HomeMy WebLinkAboutCO 2CAG-19-243, CO #2-20
Terra Dynamics
Sunset Park CO #1
Accurate Electric
&
Service Inc
1429 Ave D #356
Snohomish, WA 98290
Phone: 425-263-9477
Fax: 425-263-9156
Change Order #1
Date: April 17, 2020
Customer Name: Terra Dynamics
Address:
City: Zip: 9
Phone: Fax:
E-mail:
Site Address:
Sunset Neighborhood Park
Renton, WA
Job Description:
Re-route conduits for Rain Garden
1 – Go through and demo out the wires & all conduit that is going
to be in the way of running new conduits
2 – Install (2) new 2” conduits from existing handhold over to
the next one in line
3 – From the 2nd handhold, run a conduit straight over to the
last pole for fiber
4 – From the 2nd handhold, run (1) conduit to each handhold.
From there, over to where the light pole is
Labor:
72hrs @ $85/per 6120.00
15% M/U 918.00
Total Labor 7038.00
Terra Dynamics
Sunset Park CO #1
Material: 2092.07
15% M/U 313.81
Total Material 2405.88
Bid Price: $9443.00
One year warranty on all parts and labor
Not included in price:
Sales Tax
Any additional work not stated
Terms of Agreement
Progressive
Accept _____________
Signature: ________________________________________________
Steve Billington 425-263-9477 or 206-778-1186
Accurate Electric & Service Inc
SNP2 COP-003 Relocate existing conduits at Raingarden 4/27/2020
Labor Rate/MH No.Hours Subtotal
Foreman 64.26$ 1 4 257.04$
Group 4 Operator 66.23$ 1 6 397.38$
General Labor 61.72$ 2 6 740.64$
Labor 1,395.06$
Overhead 12%167.41$
Profit 6%93.75$
Total 1,656.22$
Equipment Rate/MH No.Hours Subtotal
Takeuchi TB 285 Excavator 45.81$ 1 6 274.86$
Equipment 274.86$
Overhead 12%32.98$
Profit 6%18.47$
Total 326.31$
Materials Qty Unit Cost/Unit Subtotal
Sand Bedding 2.00 Tons 24.00$ 48.00$
Materials 48.00$
Overhead 12%5.76$
Profit 6%3.23$
Total 56.99$
Subcontractors Qty Unit Cost/Unit Subtotal
Accurate Electric 1 LS 9,443.00$ 9,443.00$
-$
Subcontactors 9,443.00$
Overhead 4%377.72$
Profit 4%392.83$
Total 10,213.55$
Small Tools 3%41.85$
Sub Total 12,294.92$
Insurance/bond 2.0%245.90$
GRAND TOTAL 12,540.81$
Vern Orr
Vern Orr Project Manager
SNP2 COP-002 Weather Days 3/10/2020
Labor Rate/MH No.Hours Subtotal
Labor -$
Overhead 12%-$
Profit 6%-$
Total -$
Equipment Rate/MH No.Hours Subtotal
Equipment
Overhead 12%
Profit 6%-$
Total -$
Materials Qty Unit Cost/Unit Subtotal
Materials
Overhead 12%
Profit 6%-$
Total -$
Weather Days Date
1/6/2020
1/10/2020
1/14/2020
1/15/2020
1/16/2020
1/23/2020
1/28/2020
1/29/2020
1/31/2020
2/4/2020
2/5/2020
2/6/2020
2/7/2020
Total Days 13
Total Days 13
Vern Orr
Vern Orr Project Manager