HomeMy WebLinkAbout0895.06 DFR 1-179.pdfEarth Solutions NWLLc
15365 NE 90'h Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWATER
GENERAL PERMIT - FIELD REPORT
ESNWRep. AK
Time On Site
11:30 AM
WAR-307963
Project Name 14500 Talbot Rd. S., Renton Weatherly Inn
Erosion Control BMPs Overall Needs
(13 Elements) Condition Repair? (§ood; fair; foor)(Yes; No)
1. Preserve Vegetation; Mark Clearing Limits
• Buffer Zones around Sensitive Areas G N
•Silt Fence
2.Establish Construction Access
• Fabric; Quarry Spalls G N • Wheel Wash
•Sweeper Truck
3.Control Flow Rates
• Stormwater Vault or Facility G N •Straw Wattles
•Check Dams
4.Install Sediment Controls
• Silt Fence
• Straw Bale Barriers
• Vegetation
• Straw G N
• Sediment Ponds, Traps & Filters
• Treatment
• Sediment Pond (Temp. or Perm.)
• Water Truck
5. Stabilize Soils
• Nets & Blankets
• Mulch, Bark & Rock
• Hydroseeding; Grass G N • Plastic Sheeting
• Straw Stockpiles
• Stockpiles
• PAM
6. Protect Slopes G N
• Benching; Track-Walking
• Pipe Slope Drains
• Plastic Sheeting; Anchors
7. Protect Drain Inlets
• Catch Basin Inserts G N
• Gutter; Road
8. Stabilize Channels and Outlets N/A N/A
• Channel Lining
• Check Dam
• Outlet Protection
• Nets and Blankets
9.Control Pollutants N/A N/A
• Chemical Storage Area Covered
• Concrete Handling
10.Control Dewatering N/A N/A
11. Maintain BMPs G N
12.Maintain SWPPP & Site Logbook G N
13.Protect Low-Impact Development (LID BMPs)
• Bioretenlion Rain Garden Facilities
• Permeable Pavement N/A N/A
0895.06 Page Report No. 1 of 2 134
Time Off Site Date Day of Week
11:45 AM 2/18/20 Tuesday
Reviewed
��
I RJ Development, LLC
Comments
Silt fence working as intended
Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
Add check dams and straw wattles as needed to
slow stormwater onsite
Add straw as needed throughout the site, 2"
minimum
CB inserts working as intended
N/A
N/A
N/A
See recommended notes
Available upon request
N/A
Earth Solutions I\IWu_c
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWATER
GENERAL PERMIT -FIELD REPORT
ESNWRep. AK
Time On Site
11:30 AM
WAR-307963
Project Name 14500 Talbot Rd. S., Renton Weatherly Inn
Monitoring, Records & Recommendations
0895.06 Page 2 of 2
Time Off Site Date
11:45 AM 2/18/20
Reviewed
I RJ Development, LLC
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? □Yes @No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Qngoing)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2" straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: 40s° F. Clear
Precipitation since last inspection (approximate): 0.19 ___ inches
Precipitation in the last 24 hours (approximate): 0.00 inches
Was water quality sampling part of this inspection? □Yes @ No
lf"Yes":
• Record results in the table below.
Report No. 134
Day of Week
Tuesday
Date
(If Completed)
•Characterize the stormwater discharge, e.g., the presence of suspended sediment, "cloudiness", discoloration, or oil sheen, if
present: N/A
•Hanna Turbidity Meter#
Monitoring Location Turbidity pH Notes (NTU)
Is the site in compliance with the SWPPP and the permit requirements? @Yes □No
lf "No":
•Indicate the tasks necessary to bring the site into compliance in the table above.
•Has the non-compliance been reported to the Department of Ecology?□Yes □No
•Should the SWPPP be modified?□Yes □No �f-"This report is true, accurate, and complete to the best of my knowledge and belief."
Inspector Name: Andrew Kimn CESCL Number: CESCL-EF8183912 Inspection Date: 2/18/20
I
i
Earth Solutions NWuc
15365 NE 90 11, Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep. AK
Time On Site
11:45 AM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
12:00 PM
Page
1/1
Date
2/18/20
Weather
40s°F, Clear
Client/Owner
Report No.
134A
Day of Week
Tuesday
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rina Construction
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
Contact
Mike
Contact
Project No.
Field Supervisor
LAC
Project Manager
Ray
Permit No.
Reviewett. i-)Vi
Reviewed
At the client's request, ESNW rep was onsite to observe or test cut slopes, test pH of stormwater, footing
excavations and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1 :1 (H:V).
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In the filled baker tanks rep observed 12.23 in a baker tank.
Rep observed that contractor added dry ice to lower the pH level. Rep observed that pH level was contained
onsite at a 6.5 pH.
Footings Excavations
Rep observed contractor use a medium sized excavator to excavate and the building footings. Rep recommended
and observed that contractor was over-excavating footings ~4" from designed footing grade. Rep observed
contractor backfill the over-excavation with a 3"-4" lift of 1 ¼" minus crushed rock for the footing subgrade to
increase stability during wall construction. Along the base of the footings, rep observed contractor install miradrain,
6" perforated pipe along the footings, and embed the pipe in a 12" lift of 2" wash rock.
ESNW rep will return to observe earthwork activities when requested by client �t-
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWA TER
GENERAL PERMIT -FIELD REPORT
ESNW Rep. AK
Time On Site
12:45 PM
WAR-307963
Project Name j 4500 Talbot Rd. S., Renton Weatherly Inn
Erosion Control BMPs Overall Needs
(13 Elements) Condition Repair? (Qood; fair; foor) (.Yes; tJ_o)
1. Preserve Vegetation; Mark Clearing Limits
• Buffer Zones around Sensitive Areas G N
•Silt Fence
2. Establish Construction Access . Fabric; Quarry Spalls G N • Wheel Wash
•Sweeper Truck
3. Control Flow Rates
• Stormwater Vault or Facility G N •Straw Wattles
•Check Dams
4. Install Sediment Controls
• Silt Fence
• Straw Bale Barriers
• Vegetation
• Straw G N
• Sediment Ponds, Traps & Filters
• Treatment
• Sediment Pond (Temp. or Perm.)
• Water Truck
5. Stabilize Soils
• Nets & Blankets
• Mulch, Bark & Rock
• Hydroseeding; Grass G N • Plastic Sheeting
• Straw Stockpiles
• Stockpiles
• PAM
6. Protect Slopes G N
• Benching; Track-Walking
• Pipe Slope Drains
• Plastic Sheeting; Anchors
7. Protect Drain Inlets
• Catch Basin Inserts G N
• Gutter: Road
8. Stabilize Channels and Outlets N/A N/A
• Channel Lining
• Check Dam
• Outlet Protection
• Nets and Blankets
9. Control Pollutants N/A N/A
• Chemical Storage Area Covered
• Concrete Handling
10. Control Dewatering N/A N/A
11. Maintain BMPs G N
12. Maintain SWPPP & Site Logbook G N
13.Protect Low-Impact Development (LID BMPs)
• Bioretention Rain Garden Facilities
• Permeable Pavement N/A NIA
0895.06 Page Report No. 1 of 2 138a
Time Off Site Date Day of Week
1 :15 PM 2/24/20 Monday
Reviewe��
J RJ Development, LLC
Comments
Silt fence working as intended
Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
Add check dams and straw wattles as needed to
slow stormwater onsite
Add straw as needed throughout the site, 2"
minimum
CB inserts working as intended
N/A
N/A
N/A
See recommended notes
Available upon request
N/A
Earth Solutions I\IWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWATER
GENERAL PERMIT - FIELD REPORT
ESNW Rep. AK
Time On Site
12:45 PM
WAR-307963
Project Name 14500 Talbot Rd. S., Renton Weatherly Inn
Monitoring, Records & Recommendations
0895.06 Page 2 of 2
Time Off Site Date
1:15 PM 2/24/20
Reviewed
I RJ Development, LLC
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? D Yes @No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Qngoing)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2" straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: 40s° F Clear
Precipitation since last inspection (approximate): 0.00 ___ inches
Precipitation in the last 24 hours (approximate): 0.00 inches
Was water quality sampling part of this inspection? D Yes @No
If "Yes":
• Record results in the table below,
Report No. 138a
Day of Week
Monday
Date
(If Completed)
• Characterize the stormwater discharge, e.g., the presence of suspended sediment, "cloudiness", discoloration, or oil sheen, if
present: N/A
• Hanna Turbidity Meter#
Monitoring Location Turbidity pH Notes (NTU)
Is the site in compliance with the SWPPP and the permit requirements? 0 Yes □No
lf"No":
• Indicate the tasks necessary to bring the site into compliance in the table above.
• Has the non-compliance been reported to the Department of Ecology?D Yes □No
• Should the SWPPP be modified?D Yes D No �f-"This report is true, accurate, and complete to the best of my knowledge and belief."
lnsoector Name: Andrew Kimn CESCL Number: CESCL-EF8183912 Inspection Date: 2/24/20
I
Earth Solutions NWu_c
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep.
AK, TSH
Time On Site
11:45 AM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
2:00 PM
Page
1/1
Date
3/2/20
Weather
40s°F, Rain
ClienUOwner Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rino Construction
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
Contact
Mike
Contact
Project No.
Field Supervisor
LAC
Project Manager 5�{2.
Permit No.
Report No.
143
Day of Week
Monday
the client's request, ESNW rep was onsite to observe or test cut slopes, wall backfill with cement, test pH of
stormwater and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1: 1 (H:V).
Wall Backfill with Cement
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix. Rep observed contractor place
12"-18" lifts for a hoe pack and 6"-8" lifts for a jumping jack during compaction. Rep will return to observe and test
the compaction of the wall backfill as needed.
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In the filled baker tanks rep observed 9.46 NTU and a pH
of 6.5. Rep observed that pH level was contained onsite at 6.5 pH.
ESNW rep will return to observe earthwork activities when requested by client �f-
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNW Rep.
AK,
Time On Site
1:15 PM
Travel Time
1.25 Hr. RT
Project No. Page Report No.
0895.06 1/1 144
Time Off Site Date Day of Week
1:30 PM 3/3/20 Tuesday
Weather
40s°F, Overcast
Client/Owner Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rino Construction
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
Contact
Mike
Contact
Project No.
Field Supervisor
LAC
Reviewi.t-., /
oi.
Project Manager s��
Permit No.
the client's request, ESNW rep was onsite to observe or test cut slopes, footing excavations and earthwork
activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1 :1 (H:V).
Footings Excavations
Rep observed contractor use a medium sized excavator to excavate and the building footings. Rep recommended
and observed that contractor was over-excavating footings ~4" from designed footing grade. Rep observed
contractor backfill the over-excavation with a 3"-4" lift of 1 ¼" minus crushed rock for the footing subgrade to
increase stability during wall construction. Rep used a ½" steel t-probe and observed the footing subgrade to be
very dense, firm, unyielding, and suitable for support of the proposed footings.
ESNW rep will return to observe earthwork activities when requested by client �f-
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWATER
GENERAL PERMIT - FIELD REPORT
ESNW Rep. AK
Time On Site
1:00 PM
WAR-307963
Project Name 14500 Talbot Rd. S., Renton Weatherly Inn
Erosion Control BMPs Overall Needs
(13 Elements) Condition Repair? (Qood; fair; foor) (Yes;No)
1. Preserve Vegetation; Mark Clearing Limits
• Buffer Zones around Sensitive Areas G N
•Silt Fence
2.Establish Construction Access. Fabric; Quarry Spalls
• Wheel Wash G N
• Sweeper Truck
3.Control Flow Rates
• Stormwater Vault or Facility G N •Straw Wattles
•Check Dams
4. Install Sediment Controls
• Sill Fence
• Straw Bale Barriers
• Vegetation
• Straw G N
• Sediment Ponds, Traps & Filters
• Treatment
• Sediment Pond (Temp. or Perm.)
• Water Truck
5. Stabilize Soils
• Nets & Blankets
• Mulch, Bark & Rock
• Hydroseeding; Grass G N • Plastic Sheeting
• Straw Stockpiles
• Stockpiles
• PAM
6. Protect Slopes G N
• Benching; Track-Walking
• Pipe Slope Drains
• Plastic Sheeting; Anchors
7. Protect Drain Inlets
• Catch Basin Inserts G N
• Gutter; Road
8. Stabilize Channels and Outlets N/A N/A
• Channel Lining
• Check Dam
• Outlet Protection
• Nets and Blankets
9. Control Pollutants N/A N/A
• Chemical Storage Area Covered
• Concrete Handling
10. Control Dewatering N/A N/A
11. Maintain BMPs G N
12. Maintain SWPPP & Site Logbook G N
13. Protect Low-Impact Development (LID BMPs)
• Bioretention Rain Garden Facilities
• Permeable Pavement N/A N/A
0895.06 Page Report No. 1 of 2 144a
Time Off Site Date Day of Week
1:15 PM 3/3/20 Tuesday
Reviewed e3l4'
I RJ Development, LLC I
Comments
Silt fence working as intended
Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
Add check dams and straw wattles as needed to
slow stormwater onsite
Add straw as needed throughout the site, 2"
minimum
CB inserts working as intended
N/A
N/A
N/A
See recommended notes
Available upon request
N/A
Earth Solutions I\IWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWA TER
GENERAL PERMIT -FIELD REPORT
ESNW Rep. AK
Time On Site
1:00 PM
WAR-307963
Project Name 14500 Talbot Rd. S., Renton Weatherly Inn
Monitoring, Records & Recommendations
0895.06 Page 2 of 2
Time Off Site Date
1 :15 PM 3/3/20
Reviewed
I RJ Development, LLC
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? D Yes 0No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Qngoing)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2" straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: 4Q§° F, QverQast
Precipitation since last inspection (approximate): 0.54 ___ inches
Precipitation in the last 24 hours (approximate): 0.12 inches
Was water quality sampling part of this inspection? D Yes lt'.fNo
If "Yes":
• Record results in the table below.
Report No. 144a
Day of Week
Tuesday
Date
(If Completed)
• Characterize the stormwater discharge, e.g., the presence of suspended sediment, "cloudiness", discoloration, or oil sheen, if
present: NIA
• Hanna Turbidity Meter#
Monitoring Location Turbidity pH Notes (NTU)
Is the site in compliance with the SWPPP and the permit requirements? 0Yes □No
lf"No":
• Indicate the tasks necessary to bring the site into compliance in the table above.
• Has the non-compliance been reported to the Department of Ecology?D Yes □No
• Should the SWPPP be modified?D Yes □No �f-"This report is true, accurate, and complete to the best of my knowledge and belief."
Inspector Name: Andrew Kimn CESCL Number: CESCL-EFB183912 Inspection Date: 3/3/20
I
:
Earth Solutions NWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep. AK
Time On Site
12:00 PM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
1:30 PM
Page
1/2
Date
3/4/20
Weather
40s°F, Clear
ClienUOwner Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rino Construction
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
Contact
Mike
Contact
Project No.
Project Manager
'5�'iL
Permit No.
Report No.
145
Day of Week
Wed
the client's request, ESNW rep was onsite to observe or test cut slopes, wall backfill with cement, water line backfill
and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1 :1 (H:V).
Wall Backfill with Cement
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix. Rep observed contractor place
12"-18" lifts for a hoe pack and 6"-8" lifts for a jumping jack during compaction. Rep took compaction tests on
backfill and observed material to be adequate of at least 95% of its maximum dry density that was adjusted based
on calculations with the cement treatment (130.7 lbs./cu. ft.).
Water Line Backfill
Rep observed the prior to arrival that contractor had used a medium sized excavator to excavate a water line
trench (W8'xD12'). Contractor expressed plans to continue working on water line backfill tomorrow, March 5,
2020. Rep will return to observe or test backfill as needed.
ESNW rep will return to observe earthwork activities when requested by client +wf-
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWttc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep. AK
Time On Site
12:00 PM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
1:30 PM
Page 2/2
Date
3/4/20
Weather
40s°F, Clear
ClienUOwner
Report No.
145
Day of Week
Wed
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rina Construction
Contractor #2
Are approved plans/permits on site?
Test Test Location
Number (Wall Backfill)
Contact Mike
Contact
Project No.
Elevation
127 See map for approximate location -10'
128 See map for approximate location -8'
Supplementary Report:
i � l
..
;I ' ,.-\ ,· I, .. I ..,,�
Reference
Compaction
Curve
1
1
·1
Field Supervisor Reviewed
LAC
Project Manager r SS(L
Permit No.
Maximum Fill Test % of
Dry Density Moisture Dry Density Maximum
(pcf) (%) (pcf) Dry Density
130.7 16.9 124.6 95
130.7 18.4 124.1 95
-7
..
[ 127,128 I .,_ . __ j
Project Name
Weatherly Inn
Earth Solutions I\IWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
Job Location
ESNWRep.AK
Time On Site
12:00 Pm
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
1:15 PM
Page
1/1
Date
3/5/20
Weather
40s°F, Clear
ClienUOwner4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Report No.
146
Day of Week
Thursday
Contractor #1
Rina Construction ContactMike Field SupervisorLAC Reviewe�-,, /
41\
Contractor #2 Contact Project Manager-�cl--
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
the client's request, ESNW rep was onsite to observe or test cut slopes, wall backfill with cement, water line backfill
and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1: 1 (H:V).
Wall Backfill with Cement
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix. Rep observed contractor place
12"-18" lifts for a hoe pack and 6"-8" lifts for a jumping jack during compaction. Rep will return to observe or test
backfill as needed.
Water Line Backfill
Rep observed the prior to arrival that contractor had used a medium sized excavator to excavate a water line
trench (W8'xD12'). Contractor expressed plans to continue working on water line backfill tomorrow, March 6,
2020. Rep will return to observe or test backfill as needed.
ESNW rep will return to observe earthwork activities when requested by client +wf-
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWuc
15365 NE 901h Street, Suite 100
Redmond, WA 98052
Main (425) 449-47041 Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
ESNWRep. AK
Time On Site
2:15Pm
Project No.
0895.06
Time Off Site
3:30 PM
Page Report No.
1/1 147
Date Day of Week
3/6/20 Friday
Weather Travel Time
1.25 Hr. RT 40s°F, Overcast
Project Name
Weatherly Inn
Contractor #1
Rino Construction
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
Job Location
4500 Talbot Rd. S., Renton, WA
Contact
Mike
Contact
Project No.
Client/Owner
RJ Development, LLC
Field Supervisor
LAC
Project Manager
$5fL
Permit No.
the client's request, ESNW rep was onsite to observe or test cut slopes, wall backfill with cement, water line backfill
and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1 :1 (H:V).
Wall Backfill with Cement
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix. Rep observed contractor place
12"-18" lifts for a hoe pack and 6"-8" lifts for a jumping jack during compaction. Rep will return to observe or test
backfill as needed.
Water Line Backfill
Rep observed the prior to arrival that contractor had used a medium sized excavator to excavate a water line
trench (W8'xO12'). Contractor expressed plans to continue working on water line backfill Monday, March 9, 2020.
Rep will return to observe or test backfill as needed.
ESNW rep will return to observe earthwork activities when requested by client +wf--
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep.AK
Time On Site
1:45PM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
2:45 PM
Page
1/1
Date
3/9/20
Weather
40s°F, Clear
Client/Owner
Report No.
148
Day of Week
Monday
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rino Construction
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
Contact
Mike
Contact
Project No.
Field SupervisorLAC
Project Manager
Ray
Permit No.
Review�')/,,
Reviewed
the client's request, ESNW rep was onsite to observe or test cut slopes, test pH of stormwater, water line backfill
and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1: 1 (H:V).
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In the filled baker tanks rep observed 10.2 NTU in a baker
tank. Rep observed that contractor added dry ice to lower the pH level. Rep observed that pH level was contained
onsite at 6.5 pH.
Water Line Backfill
Rep observed the prior to arrival that contractor had used a medium sized excavator to excavate a water line
trench (W8'xD12'). Contractor expressed plans to continue working on water line backfill Tuesday, March 10,
2020. Rep will return to observe or test backfill as needed.
ESNW rep will return to observe earthwork activities when requested by client �f-
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions I\IWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-47041 Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWATER
GENERAL PERMIT - FIELD REPORT
ESNWRep. AK
Time On Site
1:15PM
WAR-307963
Project Name 14500 Talbot Rd. S., Renton Weatherly Inn
Erosion Control BMPs Overall Needs
(13 Elements) Condition Repair? (Q.ood; fair; foor) (Xes;Jio)
1.Preserve Vegetation; Mark Clearing Limits
• Buffer Zones around Sensitive Areas G N
•Silt Fence
2. Establish Construction Access
• Fabric; Quarry Spalls G N • WheelWash
•Sweeper Truck
3. Control Flow Rates
• Stormwater Vault or Facility G N •Straw Wattles
•Check Dams
4.Install Sediment Controls
• Silt Fence
• Straw Bale Barriers
• Vegetation
• Straw G N
• Sediment Ponds, Traps & Filters
• Treatment
• Sediment Pond (Temp. or Perm.)
• Water Truck
5.Stabilize Soils
• Nets & Blankets
• Mulch, Bark & Rock
• Hydroseeding; Grass G N • Plastic Sheeting
• Straw Stockpiles
• Stockpiles
• PAM
6. Protect Slopes G N
• Benching; Track-Walking
• Pipe Slope Drains
• Plastic Sheeting; Anchors
7. Protect Drain Inlets
• Catch Basin Inserts G N
• Gutter; Road
8. Stabilize Channels and Outlets NIA NIA
• Channel Lining
• Check Dam
• Outlet Protection
• Nets and Blankets
9. Control Pollutants NIA NIA
• Chemical Storage Area Covered
• Concrete Handling
10.Control Dewatering NIA NIA
11. Maintain BMPs G N
12. Maintain SWPPP & Site Logbook G N
13. Protect Low-Impact Development (LID BMPs)
• Bioretention Rain Garden Facilities
• Permeable Pavement NIA NIA
0895.06 Page Report No . 1 of 2 148a
Time Off Site Date Day of Week
1:45 PM 319120 Monday
Revie�
"o\ \,i...,
j RJ Development, LLC
Comments
Silt fence working as intended
Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
Add check dams and straw wattles as needed to
slow stormwater onsite
Add straw as needed throughout the site, 2"
minimum
CB inserts working as intended
NIA
NIA
NIA
See recommended notes
Available upon request
NIA
Earth Solutions NWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-47041 Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWATER
GENERAL PERMIT - FIELD REPORT
ESNWRep. AK
Time On Site
1:15 PM
WAR-307963
Project Name 14500 Talbot Rd. S., Renton Weatherly Inn
Monitoring, Records & Recommendations
0895.06 Page 2 of 2
Time Off Site Date
1:45 PM 3/9/20
Reviewed
I RJ Development, LLC
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? □Yes @No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
a:es; No; Qngoing)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2" straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: 40s° F Clear
Precipitation since last inspection (approximate): 0.84 __ inches
Precipitation in the last 24 hours (approximate): 0.06 inches
Was water quality sampling part of this inspection? □Yes 0No
lf'Yes":
• Record results in the table below.
Report No. 148a
Day of Week
Monday
Date
(If Completed)
•Characterize the stormwater discharge, e.g., the presence of suspended sediment, "cloudiness", discoloration, or oil sheen, if
present: NIA
•Hanna Turbidity Meter#
Monitoring Location Turbidity pH Notes (NTU)
Is the site in compliance with the SWPPP and the permit requirements? 0Yes □No
lf"No":
• Indicate the tasks necessary to bring the site into compliance in the table above.
• Has the non-compliance been reported to the Department of Ecology?□Yes □No
• Should the SWPPP be modified?D Yes □No �f-"This report is true, accurate, and complete to the best of my knowledge and belief."
lnsoector Name: Andrew Kimn CESCL Number. CESCL-EF8183912 Inspection Date: 3/9/20
I
Project Name
Weatherly Inn
Contractor #1 Rino Construction
Earth Solutions I\IWuc
15365 NE 90 th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 J Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep. AK
Time On Site
12:30 PM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
2:00 PM
Page 1/2
Date
3/10/20
Weather
40s°F, Clear
ClienUOwner
4500 Talbot Rd. S., Renton, WA RJ Developme11.Yi.LC
Contact
Mike
Field Supervisor
LAC
Report No.
149
Day of Week
Tuesday
Contractor #2 Contact Project Manager
Ray
Reviewed
Are approved plans/permits on site? Project No. Permit No.
Test Test Location Reference Maximum Fill Test % of
Number (Water Backfill) Elevation Compaction Dry Density Moisture Dry Density Maximum
Curve (pcf) (%) (pcf) Dry Density
129 See map for approximate location -4'1 130.7 22.4 124.6 95
130 See map for approximate location -2'1 130.7 21.6 125.3 96
131 See map for approximate location SG 1 130.7 20.7 124.4 95
Supplementary Report:
the client's request, ESNW rep was onsite to observe or test cut slopes, water line backfill, footing backfill and
earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1: 1 (H:V).
Water Line Backfill
Rep observed the prior to arrival that contractor had used a medium sized excavator to excavate a water line
trench (W8'xD12'). Rep observed contractor use a medium sized excavator to mix and cement treat native brown
silty sand with gravel material. Rep observed contractor treat native material with a 3% cement mix. Rep observed
contractor place 12"-18" lifts and compaction with a hoe pack. Rep took compaction tests on backfill and observed
material to be adequate of at least 95% of its maximum dry density that was adjusted based on calculations with
the cement treatment (130.7 lbs./cu. ft.).
Footing Backfill
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix. Rep observed contractor place 8"-
8" lifts and compaction with a jumping jack. Rep took compaction tests on backfill and observed material to be
adequate of at least 95% of its maximum dry density that was adjusted based on calculations with the cement
treatment (130.7 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client �f--
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWLLc
15365 NE 90th Street, Suite 1 oo
Redmond, WA 98052
Main (425) 449-4704 / Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep. AK
Time On Site
12:30 PM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
2:00 PM
Page 2/2
Date
3/10/20
Weather
40s°F, Clear
Client/Owner
Report No.
149
Day of Week
Tuesday
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rine Construction
Contractor #2
Are approved plans/permits on site?
Contact
Mike
Contact
Project No.
Reference Test Test Location
Number (Footing Backfill) Elevation Compaction
132 See map for approximate location
133 See map for approximate location
134 See map for approximate location
•
• I
--... �-.... ___ .. __ .... 132 133 J
SG
SG
SG
Curve
1
. .. ., ...... ., •
Maximum
Field Supervisor LAC
Project Manager Ray
Permit No.
Fill
Dry Density Moisture
(pcf) (%)
130.7 18.3
130.7 16.8
130.7 18.0
129,130,131
Reviewed
Reviewed
Test % of
Dry Density Maximum
(pcf) Dry Density
124.8 96
125.2 96
124.7 95
Earth Solutions NWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep. AK
Time On Site
12:30 PM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
1:45 PM
Page
1/1
Date
3/11 /20
Weather
40s°F, Clear
Client/Owner
Report No,
150
Day of Week
Wed
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rino Construction
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
ContactMike
Contact
Project No.
Field SupervisorLAC
Project ManagerRay
Permit No.
Review� ""t/i ,;
Reviewed
the client's request, ESNW rep was onsite to observe or test cut slopes, footing backfill, test pH of stormwater and
earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1: 1 (H :V).
Rep observed contractor using a medium sized excavator to place 2" wash rock behind the wall. Rep observed
that contractor had placed miradrain to the top elevation of the cast-in-place wall. Contractor expressed plans to
continue working on wall backfill.
Footing Backfill
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix. Rep observed contractor place 8" -
8" lifts and compaction with a jumping jack. Rep will return to take compaction tests as needed.
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In the filled baker tanks rep observed 2.0 NTU and a pH of
6.5. Rep observed that pH level was contained onsite at 6.5 pH.
ESNW rep will return to observe earthwork activities when requested by client �f-
Andrew Kimn, Senior Technician, 206-430-9183
Project Name
Weatherly Inn
Earth Solutions NWuc
15365 NE 90'" Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep. AK
Time On Site
3:45 PM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
4:00 PM
Page
1/1
Date
3/12/20
Weather
40s°F, Clear
ClienUOwner 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Report No.
151
Day of Week
Thursday
Contractor #1
Rina Construction
Contact Mike Field Supervisor
LAC Reviewe� "'/i .s
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
Contact
Project No.
Project Manager
Ray
Permit No.
the client's request, ESNW rep was onsite to observe or test cut slopes and earthwork activities.
Cut Slopes
Reviewed
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1 :1 (H:V).
Rep observed contractor using a medium sized excavator to place 2" wash rock behind the wall. Rep observed
that contractor had placed miradrain to the top elevation of the cast-in-place wall. Contractor expressed plans to
continue working on wall backfill.
ESNW rep will return to observe earthwork activities when requested by client +wf-
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWLLc
15365 NE 90 th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
DAILY FIELD REPORT
Job Location
ESNWRep. AK
Time On Site
1:30 PM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
3:30 PM
Page
1/2
Date
3/13/20
Weather
40s°F, Clear
ClienUOwner
Report No.
152
Day of Week
Friday
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rina Construction
Contractor #2
Are approved plans/permits on site?
Supplementary Report:
Contact Mike
Contact
Project No.
Field Supervisor
LAC
Project Manager Ray
Permit No.
Reviewc,._. "/i S
Reviewed
the client's request, ESNW rep was onsite to observe or test cut slopes, footing backfill and earthwork activities.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1: 1 (H:V).
Footing Backfill
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix. Rep observed contractor place 8"-
8" lifts and compaction with a jumping jack. Rep took compaction tests on backfill and observed material to be
adequate of at least 95% of its maximum dry density that was adjusted based on calculations with the cement
treatment (130.7 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client �f-
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWuc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
Job Location
ESNWRep. AK
Time On Site
1:30 PM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
3:30 PM
Page
2/2
Date
3/13/20
Weather
40s°F, Clear
ClienUOwner
Report No.
152
Day of Week
Friday
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rina Construction
Contact
Mike
Contractor #2 Contact
Are approved plans/permits on site? Project No.
Test
Number
135
136
137
Test Location
(Footing Backfill) Elevation
See map for approximate location SG
See map for approximate location SG
See map for approximate location SG
..... ---- ■-...... -•r ,,. _.. ·---
►•--- ... ___ _ ... _,,._4' __ ... ..._ ...-- ·
135 136
Reference
Compaction
Curve
1
1
Maximum
Field Supervisor
LAC
Project Manager Ray
Permit No.
Fill
Dry Density Moisture
(pcf)
130.7
130.7
130.7
'I.' ..
(%)
23.3
25.0
22.8
Reviewed
Reviewed
Test % of
Dry Density Maximum
(pcf) Dry Density
125.2 96
125.0 96
124.8 96
_J
Earth Solutions NWu_c
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWATER
GENERAL PERMIT - FIELD REPORT
ESNWRep, AK
Time On Site
11:00 AM
WAR-307963
Project Name 14500 Talbot Rd. S., Renton Weatherly Inn
Erosion Control BMPs Overall Needs
(13 Elements) Condition Repair? (good; fair, .E,oor) C(es;No)
1.Preserve Vegetation; Mark Clearing Limits
• Buffer Zones around Sensitive Areas G N
• Silt Fence
2.Establish Construction Access
• Fabric; Quarry Spalls G N • Wheel Wash
• Sweeper Truck
3. Control Flow Rates
• Stormwater Vault or Facility G N •Straw Wattles
•Check Dams
4. Install Sediment Controls
• Silt Fence
• Straw Bale Barriers
• Vegetation
• Straw G N
• Sediment Ponds, Traps & Filters
• Treatment
• Sediment Pond (Temp. or Perm.)
• Water Truck
5. Stabilize Soils
• Nets & Blankets
• Mulch, Bark & Rock
• Hydroseeding; Grass G N • Plastic Sheeting
• Straw Stockpiles
• Stockpiles
• PAM
6.Protect Slopes G N
• Benching; Track-Walking
• Pipe Slope Drains
• Plastic Sheeting; Anchors
7. Protect Drain Inlets
• Catch Basin Inserts G N
• Gutter; Road
8. Stabilize Channels and Outlets NIA NIA
• Channel Lining
• Check Dam
• Outlet Protection
• Nets and Blankets
9. Control Pollutants NIA NIA
• Chemical Storage Area Covered
• Concrete Handling
10. Control Dewatering NIA NIA
11.Maintain BMPs G N
12.Maintain SWPPP & Site Logbook G N
13. Protect Low-Impact Development (LID BMPs)
• Bioretenlion Rain Garden Facilities
• Permeable Pavement NIA NIA
0895.06 Page Report No. 1 of 2 154a
Time Off Site Date Day of Week
11:30 AM 3116120 Monday
Reviewed
��\ \'2)
I RJ Development, LLC
Comments
Silt fence working as intended
Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
Add check dams and straw wattles as needed to
slow stormwater onsite
Add straw as needed throughout the site, 2"
minimum
CB inserts working as intended
NIA
NIA
NIA
See recommended notes
Available upon request
NIA
Earth Solutions NWLLc
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 I Fax (425) 449-4711
www.esnw.com
CONSTRUCTION STORMWATER
GENERAL PERMIT -FIELD REPORT
ESNWRep. AK
Time On Site
11:00 AM
WAR-307963
Project Name 14500 Talbot Rd. S., Renton Weatherly Inn
Monitoring, Records & Recommendations
0895.06 Page 2 of 2
Time Off Site Date
11:30 AM 3/16/20
Reviewed
I RJ Development, LLC
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? □Yes @No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Qngoing)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2" straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: 40s° F Clear
Precipitation since last inspection (approximate): 0.06 ___ inches
Precipitation in the last 24 hours (approximate): 0.00 inches
Was water quality sampling part of this inspection? □Yes @No
lf'Yes":
• Record results in the table below.
Report No. 154a
Day of Week
Monday
Date
(If Completed)
•Characterize the stormwater discharge, e.g., the presence of suspended sediment, "cloudiness", discoloration, or oil sheen, if
present: N/A
• Hanna Turbidity Meter#
Monitoring Location Turbidity pH Notes (NTU)
Is the site in compliance with the SWPPP and the permit requirements? @Yes □No
lf"No":
•Indicate the tasks necessary to bring the site into compliance in the table above.
•Has the non-compliance been reported to the Department of Ecology? D Yes □No
•Should the SWPPP be modified? D Yes □No
�� "This report is true, accurate, and complete to the best of my knowledge and belief."
Inspector Name: Andrew Kimn CESCL Number: CESCL-EF8183912 Inspection Date: 3/16/20
I
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 157
Time On Site Time Off Site Date Day of Week
11:00 AM 3:30 PM 3/19/20 Thursday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V).
Footing Backfill
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix. Rep observed contractor place
12” lifts and compacted with a jumping jack or a hoe pack when able. Rep took compaction tests on backfill and
observed material to be adequate (at least 95% of its maximum dry density that was adjusted based on calculations
with the cement treatment) (Fig 1) (130.7 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/3
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 157
Time On Site Time Off Site Date Day of Week
11:00 AM 3:30 PM 3/19/20 Thursday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Test
Number
Test Location
(Footing Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
144 See map for approximate location -2 SG 2 125.7 21.5 119.1 95
145 See map for approximate location -2 SG 2 125.7 20.1 119.0 95
146 See map for approximate location -2 SG 2 125.7 19.5 119.6 95
147 See map for approximate location -2 SG 2 125.7 19.9 121.2 96
148 See map for approximate location SG 2 125.7 20.6 120.6 96
149 See map for approximate location SG 2 125.7 18.7 119.2 95
150 See map for approximate location SG 2 125.7 19.1 118.7 95
151 See map for approximate location SG 2 125.7 20.2 122.3 97
2/3
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 157
Time On Site Time Off Site Date Day of Week
11:00 AM 3:30 PM 3/19/20 Thursday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Fig. 1 Approximate location of compaction tests on footing backfill CTB material
146
145
144
147 14
149
150
151
3/3
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 158
Time On Site Time Off Site Date Day of Week
11:00 AM 3:00 PM 3/20/20 Friday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V).
Footing Backfill
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix (Fig 1). Rep observed contractor
place 12” lifts and compacted with a jumping jack or a hoe pack when able. Rep took compaction tests on backfill
and observed material to be adequate (at least 95% of its maximum dry density that was adjusted based on
calculations with the cement treatment) (130.7 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Fig. 1 Contractor placing 5/8’’ crushed rock and geotextile along wall before backfilling with CTB
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 158
Time On Site Time Off Site Date Day of Week
11:00 AM 3:00 PM 3/20/20 Friday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Test
Number
Test Location
(Footing Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
152 See map for approximate location -4 SG 1 130.7 18.9 125.9 96
153 See map for approximate location -4 SG 1 130.7 21.1 125.4 96
154 See map for approximate location -2 SG 1 130.7 17.5 126.2 96
155 See map for approximate location -2 SG 1 130.7 19.3 128.5 98
156 See map for approximate location SG 1 130.7 20.2 127.0 97
157 See map for approximate location SG 1 130.7 19.7 124.8 95
Fig. 2 Approximate location of compaction tests on footing backfill CTB material
2/2
153
154
155
156
157
152
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 159
Time On Site Time Off Site Date Day of Week
11:00 AM 3:00 PM 3/23/20 Monday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V).
Footing Backfill
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix (Fig 1). Rep observed contractor
place 12” lifts and compacted with a jumping jack or a hoe pack when able. Rep took compaction tests on backfill
and observed material to be adequate (at least 95% of its maximum dry density that was adjusted based on
calculations with the cement treatment) (130.7 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/3
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 159
Time On Site Time Off Site Date Day of Week
11:00 AM 3:00 PM 3/23/20 Monday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Test
Number
Test Location
(Footing Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
158 See map for approximate location -10 SG 1 130.7 20.4 126.0 96
159 See map for approximate location -10 SG 1 130.7 19.7 129.1 98
160 See map for approximate location -10 SG 1 130.7 16.9 130.0 98
161 See map for approximate location -8 SG 1 130.7 18.3 125.1 95
162 See map for approximate location -8 SG 1 130.7 17.8 126.8 97
163 See map for approximate location -8 SG 1 130.7 19.5 124.9 95
164 See map for approximate location -6 SG 1 130.7 20.0 129.2 98
165 See map for approximate location -6 SG 1 130.7 21.6 128.7 98
166 See map for approximate location -6 SG 1 130.7 21.4 126.0 96
167 See map for approximate location -4 SG 1 130.7 15.7 127.8 97
168 See map for approximate location -4 SG 1 130.7 19.2 127.3 97
169 See map for approximate location -4 SG 1 130.7 18.9 124.6 95
170 See map for approximate location -2 SG 1 130.7 17.8 126.9 97
171 See map for approximate location -2 SG 1 130.7 20.2 129.0 98
172 See map for approximate location -2 SG 1 130.7 21.2 128.2 98
2/3
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 159
Time On Site Time Off Site Date Day of Week
11:00 AM 3:00 PM 3/23/20 Monday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill CTB material
Area of compaction tests 158-172
3/3
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 160
Time On Site Time Off Site Date Day of Week
11:00 AM 12:30 PM 3/24/20 Tuesday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V).
Footing Backfill
Rep observed contractor use a medium sized excavator to mix and cement treat native brown silty sand with gravel
material. Rep observed contractor treat native material with a 3% cement mix (Fig 1). Rep observed contractor
place 12” lifts and compacted with a jumping jack or a hoe pack when able. Rep took compaction tests on backfill
and observed material to be adequate (at least 95% of its maximum dry density that was adjusted based on
calculations with the cement treatment) (133.1 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/3
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 160
Time On Site Time Off Site Date Day of Week
11:00 AM 12:30 PM 3/24/20 Tuesday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Test
Number
Test Location
(Footing Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
173 See map for approximate location -9 SG 2 133.1 20.3 130.1 97
174 See map for approximate location -9SG 2 133.1 19.6 129.3 97
175 See map for approximate location -9 SG 2 133.1 17.8 128.9 96
176 See map for approximate location -7 SG 2 133.1 20.7 126.8 95
177 See map for approximate location -7 SG 2 133.1 19.2 127.1 95
178 See map for approximate location -7 SG 2 133.1 19.3 126.2 95
179 See map for approximate location -5 SG 2 133.1 20.1 131.0 98
180 See map for approximate location -5 SG 2 133.1 19.6 128.4 96
181 See map for approximate location -3 SG 2 133.1 19.0 127.7 95
2/3
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 160
Time On Site Time Off Site Date Day of Week
11:00 AM 12:30 PM 3/24/20 Tuesday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill CTB material
173
174 175 176
177
178
179 180
181
3/3
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 161
Time On Site Time Off Site Date Day of Week
11:00 AM 12:00 PM 3/24/20 Wednesday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V).
Footing Backfill
No footing backfill or compaction was in progress onsite.
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 162
Time On Site Time Off Site Date Day of Week
3:30 PM 5:00 PM 4/21/20 Tuesday
Travel Time Weather
1.00Hr. RT 50s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes, test pH of stormwater and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the north slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation
Material Export
While onsite rep observed material being exported offsite.
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In the filled baker tank rep observed <25NTU. Rep observed
that contractor added dry ice to lower the pH level to 6.5, suitable for sewer discharge. Rep observed that pH
level was contained onsite.
Footing Backfill
ESNW rep observed footing excavation. Rep. used a ½” steel T-probe to probe locations along the footing
subgrade. ESNW rep. observed footing subgrade to be dense and composed of suitable material for footing
construction.
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn Field Technician 206-430-9183
1/1
Earth Solutions NWLLC
Field Rep. Project No. Page of Report No.
JTL 0895.06 1/1 163
1805 136th Place NE,
Suite 201
Bellevue, WA 98005
(425) 449-4704
FAX:
(425) 449-4711
TOLL FREE:
(866) 366-8710
Time On Site Time Off Site Date Day of Week
8:30 AM 1:45 PM 4/27/20 Monday
DAILY FIELD REPORT Travel Time Weather
1.25 Hr. RT 60soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2
RM Construction NW, Inc
Contact Project Manager
SSR
Reviewed
Are approved Plans/Permits onsite YES NO Project No. Permit No.
At the client’s request, ESNW rep was onsite to observe rockery construction and earthwork activities. The focus of
the work is related to completing the rockeries along the south side of the project.
Rockeries
The temporary slope (covered area in photo below) has been covered and otherwise protected from weather related
instability and has remained stable during the temporary period, as observed by ESNW representative. While onsite,
rep used a ½” steel t-probe and observed the keyway for the lower tier rockery located at the southeast quadrant of
the site. Rep observed the keyway to be very dense, firm, unyielding, and suitable for support of the proposed rockery.
Rep observed contractor place courses of rocks. Rep observed contractor place a 4” perforated drain pipe behind the
first course of the rockery, embed the pipe in an 18” lift of 1”-2” wash rock, geotextile, then backfill over the geotextile
with 2”-4” quarry spalls. (See Image)
ESNW rep will return to observe earthwork activities when requested by client.
Jackson Lundgren, Field Technician, (206) 468-0991
Earth Solutions NWLLC
Field Rep. Project No. Page of Report No.
JTL 0895.06 1/1 164
1805 136th Place NE,
Suite 201
Bellevue, WA 98005
(425)449-4704
FAX:
(425)449-4711
TOLL FREE:
(866)366-8710
Time On Site Time Off Site Date Day of Week
8:30 AM 1:45 PM 4/28/20 Tuesday
DAILY FIELD REPORT Travel Time Weather
1.25 Hr. RT 60soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2
RM Construction NW, Inc
Contact Project Manager
SSR
Reviewed
Are approved Plans/Permits onsite YES NO Project No. Permit No.
At the client’s request, ESNW rep was onsite to observe rockery construction and earthwork activities. The focus of
the work is related to completing the rockeries along the south side of the project.
Rockeries
While onsite, rep used a ½” steel t-probe and observed the keyway for the rockery located at the southeast quadrant
of the site. Rep observed the keyway to be very dense, firm, unyielding, and suitable for support of the proposed
rockery. Rep observed contractor place courses of rocks. Rep observed contractor place a 4” perforated drain pipe
behind the first course of the rockery, embed the pipe in an 18” lift of 1”-2” wash rock, geotextile, then backfill over the
geotextile with 2”-4” quarry spalls. (See Image)
ESNW rep will return to observe earthwork activities when requested by client.
Jackson Lundgren, Field Technician, (206) 468-0991
Earth Solutions NWLLC
Field Rep. Project No. Page of Report No.
JTL 0895.06 1/1 165
1805 136th Place NE,
Suite 201
Bellevue, WA 98005
(425)449-4704
FAX:
(425)449-4711
TOLL FREE:
(866)366-8710
Time On Site Time Off Site Date Day of Week
10:30 AM 2:45 PM 4/29/20 Wednesday
DAILY FIELD REPORT Travel Time Weather
1.25 Hr. RT 60soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2
RM Construction NW, Inc
Contact Project Manager
SSR
Reviewed
Are approved Plans/Permits onsite YES NO Project No. Permit No.
At the client’s request, ESNW rep was onsite to observe rockery construction and earthwork activities. The focus of
the work is related to completing the rockeries along the south side of the project.
Rockeries
While onsite, rep used a ½” steel t-probe and observed the keyway for the rockery located at the southeast quadrant
of the site. Rep observed the keyway to be very dense, firm, unyielding, and suitable for support of the proposed
rockery. Rep observed contractor place upper course of rocks, then backfill with 2”-4” quarry spalls. Observation of
the area above the rockery found no tension cracks, slumping or other obvious signs of instability of native material.
ESNW rep recommended 2’ over-excavation for lower rockery keyway located at southwest quadrant of site. (See
Image)
ESNW rep will return to observe earthwork activities when requested by client.
Jackson Lundgren, Field Technician, (206) 468-0991
Earth Solutions NWLLC
Field Rep. Project No. Page of Report No.
JTL 0895.06 1/1 166
1805 136th Place NE,
Suite 201
Bellevue, WA 98005
(425)449-4704
FAX:
(425)449-4711
TOLL FREE:
(866)366-8710
Time On Site Time Off Site Date Day of Week
10:00 AM 2:30 PM 4/30/20 Thursday
DAILY FIELD REPORT Travel Time Weather
1.25 Hr. RT 60soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2
RM Construction NW, Inc
Contact Project Manager
SSR
Reviewed
Are approved Plans/Permits onsite YES NO Project No. Permit No.
At the client’s request, ESNW rep was onsite to observe rockery construction, earthwork activities, and test pH of
stormwater. The focus of the work is related to completing the rockeries along the south side of the project.
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In the filled baker tank rep observed <25NTU. Rep observed
that contractor added dry ice to lower the pH level to 6.5, suitable for sewer discharge. Rep observed that pH level
was contained onsite.
Rockeries
While onsite, rep used a ½” steel t-probe and observed the keyway for the rockery located at the southwest quadrant
of the site. Rep observed the keyway to be very dense, firm, unyielding, and suitable for support of the proposed
rockery. Rep observed contractor place courses of rocks. Rep observed contractor place a 4” perforated drain pipe
behind the first course of the rockery, embed the pipe in an 18” lift of 1”-2” wash rock, geotextile, then backfill over
the geotextile with 2”-4” quarry spalls. Native material above the rockery was found to be in a stable condition. ESNW
rep recommended 2’ over-excavation for rockery located at southwest quadrant of site. (See Image)
ESNW rep will return to observe earthwork activities when requested by client.
Jackson Lundgren, Field Technician, (206) 468-0991
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
1 of 2
Report No.
166a
Time On Site
11:00 AM
Time Off Site
11:30 AM
Date
4/30/20
Day of Week
Thursday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1.Preserve Vegetation; Mark Clearing Limits
•Buffer Zones around Sensitive Areas
•Silt Fence
G N Silt fence working as intended
2.Establish Construction Access
•Fabric; Quarry Spalls
•Wheel Wash
•Sweeper Truck
G N Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
3.Control Flow Rates
•Stormwater Vault or Facility
•Straw Wattles
•Check Dams
G N Add check dams and straw wattles as needed to
slow stormwater onsite
4.Install Sediment Controls
•Silt Fence
•Straw Bale Barriers
•Vegetation
•Straw
•Sediment Ponds, Traps & Filters
•Treatment
•Sediment Pond (Temp. or Perm.)
•Water Truck
G N Add straw as needed throughout the site, 2”
minimum
5. Stabilize Soils
•Nets & Blankets
•Mulch, Bark & Rock
•Hydroseeding; Grass
•Plastic Sheeting
•Straw Stockpiles
•Stockpiles
•PAM
G N
6.Protect Slopes
•Benching; Track-Walking
•Pipe Slope Drains
•Plastic Sheeting; Anchors
G N
7.Protect Drain Inlets
•Catch Basin Inserts
•Gutter; Road
G N CB inserts working as intended
8.Stabilize Channels and Outlets
•Channel Lining
•Check Dam
•Outlet Protection
•Nets and Blankets
N/A N/A N/A
9. Control Pollutants
•Chemical Storage Area Covered
•Concrete Handling
N/A N/A N/A
10. Control Dewatering N/A N/A N/A
11. Maintain BMPs G N See recommended notes
12.Maintain SWPPP & Site Logbook G N Available upon request
13. Protect Low-Impact Development (LID BMPs)
•Bioretention Rain Garden Facilities
•Permeable Pavement N/A N/A N/A
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
2 of 2
Report No.
166a
Time On Site
11:00 AM
Time Off Site
11:30 AM
Date
4/30/20
Day of Week
Thursday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Monitoring, Records & Recommendations
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? Yes No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Ongoing)
Date
(If Completed)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2” straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: _50sO F, Clear____________________
Precipitation since last inspection (approximate): 0.15______ inches
Precipitation in the last 24 hours (approximate): _0.00______ inches
Was water quality sampling part of this inspection? Yes No
If “Yes”:
•Record results in the table below.
•Characterize the stormwater discharge, e.g., the presence of suspended sediment, “cloudiness”, discoloration, or oil sheen, if
present: ____N/A________________________________________________________________________________________
•Hanna Turbidity Meter # ____________________
Monitoring Location Turbidity
(NTU) pH Notes
Baker Tank 8.5 7.5
Is the site in compliance with the SWPPP and the permit requirements? Yes No
If “No”:
•Indicate the tasks necessary to bring the site into compliance in the table above.
•Has the non-compliance been reported to the Department of Ecology?Yes No
•Should the SWPPP be modified?Yes No
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Inspector Name: Jackson Lundgren CESCL Number: CESCL-EF8183892 Inspection Date: 4/30/20
Earth Solutions NWttc
1805 1361h Place NE,
Suite 201
Bellevue, WA 98005
(425)449-4704
FAX:
(425) 449-4711
TOLL FREE :
(866)366-8710
DAILY FIELD REPORT
Job Location
Field Rep.
JTL
Time On Site
10:00AM
Travel Time
1.25 Hr. RT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA
Contractor #1
Rina Construction
Contractor #2
RM Construction NW, Inc
Are approved Plans/Permits onsite
Supplementary Report:
Contact
Mike
Contact
□YES □ NO Project No.
Project No.
0895.06
Time Off Site
12:30 PM
ClienUOwner
Page of
1 /1
Date
5/4/20
Weather
60s°F, Clear
Report No.
167
Day of Week
Monday
RJ Development, LLC
Field Supervisor
LAC
Reviewed � ¾Cl\
Project Manager Reviewed
SSR
Permit No.
At the client's request, ESNW rep was onsite to observe earthwork activities, cut slopes, and test footing subgrade.
Footing Backfill
ESNW rep observed concrete pouring for a cast-in-place footing wall. Rep. used a ½" steel T-probe to probe
locations along the footing subgrade. ESNW rep. observed footing subgrade to be dense and composed of suitable
material for footing construction.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0. 75: 1 (H:V) slope. Although over-steepened, slopes are stable in current configuration and
stable to work within. The contractor is responsible for providing all safety measures in accordance with state and
federal regulation
ESNW rep will return to observe earthwork activities when requested by client.
Fig 1. Concrete pouring at footing wall
Jackson Lund ren, Field Technician, 206 468-0991
Earth Solutions I\IWLLc
1805 136th Place NE,
Suite 201
Bellevue, WA 98005
(425)449-4704
FAX:
(425)449-4711
TOLL FREE:
(866)366-8710
DAILY FIELD REPORT
Job Location
Field Rep.
JTL
Time On Site
09:45 AM
Travel Time
1.25 Hr. RT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA
Contractor #1
Rina Construction
Contractor #2
RM Construction NW, Inc
Are approved Plans/Permits onsite
Supplementary Report:
Contact
Mike
Contact
□YES □ NO Project No.
Project No.
0895.06
Time Off Site
10:45 AM
ClienVOwner
Page of
1/1
Date
5/5/20
Weather
60s°F, Clear
RJ Development, LLC
Field Supervisor
LAC
Project Manager Reviewed
SSR
Permit No.
Report No.
168
Day of Week
Tuesday
At the client's request, ESNW rep was onsite to observe earthwork activities, cut slopes, and test footing subgrade.
Footing Excavation
ESNW rep observed footing excavation for an 8'x8' footing. Rep. used a½" steel T-probe to probe locations along
the footing subgrade. ESNW rep. observed footing subgrade to be dense, gray-blue silty clay and composed of
suitable material for footing construction.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0. 75: 1 (H:V) slope. Although over-steepened, slopes are stable in current configuration and
stable to work within. The contractor is responsible for providing all safety measures in accordance with state and
federal regu lation
ESNW rep will return to observe earthwork activities when requested by client.
,i. __ ..,,_,.,,r...,'61-.:3i.iiiii,,,i,1Molaiill_,.lliM.._,... Fig 1. 8' x 8' footing with trench box
Jackson Lund ren, Field Technician, 206 468-0991
Earth Solutions NWLLc
1805 136th Place NE, Suite 201 Bellevue, WA 98005 (425)449-4704
FAX: (425)449-4711TOLL FREE: (866)366-8710
DAILY FIELD REPORT
Job Location
Field Rep.
JTL
Time On Site
12:30 PM
Travel Time
1.25 Hr. RT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA
Contractor #1
Rina Construction
Contractor #2
RM Construction NW, Inc
Are approved Plans/Permits onsite
Supplementary Report:
Contact
Mike
Contact
□YES □ NO Project No.
Project No.
0895.06
Time Off Site
1:45 PM
ClienUOwner
Page of
1/1
Date
5/6/20
Weather
60s°F, Rain
RJ Development, LLC
Field Supervisor
LAC
Project Manager Reviewed
SSR
Permit No.
Report No.
169
Day of Week
Wednesday
At the client's request, ESNW rep was onsite to observe earthwork activities, cut slopes, and test footing subgrade.
Footing Backfill
ESNW rep observed footing backfill. Rep. used a½" steel T-probe to probe locations along the footing subgrade.
ESNW rep. observed footing subgrade to be dense and composed of suitable material for footing construction.
Footings were backfilled with sandy silt native material and compacted in 1' lifts with a jumping jack.
Footing Excavation
ESNW rep observed footing excavation along the east side of the site. Rep. used a ½" steel T-probe to probe
locations along the footing subgrade. ESNW rep. observed footing subgrade to be located in silty sand, and dense
and composed of suitable material for footing construction.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration and
stable to work within. The contractor is responsible for providing all safety measures in accordance with state and
federal regulation
ESNW rep will return to observe earthwork activities when re
Fig 1. Footing backfill with native material
Jackson Lund ren, Field Technician, 206 468-0991
Earth Solutions I\IWLLc
1805 136th Place NE,
Suite 201
Bellevue, WA 98005
(425) 449-4704
FAX:
(425) 449-4711
TOLL FREE:
(866) 366-8710
DAILY FIELD REPORT
Job Location
Field Rep.
JTL
Time On Site
11:00 AM
Travel Time
1.25 Hr. RT
Project No.
0895.06
Time Off Site
11:45 AM
Client/Owner
Page of
1 /1
Date
5/7/20
Weather
60s°F, Clear
Report No.
170
Day of Week
Thursday
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1
Rina Construction
Contractor #2
RM Construction NW, Inc
Are approved Plans/Permits onsite
Supplementary Report:
Contact
Mike
Contact
□YES □ NO Project No.
Field Supervisor
LAC
Reviewe� �'\
Project Manager Reviewed
SSR
Permit No.
At the client's request, ESNW rep was onsite to observe earthwork activities, test pH of stormwater and footing
subgrade.
Footing Backfill
ESNW rep observed footing backfill. Rep . used a½" steel T-probe to probe locations along the footing subgrade.
ESNW rep. observed footing subgrade to be dense and composed of suitable material for footing construction.
Footings with 4" drain pipe in crushed rock and filter fabric were backfilled with sandy silty native material and
compacted in 1' lifts with a jumping jack.
Footing Excavation
ESNW rep observed footing excavation along the east side of the site. Rep. used a½" steel T-probe to probe
locations along the footing subgrade. ESNW rep. observed footing subgrade to be located in silty sand, and dense
and composed of suitable material for footing construction.
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. In the filled baker tank rep observed <25NTU. Rep observed
that contractor added dry ice to lower the pH level to 6.5, suitable for sewer discharge. Rep observed that pH level
was contained onsite.
will return to observe earthwork activities when requested by client.
Earth Solutions NWLLC
Field Rep. Project No. Page of Report No.
JTL 0895.06 1/1 171
1805 136th Place NE,
Suite 201
Bellevue, WA 98005
(425)449-4704
FAX:
(425)449-4711
TOLL FREE:
(866)366-8710
Time On Site Time Off Site Date Day of Week
11:00 AM 11:45 AM 5/8/20 Friday
DAILY FIELD REPORT Travel Time Weather
1.25 Hr. RT 60soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2
RM Construction NW, Inc
Contact Project Manager
SSR
Reviewed
Are approved Plans/Permits onsite YES NO Project No. Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe earthwork activities and test footing subgrade.
Footing Backfill
ESNW rep observed footing backfill. Rep. used a ½” steel T-probe to probe locations along the footing subgrade.
ESNW rep. observed footing subgrade to be dense and composed of suitable material for footing construction.
Footings were backfilled with sandy silty native material and compacted in 1’ lifts with a jumping jack.
ESNW rep will return to observe earthwork activities when requested by client.
Fig 1. Preparing the subgrade for slab pouring and backfilling footiongs
Jackson Lundgren, Field Technician, (206) 468-0991
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
1 of 2
Report No.
171a
Time On Site
10:00 AM
Time Off Site
10:30 AM
Date
5/8/20
Day of Week
Friday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Erosion Control BMPs
(13 Elements)
Overall
Condition
(Good; Fair; Poor)
Needs
Repair?
(Yes; No)
Comments
1.Preserve Vegetation; Mark Clearing Limits
•Buffer Zones around Sensitive Areas
•Silt Fence
G N Silt fence working as intended
2.Establish Construction Access
•Fabric; Quarry Spalls
•Wheel Wash
•Sweeper Truck
G N Sweep roadway when soil is seen on surface,
replenish quarry spalls as needed
3.Control Flow Rates
•Stormwater Vault or Facility
•Straw Wattles
•Check Dams
G N Add check dams and straw wattles as needed to
slow stormwater onsite
4.Install Sediment Controls
•Silt Fence
•Straw Bale Barriers
•Vegetation
•Straw
•Sediment Ponds, Traps & Filters
•Treatment
•Sediment Pond (Temp. or Perm.)
•Water Truck
G N Add straw as needed throughout the site, 2”
minimum
5. Stabilize Soils
•Nets & Blankets
•Mulch, Bark & Rock
•Hydroseeding; Grass
•Plastic Sheeting
•Straw Stockpiles
•Stockpiles
•PAM
G N
6.Protect Slopes
•Benching; Track-Walking
•Pipe Slope Drains
•Plastic Sheeting; Anchors
G N
7.Protect Drain Inlets
•Catch Basin Inserts
•Gutter; Road
G N CB inserts working as intended
8.Stabilize Channels and Outlets
•Channel Lining
•Check Dam
•Outlet Protection
•Nets and Blankets
N/A N/A N/A
9. Control Pollutants
•Chemical Storage Area Covered
•Concrete Handling
N/A N/A N/A
10. Control Dewatering N/A N/A N/A
11. Maintain BMPs G N See recommended notes
12.Maintain SWPPP & Site Logbook G N Available upon request
13. Protect Low-Impact Development (LID BMPs)
•Bioretention Rain Garden Facilities
•Permeable Pavement N/A N/A N/A
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com
ESNW Rep.
JTL 0895.06 Page
2 of 2
Report No.
171a
Time On Site
10:00 AM
Time Off Site
10:30 AM
Date
5/8/20
Day of Week
Friday
WAR-307963 Reviewed
CONSTRUCTION STORMWATER
GENERAL PERMIT – FIELD REPORT
Project Name
Weatherly Inn 4500 Talbot Rd. S., Renton RJ Development, LLC
Monitoring, Records & Recommendations
Will existing BMPs need to be modified or removed, or will other BMPs need to be installed? Yes No
List the completed, not-yet-completed, or ongoing action items in the table below:
Actions Items Completed?
(Yes; No; Ongoing)
Date
(If Completed)
Sweep site entrance when soil is seen on roadway Ongoing
Add 2” straw throughout the site over exposed soils as needed Ongoing
Replenish quarry spalls at the main entrance to the site as needed Ongoing
Replace plastic sheeting on exposed slopes as needed Ongoing
Current Weather: _60sO F, Clear____________________
Precipitation since last inspection (approximate): 0.28______ inches
Precipitation in the last 24 hours (approximate): _0.00______ inches
Was water quality sampling part of this inspection? Yes No
If “Yes”:
•Record results in the table below.
•Characterize the stormwater discharge, e.g., the presence of suspended sediment, “cloudiness”, discoloration, or oil sheen, if
present: ____N/A________________________________________________________________________________________
•Hanna Turbidity Meter # ____________________
Monitoring Location Turbidity
(NTU) pH Notes
22 7.0
Is the site in compliance with the SWPPP and the permit requirements? Yes No
If “No”:
•Indicate the tasks necessary to bring the site into compliance in the table above.
•Has the non-compliance been reported to the Department of Ecology?Yes No
•Should the SWPPP be modified?Yes No
“This report is true, accurate, and complete to the best of my knowledge and belief.”
Inspector Name: Jackson Lundgren CESCL Number: CESCL-EF8183892 Inspection Date: 5/8/20
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 172
Time On Site Time Off Site Date Day of Week
11:00 AM 12:30 PM 5/11/20 Monday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the north slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation.
Footing Backfill
Rep observed contractor use a medium sized excavator to backfill with native brown silty sand with gravel material.
Rep observed contractor place 12” lifts of native soil and compact with a jumping jack (or a hoe pack when able).
Pea gravel was placed on top of the compacted footing backfill and a vapor barrier was installed over the pea
gravel in preparation for slab pouring. Rep took compaction tests on backfill and observed material to be suitably
dense for slab support (at least 95% of its maximum dry density of 133.1 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Fig. 1 Excavator placing pea gravel on top of compacted footing backfill
1/2
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 172
Time On Site Time Off Site Date Day of Week
11:00 AM 12:30 PM 5/11/20 Monday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Test
Number
Test Location
(Footing Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
182 See map for approximate location -1 SG 5 133.1 9.89 127.2 95
183 See map for approximate location -1 SG 5 133.1 10.11 128.2 96
184 See map for approximate location -1 SG 5 133.1 11.10 125.9 95
185 See map for approximate location -1 SG 5 133.1 10.25 126.1 95
Fig. 2 Approximate location of compaction tests on footing backfill
2/2
183 182 184 185
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 173
Time On Site Time Off Site Date Day of Week
12:30 PM 1:30 PM 5/12/20 Tuesday
Travel Time Weather
1.00Hr. RT 40s, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the north slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall.
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Fig. 1 Pea gravel course in footing trench
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 174
Time On Site Time Off Site Date Day of Week
12:30 PM 1:00 PM 5/13/20 Wednesday
Travel Time Weather
1.00Hr. RT 50s, Rain
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall.
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
Fig. 1 Footing trenches for cast-in-place walls
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 175
Time On Site Time Off Site Date Day of Week
12:30 PM 1:30 PM 5/14/20 Thursday
Travel Time Weather
1.00Hr. RT 50s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall.
Water Main Tie-In
Rep observed City of Renton officials and Rino Construction representatives excavating the area around the water
main to tie-in site utilities. Water main to be backfilled with 5/8’’ minus crushed rock and covered with a steel plate
until backfill.
ESNW rep will return to observe earthwork activities when requested by client
Fig. 1 Footing trenches for cast-in-place walls
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 176
Time On Site Time Off Site Date Day of Week
12:30 PM 1:30 PM 5/18/20 Monday
Travel Time Weather
1.00Hr. RT 60s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall. Rep observed footings had been poured in part of the footing trenches.
Temporary Stormwater Pond
Rep observed temporary stormwater pond immediately South of the site entrance had been filled in with native
material from the main stockpile for export in order to clear space for footing excavation along the East margin of
the site. Contractor relayed that Temporary stormwater pond will be excavated and filled in with 1’ lifts of
compacted native material at a later date after the bulk of the stockpiled material has been exported.
ESNW rep will return to observe earthwork activities when requested by client
Fig. 1 Footing trenches for cast-in-place walls with concrete poured
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 177
Time On Site Time Off Site Date Day of Week
11:45 AM 12:15 PM 5/19/20 Tuesday
Travel Time Weather
1.00Hr. RT 60s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe slope stability and test stormwater pH
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
Test pH of Stormwater
Rep took pH tests to determine the pH of stormwater. The baker tank was not filled and did not require sewer
discharge. Rep observed that pH level was contained onsite.
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 178
Time On Site Time Off Site Date Day of Week
12:00 PM 12:30 PM 5/20/20 Wednesday
Travel Time Weather
1.00Hr. RT 60s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade and slope stability.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall. Rep observed footings had been poured in part of the footing trenches.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 179
Time On Site Time Off Site Date Day of Week
1:00 PM 1:30 PM 5/21/20 Thursday
Travel Time Weather
1.00Hr. RT 60s, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
SSR
Are approved plans/permits on site?Project No.Permit No.
Fig. 2 Approximate location of compaction tests on footing backfill
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe footing subgrade and slope stability.
Footing Excavation
Rep observed contractor use a medium sized excavator to excavate native brown silty sand with gravel material.
The trenches for cast-in-place walls measured approximately 2.5’ x 4’ with a 6’’ lift of pea gravel at the bottom.
While onsite, rep used a ½” steel t-probe and observed the footing subgrade located along the eastern margin of
the site. Rep observed the footing subgrade to be very dense, firm, unyielding, and suitable for support of the
proposed cast-in-place wall. Rep observed footings had been poured in part of the footing trenches. Contractor
relayed that backfill of the 8’x8’x12’ footing with 3’ of crushed rock and native material to occur 5/22/20.
Cut Slopes
While onsite, rep observed slopes of the cut slopes to be near vertical. Rep observed that the north slopes of the
excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes are stable in current configuration
and stable to work within. The contractor is responsible for providing all safety measures in accordance with state
and federal regulation
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991
1/1