The following is our response and approval for various design changes to the water mains related to the Weatherly Inn development at 4500 Talbot Rd S:
1. Installation of additional horizontal bends at northwest corner of site
I have evaluated the request for the installation of 2 additional horizontal 45° bends on the new water line at the northwest corner of the site to avoid a conflict with an existing
underground power conduit.
I am approving the installation of the 2- 45° bends subject to the use of Megalug-type retainer glands on the 2 MJ bends and also with the installation of concrete thrust blocks per
city standard plan no. 330.2.
2. Revision to connection to existing water line at southeast corner of site
I have visited the site on Friday 6/25/20 to evaluate the revised connection from the new on-site water main to the existing 10-inch water line near the southeast corner of the site.
A combination of horizontal and vertical bends will be required to connect the new on-site 10-inch water stub to the existing stub on the south side of the site.
After the poly-pigging cleaning, pressure testing and disinfection of the new on-site water mains, the connection from the new 10-inch stub to the existing line can be made by city forces
with the use of a combination of horizontal and vertical bends. The contractor shall provide all required fittings, shackle rods, and materials for city forces to make the final connection.
The contractor shall install concrete horizontal and vertical blocks at the bends and backfill the trenches.
The city will notify affected water customers regarding the shut-down of the existing water main to perform the connection.
After all satisfactory testing and disinfection of the new water mains, the contractor shall coordinate with the city’s inspector Tom Main to schedule the final connections by city forces
of the new water mains to the existing mains. The contractor shall kept “as-built” sketches and photos of the final connections and shall provide them to the engineer of records for
the preparation of the final as-built plans.
3. Revision to sizing of fire sprinkler stub and DDCVA
The request to change the size of the fire sprinkler stub and DDCVA from 4-inch to 6-inch is approved. Please note that the vault for the 6-inch DDCVA is larger than the one for the
4-inch. Please refer to city standard plan no. 360.2. If a 4-inch valve is already installed at the main line 10”x4”tee, we would allow the installation of a 4”x6” increaser subject
to its approval by the fire sprinkler designer/contractor. It is our understanding the revised sizing of the fire sprinkler stub and DDCVA has been confirmed with a fire sprinkler
designer. The installation of the fire sprinkler piping behind the new DDCVA vault to the building must be inspected by the Regional Fire Authority (RFA) and the contractor must be
a state-certified fire sprinkler contractor. Please make sure that the required permit has been applied for and obtained from RFA.
Please let us know if you have any questions on this matter and thank you for your patience and cooperation.
Sincerely,
Abdoul Gafour
Water Utility Engineering Manager
City of Renton Public Works
1055 S Grady Way
Renton, WA 98057
425-430-7210
206-406-0027 cell
agafour@rentonwa.gov
From: Ross Jarvis <ross.jarvis@scjalliance.com>
Sent: Friday, June 26, 2020 12:07 PM
To: Jonathan Chavez <JChavez@Rentonwa.gov>; Cobi Clark <cobi@accrete.build>; Mark Richardson <mark@accrete.build>; Frank Durocher <frank@rjdevelopment.com>; Abdoul Gafour <Agafour@Rentonwa.gov>
Cc: Thomas Main <TMain@Rentonwa.gov>; Joel Mccann <JMccann@Rentonwa.gov>; Justin T. Johnson <JTJohnson@Rentonwa.gov>; Nick Rawlins <NickR@rinocon.com>
Subject: RE: Erosion Control
Jonathan, we were recently notified that the fire line needed to increase in size from 4” to 6”. The attached water plans indicate this change and have been clouded.
Thanks,
Ross Jarvis, PE
SCJ Alliance
Principal, Civil Engineering Manager
o. 360.352.1465, ext. 131
m. 206.778.1636
www.scjalliance.com <http://www.scjalliance.com/>
From: Ross Jarvis <ross.jarvis@scjalliance.com>
Sent: Thursday, June 18, 2020 4:40 PM
To: 'Jonathan Chavez' <JChavez@Rentonwa.gov>; 'Cobi Clark' <cobi@accrete.build>; 'Mark Richardson' <mark@accrete.build>; 'Frank Durocher' <frank@rjdevelopment.com>
Cc: 'Thomas Main' <TMain@Rentonwa.gov>; 'Joel Mccann' <JMccann@Rentonwa.gov>; 'Justin T. Johnson' <JTJohnson@Rentonwa.gov>; 'Nick Rawlins' <NickR@rinocon.com>
Subject: RE: Erosion Control
Jonathan, please see attached for the proposed connection at the SE corner. The existing water line was a couple feet west of where the utility locate indicated it would be. Please
note the contractor potholed the area and determined the existing shackles and deadman were not installed as indicated on the as-builts.
Please redline any additional conditions on the approved plans.
Please keep us apprised of your review of this connection as well as the revisions at the northwest corner by the main driveway.
Thanks,
Ross Jarvis, PE
SCJ Alliance
Principal, Civil Engineering Manager
o. 360.352.1465, ext. 131
m. 206.778.1636
www.scjalliance.com <http://www.scjalliance.com/>
From: Jonathan Chavez <JChavez@Rentonwa.gov>
Sent: Wednesday, June 17, 2020 12:51 PM
To: 'Cobi Clark' <cobi@accrete.build>; Mark Richardson <mark@accrete.build>; Frank Durocher <frank@rjdevelopment.com>
Cc: Thomas Main <TMain@Rentonwa.gov>; Joel Mccann <JMccann@Rentonwa.gov>; Justin T. Johnson <JTJohnson@Rentonwa.gov>; 'Ross Jarvis' <ross.jarvis@scjalliance.com>; Nick Rawlins <NickR@rinocon.com>
Subject: RE: Erosion Control
Cobi,
Thank you for taking care of this, please have Tom or the inspector on duty verify this. Also, I have not received the erosion control reports for the last couple of weeks; I will need
to those reports.
As for the water revision, I will get back to you either end of today or tomorrow.
Thanks for your patience,
Jonathan
From: Cobi Clark <cobi@accrete.build>
Sent: Tuesday, June 16, 2020 1:30 PM
To: Jonathan Chavez <JChavez@Rentonwa.gov>; Mark Richardson <mark@accrete.build>; Frank Durocher <frank@rjdevelopment.com>
Cc: Thomas Main <TMain@Rentonwa.gov>; Joel Mccann <JMccann@Rentonwa.gov>; Justin T. Johnson <JTJohnson@Rentonwa.gov>; 'Ross Jarvis' <ross.jarvis@scjalliance.com>; Nick Rawlins <NickR@rinocon.com>
Subject: RE: Erosion Control
Jonathan:
These items have been resolved. Do you have a status updated on the approval of our driveway utility plan?
Thank you,
Cobi
From: Jonathan Chavez <JChavez@Rentonwa.gov>
Sent: Thursday, June 11, 2020 3:16 PM
To: Mark Richardson <mark@accrete.build>; Frank Durocher <frank@rjdevelopment.com>
Cc: Thomas Main <TMain@Rentonwa.gov>; Joel Mccann <JMccann@Rentonwa.gov>; Justin T. Johnson <JTJohnson@Rentonwa.gov>; 'Ross Jarvis' <ross.jarvis@scjalliance.com>; Cobi Clark <cobi@accrete.build>
Subject: Erosion Control
Importance: High
Good afternoon Mark,
The following items have been brought to my attention today. The following erosion control items must be addressed before ANY utility work can continue as of the time of this email:
* Silt Fence is missing at the front of the site. Install silt fence per the approved Erosion Control Plan.
* Silt in the driveway CB must be cleaned out and inspected.
* Truck wash is not currently operational. Please rectify.
* Stockpiles are not covered. Cover all stock piles per the approved Erosion Control Plan.
As soon as these items are addressed, call in the erosion control inspection so that utility work can resume.
Best Regards,
Jonathan Chavez, P.E.
Civil Engineer III | Dev. Eng. | CED
City of Renton
1055 S. Grady Way, Renton, WA 98057
jchavez@rentonwa.gov <mailto:jchavez@rentonwa.gov>
Hours: Mo -Thu, 7AM-3:30PM
COVID-19 UPDATE
City Hall is currently closed to the public but we are still available to assist you.
* Pay Invoice and Apply for Over-the-Counter Permit: Permitting Portal <https://permitting.rentonwa.gov/#/home>
* Schedule an Inspection: Permitting Portal <https://permitting.rentonwa.gov/#/home> -OR- Building: 425-430-7202; Civil/Site: 425-430-7203
* Contact Staff:
* Staff Hours: Monday through Thursday 8 a.m. to 4 p.m. (Closed Fridays) between May 22, 2020 and July 24, 2020 to help the economic challenges the City is facing from COVID-19
* Building or General Permitting: permittech@rentonwa.gov <mailto:permittech@rentonwa.gov?subject=Inquiry%20from%20Website> or 425-430-7200
* Planning: planningcustomerservice@rentonwa.gov <mailto:planningcustomerservice@rentonwa.gov?subject=Inquiry%20from%20City%20Website> or 425-430-7294
* Public Works Permitting: pwpermitting@rentonwa.gov <mailto:pwpermitting@rentonwa.gov?subject=Inquiry%20from%20City%20Website> or 206-402-8626
* Code Compliance: Renton Responds <https://rentonwa.gov/cms/one.aspx?portalId=7922741&pageId=15833143> or 425-430-7373.