CITY OF RENTON
Community Services Department
CONTRACT CHANGE ORDER AGREEMENT
3.4.2020
CONTRACT: City of Renton
CAG-19-243 Sunset Neighborhood Park,Phase 2
CONTRACTOR: Terra Dynamics,Inc.
CHANGE ORDER: No.1
SUMMARY OF PROPOSED CHANGE:
Reason/Justification:
CIP Concrete Modification to Decorative Mist Feature,HBB Landscape Architecture,12.20.2019
DESCRIPTION:
Item Qty. Description Unit Price Amount
No. w/WSST
1 1 CIP Modification to Decorative Mist Feature $ 4,597.23
L-6/1,12.20.2019
Total this Change Order: $ 4,597.23
ORIGINAL CONTRACT CURRENT CONTRACT NET CHANGE REVISED CONTRACT
AMOUNT(W/WSST) AMOUNT THIS ORDER(W/WSST) TOTAL AFTER CHANGE
$ 4,059,000.00 $ 4,059,000.00 $ 4,597.23 $ 4,063,597.23
Additional Calendar Days:
(0 calendar days)Substantial Completion Date is May 31,2020.
The payment specified and agreed to in this change order includes every claim by the contractor for any
extra payment with respect to the work described in this change order. The work covered by this change
order must be performed under the same terms and conditions as that included in the original
agreement. All of the other terms of the original agreement remain in effect.
SIGNATURES: /
Contractor: µt`�— — Date: y/,i-/ 0 2-_
Project Manager: 4 '4 — Date 5 /'/G t 20
, ��/ Date:
3��7�Zo
Approved By:
iiTERRA
DYNAMICS.
PO Box 2479•Auburn,WA 98071
253-880-3100•Fax:253-880-3109
SNP2 COP-001 Colored Concrete at Mist Feature 2/27/2020
Labor Rate/MH No. Hours Subtotal
Foreman $ 64.26 1 6 $ 385.56
Group 4 Operator $ 66.23 1 4 $ 264.92
General Labor $ 61.72 2 8 $ 987.52
Labor $ 1,638.00
Overhead 12% $ 196.56
Profit 6% $ 110.07
Total $ 1,944.63
Equipment Rate/MH No. Hours Subtotal
Takeuchi TB 285 Excavator $ 45.81 1 4 $ 183.24
Equipment $ 183.24
Overhead 12% $ 21.99
Profit 6% $ 12.31
Total $ 217.54
Materials Qty Unit Cost/Unit Subtotal
Concrete disposal 1.00 CY $ 22.00 $ 22.00
Materials $ 22.00
Overhead 12% $ 2.64
Profit 6% $ 1.48
Total $ 26.12
Subcontractors Qty Unit Cost/Unit Subtotal
Caliber Concrete 60 SF $ 28.66 $ 1,719.60
$
Subcontactors $ 1,719.60
Overhead 4% $ 68.78
Profit 4% $ 71.54
Total $ 1,859.92
Small Tools 3% $ 49.14
Sub Total $ 4,097.35
Insurance/bond 2.0% $ 81.95
GRAND TOTAL $ 4,179.30
verve.Orr /�
Vern Orr Project Manager .1—\O/c -ta 4 11,i3
,f 1-19q723
COXC*Z?E PATTERNED CONCRETE
CONSTRUCTION INC. OF SEATTLE
Date Due : February 17,2020 12:00 AM
Prospective Project Contractor -' - -- - -�-
[t�)R I'N.f f,yt)!_l_i Ctf.C'If'll �a"t (1yt.t
4.11.411110109.44,.
Att. : Estimator or Bid Coordinator Proposal# : 1
Re. : Sunset Neighborhood Park PH 2-Added Integral Colored Paving Authored by : Todd
Loc. : Renton,WA
Approved by Todd
ITEM# BID ITEM&DESCRIPTION QUANTITY UNIT PRICE AMOUNT
Cement Concrete Sidewalk(6"Thick)Integral Color W/WWM 60 SF $28.66 $1,719.60
ProjectTotal:I $1,719.60
SECTION 1.0-NOTES
The pricing contained herein is dependant on all work items listed being performed by Caliber Concrete Construction Inc. Any addition/deletion of work items or quantities could result in
amended pricing.All above quantities are approximated based on information given at time of bid. All final payments will be based on field measurements. Due to current backlog Caliber
Concrete Construction Inc.cannot guarantee meeting the exact schedule. The insurance coverage included in this proposal is the Master Pak Endorsement"CG 84 12 03". Any additional
endorsements will be provided at$1,000.00 per project.
SECTION 1.1 -EXCLUDED
Pumping,night work,sub grade,layout,embeds, joint seal&sealant,saw cutting,concrete washout(eco pan),sand blasting,traffic control,flagging,barricades,scaffolding,fall protection,
extruded curbing,pipe bollards,job water,bonds costs,permits,material testing, pretreat,design fees,inspection fees,engineering,exterior site,retaining,or masonry walls or footings,
precast concrete hardeners and sealers,water proofing, shade sand,demolition and removal of any existing(including asphalt),utility adjustments,assessed penalty clauses.
•
SECTION 1.2-EXPIRATION
Caliber Concrete Construction Inc.reserves the right to withdraw this proposal if not accepted in writing via signed letter of Internet or proposal within 30 days of bid due date. Acceptance
of the prices contained herein constitutes agreement of all the terms and conditions in the above sections
Caliber Concrete Authorized Sianature Acceptance of Proposal
The above prices,specifications,and conditions are satisfactory and are
0`'" hereby accepted. Caliber Concrete is authorized to do the work as specified.
7 Payment will be made as outlined above.
Acceptance: