HomeMy WebLinkAboutCO 1CAG-20-006, CO #1-20 CITY OF RENTON Community Services Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CAG-20-006 5/29/2020 CONTRACTOR: Emtech, LLC. CHANGE ORDER: #1 SUMMARY OF PROPOSED CHANGE: Reason/Justification: This Change Order addresses the modifications required for the Contractor to gain access to the bridge structure from the east. The change in access will involve placing timber bunking to distribute the load for equipment moving over the timber trestle and steel bridge. DESCRIPTION: Item Qty. Description Unit Price Amount No. w/ WSST 1 1 Access Modification - Timber Bunking$ 15,389.30 $ 16,928.23 Total this Change Order: 1 $ 16,928.23 ORIGINAL CONTRACT AMOUNT (W/ WSST) CURRENT CONTRACT AMOUNT NET CHANGE THIS ORDER (W/ WSST) REVISED CONTRACT TOTAL AFTER CHANGE $ 367,400.00 $ 367,400.00 $ 16,928.23 $ 384,328.23 Additional Calendar Days: (0) No Extension of Time. Completion Date is December 30, 2020. The payment specified and agreed to in this change order includes every claim by the contractor for any extra payment with respect to the work described in this change order. The work covered by this change order must be performed under the same terms and conditions as that included in the original agreement. All of the other terms of the original agreement remain in effect. SIGNATURES: Contractor: ,o u��,.,o�,,,,Pon Date: 6/2/2020 Project Manager: ? �' " Date 6/2/2020 Date: (11 2-f 2Z (name of 0 emtech To: Betsv Severtsen Parks Planning and Natural Resources 1055 S. Grady Way Renton, WA 98057 Re: Providing bunking to distrubute load for equipment transport Scope of Changes: Change Order Emtech, LLC 1133 Kresky Ave. STE 106 Centralia, WA 98531 (360) 748-4891 Date: 5/28/20 CO No. 001 Rev#: 1 RFI No. Providing labor and materials to put bunking down to distribute load for equipment moving over the timber trestle and steel bridge. See attached drawings, no. G-1 and G-6, from WSP for reference. Total price per attached breakdown: $15,389.30 State and local sales tax: included X not included Extension of time: 0 We have proceeded with the work X Work will not proceed without formal authorization This price is good for 30 days from the above date, after which this request is subject to revision. Sincerely, B4!! . aY F1T DA1 POT) Ben Booher, General Manager Emtech, LLC. CHANGE ORDER REQUEST SUMMARY Cedar River Bridge Repairs PCO: DESCRIPTION: Owner CPR/CCD #: RFI: DATE: LABOR HOURS RATE TOTAL FIELDTECHNICIAN 50 X $ 68.00 - $ 3,400.00 SUPERINTENDENT 14 X $ 73.00 - $ 1,022.00 X - $ - X - $ X - $ - X - $ - X - $ SUBTOTAL $ 4,422.00 SMALL TOOL ALLOWANCE @ 0.00% $ - SUBTOTAL $ 4,422.00 MARK-UP @ 15.00% $ 663.30 TOTAL LABOR $ 5,085.30 MATERIALS/EQUIPMENT PHASE CODE UNITS RATE LUMBER X $ 8,960.00 $ 8,960.00 X - $ - X - $ X - $ X - $ - X - $ - SUBTOTAL $ 8,960.00 USE TAX ON MATERIALS AND EQUIPMENT 0.00% $ - MARK-UP @ 15.00% $ 1,344.00 TOTAL MATERIAL/EQUIPMENT $ 10,304.00 SUBCONTRACTS PHASE CODE UNITS RATE X - $ - X - $ - X - $ X $ X $ X $ X S SUBTOTAL MARK-UP @ TOTAL SUBCONTRACTS PROPOSALSUBTOTAL BONDS/Liability/Builders Risk/B&O Tax PROPOSALTOTAL 6.00% 0.00% $ 15,389.30 $ 15,389.30 W J F— LU DC H J H W i oc a 0 w U 0 � G r a 5 u 0 0 0 0 W 5 z a g a a 0 U W a z 0 O G G G G Lm'IzSp zGo �9r 2 G 2. LL c .. c c c c 0 � o ma m main cl) "4--- Z 0 Z 0 c� R a W z= W to W o � (� Z o 0 vZ W � k z w k z w a O z w o 0 Q OU Mo CO V 60 J_ ti Z 0 LLI ti 9 Z 0 Z O f Z � ® L V > li = N O Z O 5 O a z W 0 p 00 W Z Q z Oz F-��zax Z Z a j f Y d I \\ � � k _ � k � - - - - - - - - - | k - § \\� / . \} �-- -A so - _ 4 - l. - � - 4 ]§ - -- - OR- _ ({ �( 4 _ 2 7,_ _20, \ \ 4 M!/m \ 4 \\ =a L-101,IN � � mv