARY OF PROPOSED CHANGE:
Reason/Justification:
Missed 10%Sales Tax to the Contract
DESCRIPTION:
Item Qty. Description Unit Price Amount
No. w/WSST
1 1 Missed Sales Tax $ 1,742.50 $ 1,742.50
Total this Change Order: $ 1,742.50
ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT
AMOUNT(W/WSST) AMOUNT THIS ORDER(W/WSST) TOTAL AFTER CHANGE
$ 17,425.00 $ 17,425.00 $ 1,742.50 $ 19,167.50
Additional Calendar Days:
(xx calendar days)(written U)calendar days-Extension of Time.Completion Date is(date).
The payment specified and agreed to in this change order includes every claim by the contractor for any
extra payment with respect to the work described in this change order. The work covered by this change
order must be performed under the same terms and conditions as that included in the original
agreement. All of the other terms of the original agreement remain in effect.
SIGNATURES: ,C1,....751
Contractor: 7{/ e, Al e rms —f 1 r? Date:
Project Manager: t11/1 /6111 I.y Date 3/a/ 0,a o