CHANGE ORDER PROPOSAL
3323 Owner: City of Renton
Change Order Proposal #:17 Date:
CCI No.RFI #:44 ASK#
FO #:FLDR #:
11.03.C.4.a DIRECT LABOR COSTS
Trade Wage Rate Proposed Hours Cost
See Worksheet 0 -$
-$
-$
-$
-$
Labor Cost 1,968.16$
Direct Supervision
Safety
Small Tools & Consumables
Subtotal Direct Labor Cost 1,968.16$
29%570.77$
11.03.C.4.b DIRECT MATERIAL COSTS
Description Quantity Units Unit Cost Cost
See Worksheet -$ -$
-$ -$
-$ -$
-$ -$
Material Cost 1,015.00$
21% 213.15
11.03.C.4.c CONSTRUCTION EQUIPMENT USAGE COSTS
Description Rate Propsed Hours Cost
See Worksheet -$ 0 -$
-$ 0 -$
-$ 0 -$
Equipment Cost 1,152.00$
21%241.92$
DIRECT COST SUMMARY
Subtotal Direct Costs
OH & P on Direct Costs
11.03.C.4.d PRIME SUBCONTRACTOR'S PROPOSALS
Name Cost
Ashford 3,232.55$
Subcontract Cost 3,232.55$
OH & P on Subs by the Prime Contractor 12%387.91$
COST SUMMARY
Subtotal 8,781.46$
Bond and Insurance
TOTAL COST OF PROPOSED ESTIMATE WITHOUT SALES TAX 8,781$
Cost of delay to contract due to this change may not be included in this proposal,
April 16, 2020
McClure & Sons Inc. Project No.:
Per RFI 044 response, revise Sheet E-3: Add 1" conduit and#10
conductors for Site Light Pole. Change per Ashford's proposal.
Extra time to deal with existing conduits or pathway will be paid
no force account. Bid assumes that native can be used for
backfill.
Change Order Description:
Kennydale Reservoir Schedule B WTR-27-3956
4/16/2020 Page 1 of 6 McClure and Sons, Inc.
CHANGE ORDER PROPOSAL
but will be accessed at completion of this change order.
4/16/2020 Page 2 of 6 McClure and Sons, Inc.
EQUIPMENT RATES
Hourly Rate
Pumps
44,000 gph $18.50
125,000 gph $28.60
25' Hose $2.00
1-Ton Truck $18.50
Water Truck $28.16
Dump Truck 10yd $54.14
Marooka Dump Track $59.67
Tractor $30.00
580 Backhoe $34.51
345/992 Excavator $154.00
330 Excavator $130.00
200 Excavator $79.30
312 Excavator $56.00
Mini Excavator $28.00
Bucket Thumb $15.85
Hoepak $17.00
Boom Truck $15.67
Grout Pump $44.56
Drill Motor (APE or equal) $86.54
Leads (110+) $13.96
Auger (90') $15.00
Pickup (360) $19.93
Forklift $35.00
Dozer D-5 N LGHP $51.85
Komatsu D39PX-21 $48.00
Crane 70 Ton Lattice $197.90
Crane Grove RT750 $120.38
Crane P&H 40 $113.60
Crane Grove RT58E $77.00
Boom Extensions $5.00
6000 lb rough terrain fork lift $33.81
10,000 lb rough terrain fork lift $46.59
Sheep Foot Compactor $76.00
Trench Compactor $32.00
Roller $81.00
Skid Steer $22.00
Loader $48.00
Generator 175kw $33.50
Jumping Jack $11.50
Does not include delivery, return, fuel, operator, markups, operating cost or rental equipment.
Rental Equipment Bare for MSI Owned Equipment Only
4/16/2020 Page 5 of 6 McClure and Sons, Inc.
3323
Change Order Description:
Change Order Proposal #:17 Date:
WCD / CPR #:0 RFI #:44 ASI#0
Cost of delay to contract due to this change may not be included in this proposal,
but will be accessed at completion of this change order.
Price good for 30 days.
Change in time to contract completion:
2. The Owner required the Contractor to address the additional work by WCD which directly impacted
the Contractor's capability to perform the original work. In particular, due to the nature of the above
work the Contractor was unable to concurrently perform originally contracted work in this structure.
Consequently the Contractor was unable to resequence or reorganize the work such that the CPM
and Project cash flow would remain unaffected.
3. This delay, as substantiated by supporting documentation, did effect the CPM and in particular the
work on this structure and thereby negatively effected the timely completion of Work under the
Contract or timely completion of a portion of the Work for which time of completion was specified.
4. The additional work will prevent McClure and Sons, Inc. from completing the Project within the
current Contract completion date.
McClure & Sons Inc. Project No.:Owner No:
McClure and Sons, Inc. submits that due to no fault, act or omission on the part of
McClure and Sons, Inc. the work and circumstances involved with above Change
Order were effected by the conditions and sole actions of the Owner and/or Owners
Representative. McClure and Sons, Inc. further submits that the above change was
the sole cause of the time extension impact and could not have been avoided by any
reasonable means. McClure and Sons, Inc. has made all reasonable efforts to prevent
and mitigate the effects of the delay but herein requests a Contract Time Extension
due to the following:
Per RFI 044 response, revise Sheet E-3: Add 1" conduit
and#10 conductors for Site Light Pole. Change per
Ashford's proposal. Extra time to deal with existingApril 16, 2020
1. The delay was caused by the Owner and was of an unknown scope at the time the delay arose.
4/16/2020 Page 6 of 6 McClure and Sons, Inc.
CHANGE ORDER PROPOSAL
3323 Owner: City of Renton
Change Order Proposal #:18 Date:
CCI No.RFI #:49 ASK#
FO #:FLDR #:
11.03.C.4.a DIRECT LABOR COSTS
Trade Wage Rate Proposed Hours Cost
See Worksheet 0 -$
-$
-$
-$
-$
Labor Cost 150.68$
Direct Supervision
Safety
Small Tools & Consumables
Subtotal Direct Labor Cost 150.68$
29%43.70$
11.03.C.4.b DIRECT MATERIAL COSTS
Description Quantity Units Unit Cost Cost
See Worksheet -$ -$
-$ -$
-$ -$
-$ -$
Material Cost -$
21%
11.03.C.4.c CONSTRUCTION EQUIPMENT USAGE COSTS
Description Rate Propsed Hours Cost
See Worksheet -$ 0 -$
-$ 0 -$
-$ 0 -$
Equipment Cost 112.00$
21%23.52$
DIRECT COST SUMMARY
Subtotal Direct Costs 329.90$
OH & P on Direct Costs
11.03.C.4.d PRIME SUBCONTRACTOR'S PROPOSALS
Name Cost
Ashfords 4,032.77$
Subcontract Cost 4,032.77$
OH & P on Subs by the Prime Contractor 12%483.93$
COST SUMMARY
Subtotal 4,846.66$
Bond and Insurance
TOTAL COST OF PROPOSED ESTIMATE WITHOUT SALES TAX 4,847$
Cost of delay to contract due to this change may not be included in this proposal,
but will be accessed at completion of this change order.
April 16, 2020
McClure & Sons Inc. Project No.:
Per RFI 049 Response, Add a 3" Fiber Hand-Hole on site for
future use. Per Ashfords scope.
Kennydale Reservoir Schedule B WTR-27-3956
4/16/2020 Page 1 of 5 McClure and Sons, Inc.
EQUIPMENT RATES
Hourly Rate
Pumps
44,000 gph $18.50
125,000 gph $28.60
25' Hose $2.00
1-Ton Truck $18.50
Water Truck $28.16
Dump Truck 10yd $54.14
Marooka Dump Track $59.67
Tractor $30.00
580 Backhoe $34.51
345/992 Excavator $154.00
330 Excavator $130.00
200 Excavator $79.30
312 Excavator $56.00
Mini Excavator $28.00
Bucket Thumb $15.85
Hoepak $17.00
Boom Truck $15.67
Grout Pump $44.56
Drill Motor (APE or equal) $86.54
Leads (110+) $13.96
Auger (90') $15.00
Pickup (360) $19.93
Forklift $35.00
Dozer D-5 N LGHP $51.85
Komatsu D39PX-21 $48.00
Crane 70 Ton Lattice $197.90
Crane Grove RT750 $120.38
Crane P&H 40 $113.60
Crane Grove RT58E $77.00
Boom Extensions $5.00
6000 lb rough terrain fork lift $33.81
10,000 lb rough terrain fork lift $46.59
Sheep Foot Compactor $76.00
Trench Compactor $32.00
Roller $81.00
Skid Steer $22.00
Loader $48.00
Generator 175kw $33.50
Jumping Jack $11.50
Does not include delivery, return, fuel, operator, markups, operating cost or rental equipment.
Rental Equipment Bare for MSI Owned Equipment Only
4/16/2020 Page 4 of 5 McClure and Sons, Inc.
3323
Change Order Description:
Change Order Proposal #:18 Date:
WCD / CPR #:0 RFI #:49 ASI#0
Cost of delay to contract due to this change may not be included in this proposal,
but will be accessed at completion of this change order.
Price good for 30 days.
Change in time to contract completion:
2. The Owner required the Contractor to address the additional work by WCD which directly impacted
the Contractor's capability to perform the original work. In particular, due to the nature of the above
work the Contractor was unable to concurrently perform originally contracted work in this structure.
Consequently the Contractor was unable to resequence or reorganize the work such that the CPM
and Project cash flow would remain unaffected.
3. This delay, as substantiated by supporting documentation, did effect the CPM and in particular the
work on this structure and thereby negatively effected the timely completion of Work under the
Contract or timely completion of a portion of the Work for which time of completion was specified.
4. The additional work will prevent McClure and Sons, Inc. from completing the Project within the
current Contract completion date.
McClure & Sons Inc. Project No.:Owner No:
McClure and Sons, Inc. submits that due to no fault, act or omission on the part of
McClure and Sons, Inc. the work and circumstances involved with above Change
Order were effected by the conditions and sole actions of the Owner and/or Owners
Representative. McClure and Sons, Inc. further submits that the above change was
the sole cause of the time extension impact and could not have been avoided by any
reasonable means. McClure and Sons, Inc. has made all reasonable efforts to prevent
and mitigate the effects of the delay but herein requests a Contract Time Extension
due to the following:
Per RFI 049 Response, Add a 3" Fiber Hand-Hole on site for
future use. Per Ashfords scope.
April 16, 2020
1. The delay was caused by the Owner and was of an unknown scope at the time the delay arose.
4/16/2020 Page 5 of 5 McClure and Sons, Inc.