Accrete Construction LLC
Phone 253-286-3900 - www.accrete.build
801 Valley Ave NW Ste. A, Puyallup WA 98371
UUrrggeenntt__xx__ NNeeeedd RReessppoonnssee BByy:: 0055//1199//22002200 RRFFII ## 111144
Project: Weatherly Inn - Renton Date: 05/19/2020
Accrete Job #: W110001 Arch. Job #:
Attention: Ross Jarvis
Subject: Conflict between fire hydrant lateral and storm Reference: WT-1
Subject Matter: Architectural Structural Mechanical Electrical Civil
Request:
As discussed, there is a conflict between the storm sewer and the lateral for the fire hydrant between
the building and the trash enclosure as the storm and the water are at the same elevation at this
location.
As noted on the attached, Rino Construction suggests installing bends to lower this lateral to go under
the storm pipe and installing a deeper depth hydrant.
Please confirm that this is acceptable or provide an alternate solution, provide updated plan sheets and
submit revisions to the city if necessary.
Attachments: _Rino RFI 3.pdf ______________ Requested By: Mark Richardson
Cost Impact Schedule Impact Impact Yet To Be Determined
RFI # 114
Response:
This is an acceptable solution. Please see attached for additional notes (magenta). I will submit to the
City and copy Mark Richardson.
Response By: Ross Jarvis, PE Date: 05/19/2020
Request For Information
XXXXXXXXXXXXXXXXXXXXXX Request for Information
RINO CONSTRUCTION
PO Box 667
Maple Valley, WA 98038
360‐469‐4941 OFFICE
425‐728‐8449 FAX
RFI No: Revision No:0
Date:
Project No:
Date Required
Drawing
YES NO
Use vertical bends and dive lower than the storm pipe and install a deeper bury depth fire hydrant.
Subject:Storm Utility and Temporary Electrical Conduit conflict
Requested By:Nick Rawlins
Email ASAP
The 6" fire hydrant pipe at the east side of the upper building slab is in conflict with the storm line. The Invert elevations are the same for both
pipes.
WT‐01 Spec Section
Weatherly 3
Attention Mark Richardson
Accrete Construction 19016
Signed:
Signed:
Signed:
Corrective Action Approved:Correct as Follows:Response:
Note: All signatures required to Close‐Out RFI for Document Control Binder
Request for Information / Proposed Corrective Action:
Description of Issue:
Date:
Date:
Date:
Date:RFI Sign Off:
Response By:
LOGO HERE
5/18/2020
Company
Project:
DISTRIBUTION: 1 ‐ ORIGINAL TO DOCUMENT CONTROL BINDER
1 ‐ COPY TO RFI ORIGINATOR 1 ‐ COPY TO PERSON COMPLETING TASK
Response Approval By:
Work Completed By:
Signed:
IN COMPLIANCE WITH CITY OF RENTON STANDARDSSENNIOALFEP R ON D43668IGERSERETSSTATEOFWASHIGINEERGTO N
ROSS D. JARVISWATER UTILITYagafour 07/31/2019DEVELOPMENT ENGINEERINGjchavez 08/07/2019Conflict between storm line and water hydrant runINSTALL (2) 6" VERTICAL BEND W/ RESTRAINEDJOINT AND THUST BLOCKING. PROVIDE 18"VERTICAL SEPARATION BETWEEN STORMINVERT AND WATER LINE CROWN.SD SD SD SD SD SD SD SD
RELOCATION OF HYDRANT LATERAL BELOW NEW STORM LINEAPPROVED BY: ABDOUL GAFOUR - WATER UTILITY MANAGER- CITY OF RENTON5/20/20