AMENDMENT NO. 3 TO AGREEMENT FOR CEDAR RIVER
TRESTLE BRIDGE CONSTRUCTION SUPPORT - ACCESS
MODIFICATION
THIS AMENDMENT, dated /(2,f 1t_ I C1 , 2020, is by and between the City of Renton
(the "City"), a Washington municipal corporation, and WSP USA, Inc. ("Consultant"), a New York
corporation. The City and the Consultant are referred to collectively in this Amendment as the
"Parties." Once fully executed by the Parties, this Amendment is effective as of the last date
signed by both parties.
Whereas, the City engaged the services of the Consultant under Agreement CAG-18-109, dated
June 5, 2019, to provide necessary services for the Cedar River Trestle Bridge Repairs (referred
to herein as the "Agreement");
Whereas,the Parties wish to amend the Agreement to change the scope of work and change the
compensation in order to incorporate construction support services to develop
recommendations for allowable construction loads to access the left bank bridge pier over the
timber trestle and steel bridge.
NOW THEREFORE, It is mutually agreed upon that CAG-18-109 is amended as follows:
1. Scope of Work: Section 1, Scope of Work, is amended to add work as specified in Exhibit
A, which is attached and incorporated herein.
2. Compensation: Section 4, Compensation, is amended so that the maximum amount of
compensation payable to Consultant is increased by$ 5,619.00 from $ 100,461.00
to $ 106,080.00 , plus any applicable state and local sales taxes. The additional
compensation shall be paid based upon Work actually performed according to the rate(s)
or amounts specified in Exhibit A, which is attached and incorporated herein.
3. All terms of the Agreement not explicitly modified herein shall remain in full force and
effect and such terms shall apply to Work performed according to this Amendment as if
fully set forth herein.
IN WITNESS WHEREOF,the Parties have voluntarily entered into this Amendment as of the date
last signed by the Parties below.
CITY OF RENTON CON4WE IIEENT/FEDERAL WAY OFFICE
LEADER
PAULA GARTNER-
/, 08:33 41 AM 03=9 0/Ny0T04✓
By: ,� ,
,, By:
Kelly Beym r Paula J. Gartner
Community Services Administrator Vice President — Federal Way Office
Leader
3/112-0 3/12/2020
Date Date
Approved as to Legal Form
By:
Shane Moloney
Renton City Attorney
Contract Template Updated 01-15-2020
e)
PAGE 2 OF 2
N N ) EXHIBIT A
March 5, 2020
Mrs. Betsy Severtsen
Capital Projects Coordinator
City of Renton
1055 South Grady Way
Renton,WA 98057
Subject: Modification of Contract CAG-18-109 for Cedar River Trail Bridge Construction Support—
Fee Modification
Dear Mrs. Severtsen:
•
WSP USA is pleased to submit our fee proposal modification to the City of Renton to provide services
for the Cedar River Bridge Repairs project. Our fee modification is to incorporate construction support
services to develop recommendations for allowable construction loads to access the left bank bridge pier
over the timber trestle and steel bridge. Included in this modification is calculations for allowable
construction loads,drawings showing recommended supports and maximum wheel loads.
Modification 1 —Environmental Permitting Contract Authorization $96,661
Modification 2—Contract Extension and Rate Mod.Contract Authorization $100,461
Modification 3 —Construction Support Requested Amount: $5,619
Proposed Total Contract Amount: $106,080
The proposed contract modification would add$5,619 (Five Thousand Six Hundred and Ninteen dollars)
to perform this work on a time-and-materials basis. The total contract value would increase to a
maximum of$106,080. We will perform the work in accordance with the terms and conditions as were
accepted by the City of Renton and WSP per contract CAG-18-109.
We look forward to the opportunity to continue in assisting the City of Renton with its engineering needs.
Sin y,
Paula J. Gartner,PE, LEED AP
Vice President—Federal Way Office Leader
PJG:GDN:
Attachment A —WSP Fee Proposal
WSP USA
Suue 300
N"tR Akerue
S 206 431 24O3
vv,4..Dm
ATTACHMENT A- PROPOSAL FOR ASSESSMENT SERVICES
Location: Renton,Washington N.
Facility: Cedar River Bridge,Steel Truss Inspection and Trestle Repair Documents
Fee Estimate-WSP Labor,and Expenses-28 February 2020
Senior Project Project Senior Senior Comm.
Project Manager Engineer Const. CAD Specialist
Manager Specialist Operator
Item $280 $226 $143 $151 $133 $114 Costs
Task 1 -Project Management/Coordination $ 1,161
1.1 Management/Coordination/Document Control 1 1 $ 257
1.2 Client Communications including draft review $ -
1.3 Quality Assurance/Quality Control Plan $ -
1.4 Quality Control Review 4 $ 9Q4
1.5 Budget Monitoring and Invoicing $ -
Task 6-Bid Support and Construction Support Services $ 4,458
6.8 Structural Calculations-Access Modifications 1 8 $ 1,424
6.9 Drawings-Access Modifications 2 8 10 $ 3,034
$ -
$ -
$ -
$ -
$ -
Total WSP Hours: 3 _ 4 17 10 1 32
Subtotal WSP Labor(with Overhead&Profit):j $840 I $904 I $2,431 I I $1,330 I $114 I $5,619
Sub-Consultants
Subtotal Subconsultants:
Expenses(BergerABAM only)
Mileage= $ 0.575 per mile x miles x day(s)=
Meals&Miscellaneous Expenses= per day x people x day(s)=
Subtotal Expenses:
TOTAL COST,ROUNDED: Say: $5,619