HomeMy WebLinkAboutCO 2CAG-20-006, CO #2-20 CITY OF RENTON Community Services Department CONTRACT CHANGE ORDER AGREEMENT CONTRACT: CAG-20-006 5/28/2020 CONTRACTOR: Emtech, LLC. CHANGE ORDER: #2 SUMMARY OF PROPOSED CHANGE: Reason/Justification: During construction, the Contractor discovered a pile assembly was floating several inches above the existing footing. This Change Order addresses the modifications required for the Contractor to replace the timber footing with a concrete strip footing as recommended by the Engineer. DESCRIPTION: Item No. Qty. Description Unit Price Amount w/ WSST 1 1 Pile Assembly Footing Replacement $ 7,769.40 $ 8,546.34 Total this Change Order: 1 $ 8,546.34 ORIGINAL CONTRACT AMOUNT (W/ WSST) CURRENT CONTRACT AMOUNT NET CHANGE THIS ORDER (W/ WSST) REVISED CONTRACT TOTAL AFTER CHANGE $ 367,400.00 $ 384,328.23 $ 8,546.34 $ 392,874.57 Additional Calendar Days: (0) No Extension of Time. Completion Date is December 30, 2020. The payment specified and agreed to in this change order includes every claim by the contractor for any extra payment with respect to the work described in this change order. The work covered by this change order must be performed under the same terms and conditions as that included in the original agreement. All of the other terms of the original agreement remain in effect. SIGNATURES: Contractor:: *,10 Date: 6/2/2020 �I� Project Manager: Date 6/2/2020 0 emtech To: Betsv Severtsen NarKs Manning ana Natural Kesources 1055 S. Grady Way Renton, WA 98057 Re: Replacing footing at location called out on RFI 001A Scope of Changes: Change Order Emtech, LLC 1133 Kresky Ave. STE 106 Centralia, WA 98531 (360) 748-4891 Date: 5/28/20 CO No. 002 Rev#: 1 RFI No. 001A Providing labor and materials to completely replace timber footing per sheet S-5, Sec. 4 of plans below pile assembly as called out in RFI 001A (see attached RFI for reference). Total price per attached breakdown: $7,769.40 State and local sales tax: included X not included Extension of time: 0 We have proceeded with the work X Work will not proceed without formal authorization This price is good for 30 days from the above date, after which this request is subject to revision. Sincerely, »Pon Ben Booher, General Manager Emtech, LLC. CHANGE ORDER REQUEST SUMMARY Cedar River Bridge Repairs PCO: RR: �DATE: DESCRIPTION: Owner CPR/CCD #: LABOR HOURS RATE TOTAL FIELD TECHNICIAN 24 X $ 68.00 - $ 1,632.00 X - $ X - $ - X - $ X - $ - X - $ - X - $ SUBTOTAL $ 1,632.00 SMALL TOOL ALLOWANCE @ 0.00% $ - SUBTOTAL $ 1,632.00 MARK-UP @ 15.00% $ 244.80 TOTAL LABOR $ 1,876.80 MATERIALS/EQUIPMENT PHASE CODE UNITS RATE Concrete X $ 800.00 $ 800.00 Hardware X $ 500.00 - $ 500.00 Form X $ 259.00 - $ 259.00 Shoring X $ 1,739.00 - $ 1,739.00 Rebar X $ 600.00 - $ 600.00 Bases X $ 1,226.00 - $ 1,226.00 SUBTOTAL $ 5,124.00 USE TAX ON MATERIALS AND EQUIPMENT 0.00% $ - MARK-UP @ 15.00% $ 768.60 TOTAL MATERIAL/EQUIPMENT $ 5,892.60 SUBCONTRACTS PHASE CODE UNITS RATE X - $ - X - $ - X - $ X $ X $ X $ - X $ SUBTOTAL $ - MARK-UP @ 6.00% $ TOTAL SUBCONTRACTS $ - PROPOSAL SUBTOTAL $ 7,769.40 BONDS/Liability/Builders Risk/B&O Tax 0.00% $ - PROPOSAL TOTAL $ 7,769.40 CITY OF RENTON TRANSMITTAL LETTER • Community Services Department Parks Planning and Natural Resources . To: David Reich Transmittal No.: RFI #001A Response Address: Emtech Date: 05.20.20 1133 Kresky Ave. Suite 106 Copy to: Micah Carlson, Adrianah Heike, Alan Centralia, WA 98531 Wyatt, Leslie Betlach, Garth Nelson Contract # CAG-20-006 Routing Sent Received Project Title Cedar River Trestle Bridge Repairs Contractor X Owner X X Contractor Emtech, LLC Consultant X X Owner I X I X Contractor I I X X❑Attached X❑For Your Information ❑Returned for corrections Under separate cover via For review and comment Request for Information 11 []Approved as Noted Remarks: Attached RFI Response 001A. City of Renton requests that Emtech provide a Scope of Work proposal for City's connsideration to perform the recommendations outlined by the Engineer in the RFI Response. Item No. Copies Date Spec. Section Description Rev. Action Reviewer Comments 1 1 05.20.20 Dwgs. S-1 Pile Assembly and Footing As Noted WSP As Noted NET - No Exceptions Taken; MCN - Make Corrections Noted; A & R - Amend and Resubmit; R - Rejected; RA - Receipt Acknowledged ; SI - Submit Specified Item MA. We have verified that the material or equipment contained in this submittal meets all the requirements, including coordination with all related Work, as specified, no exceptions. F-1B. We have verified that the material or equipment contained in this submittal meets all the requirements specified, except the attached deviations. No. Deviation Submitted by: Betsy Severtsen Date: 05.20.20 1055 South Grady Way, 6th Floor; Renton, WA 98057 0 tech Request for Information Project Name: I Cedar River Trail Trestle Bridge Repairs To: Parks Planning & Natural Resources 1055 S. Grady Way Renton, WA 98057 Attn: Betsy Severtsen Action Requested X Clarification Possible Effect X Direction Approval Alternate Proposal Other: Reference Drawing No: S-1 RFI Emtech,LLC 1133 Kresky Ave STE 106 Centralia, WA 98531 360-748-4891 Contract No. CAG-20-006 RFI No. 001 Date: 5/19/20 Desired Response: 5/21/20 Increase/Decrease Cost Increase/Decrease Time No Change Detail No: Spec. Section: Article: Description: The pile assembly circled in red (see attached) is floating several inches above the old timber footing. It is hanging from the bridge, completely free from the old footing. Our crew noticed this after clearing away some brush to begin shoring. We would like to confirm the five locations that will recieve concrete footings as called out in the plans are correct. Adrianah Heike, Asst. Project Manager, Emtech LLC Subm fitter Response: In review of the for construction plans, from April 2020 and the previous inspection reports the footings to be replaced at bents 3,4,6,7, and 17 are correct. Looking at photos from previous inspection it appears that this footing has settled and it is our recommendation that this footing be replaced as shown on the attached concrete strip footing sketch. Respondent 20 May 2020 Date L C L z O w Q NIW «0 L Un X Q +"U m O O O O O O z F— O O LL F— W F- W V Z O V Zo O' c� � II r-I V w W a N U cn 0 N 0 N m 0 N U (D U) CL Cl) i SINHWIIDOQ QIS " ry w m -��I � Jo a. I Ja z Loy _- - _ w N ¢ w saf w � a3F a3E I I "' 0_ � o o .. Oil ® I I ¢ z i W u o > O M013933S3NMIM p tea oo ¢ LL —__—__—__—__—__— a N x0 a rZ w U G I I I z I I I I U I I I I I I c I I Y I I I I I I _ LIJ I I I I I I * I I L I �M a H I I I I a I I I I I I J I I I I a I I I I I s„9-,95 I Z I N I I I O I m I I I a' z all Z� g ' 4 ori I I I m I I I I I I I I i F I I I I *I * I I I I I I I I O H I I I I I I I I I I I I � a�a I -- �� o o i m I I a 3AOSV 33S 3NnH7ItlW OOP 0 I I I 'psNe6eN siq&8 IIN .ouI VS(1 dSM a 14BuAAoO 6s'P'LOS Zps6xQ�gOtl LOL00'6LMSLGAkMIs+sPs3,D'ell� WV BSB 6LOL'B �sO:uo 6LOSL9NO5f1:M GsnsS lss�