HomeMy WebLinkAboutInspector's Daily Reports - 8/15/2016 .b
y, 000000,® 0c:wof .- INSPECTOR'S DAILY REPORT
� ( Duvall Ave NE Pavement Preservation Project
Contract#CAG-16-004, Fed Aid No: STPUL-1113(003)
Page 1 of 4
�� II IIII I III IIII IIIIII I II IIIIIIII I IIII III VIII III II � �
- •
!7T:O7Oam
`03854 708-Inspector's Daily Reports 08/15/2016" ••- Monday,August 15, 2016
Inspector: dd Freih Inspector's Shift Hrs: 7:OOam TO 3:30pm
Temp Sky Time Temp Sky
61 Clear 3:30pm 83 Clear
SID Contractor a resentativen�tle ID Contrac#ori e
Re resentative%Titl
A Icon Materials Bill Johnson/Foreman F
—.�._...._—_...-..._�......._._.__._........-..........___ _.............__ __.-...................................._.
B AGS Jessie Dillard/TCS G
C NW Traffic Scoff Hoefling/Foreman I
--............._._.._._..........__._......___.--._._..._..---- – —
D J
-._—......... ....................__—.............. ._-_....................._.-.�.__..._...........---- ---..............
......
__.__.._...
...........
....
_......
....
._-
E K
,Work Activity
SID . • Descri tion _ Location_ _ Crew, , E ui
A Placing HMA for the Sta. 36+85-49+38R +/- 6M,1 F Water trk, F250 P/U, 2 F450
pavement repairs U/T, Cat CS 563C Roller, Cat
CB54B Roller, JD backhoe,
Ranco grader,Case Exc. Cat
140H grader. Cat Paver.
B Traffic control All 2F, 3M 2PCMS, 2Arrow boards, F150
P/U
C NW Traffic 18-22+00+/- 4M International U/T Curb
machine
Traffic Control
Was Traffic Control Req'd Today? _Yes Was WZTC per approved TCP? Yes
Comments: .
DeliveryMaterial
Todd� i/c 8-15-2016
Inspector's Signature Date
� . 15. mo
Re ewed By(Signature) Date
Citvof r , M INSPECTOR'S DAILY REP®RT
�n Duvall Ave NE Pavement Preservation Project
Contract#CAG-16-004, Fed Aid No: STPUL-1113(003)
Page 2 of 4
viswal Inspection
Descri on tiest.Vit, Unit per ROM/QPL?
Onsite
In/Out of
i lime Material Descri�tion Location/Ofifset Conformance
None
Me iscussion
7:00am Crews are on-site removing the wee at NE 9th St. in preparation for paving_AGS has established T/C.
8:00am Icon is placing HMA at Sta. 36+85,40+00, 64R. AGS is preparing for the extruded curbing at the medians.
---......--....... __...........................................__...._.
Is on-site to place the extruded curb at Sta. 18+00-21+00 +/-. The mold for the curbing is not placing material
in a satisfactory manner; the crews are attempting to make adjustments. Icon continues to place asphalt a
9:0.0_ am Sta.42+50, 64R +/-.
NW Traffic is placing Ext. Curbs in the southern median (Sta. 18-22+00), Icon continues to place HMA at Sta.
3+00, 64R.AGS continues to provide T/C for all work. I have contacted Casey with KC Testing to take samples
10:OOam of the extruded curb; he stated that he will be available in approxi 2 hours.__— __ -
-- -._..............._.....— -............................................_
Paving continues at Sta. 45+50, 64R+/-, NWT continues to place curb at the southern median.
10:30am
11:30am Paving continues at Sta_48+50, 64R+/-, NWT continues to place curbs
............._.. .......... ............................................... _...
__...._._._. __. ............................
NWT has stopped placing curb due to equipment failure. Icon is placing wedges at the intersection of 9th and a
12:30pm Sta.36+85, 64R.
Icon is placing temp markings on new surface to allow opening of the left lane to traffic. The electrical contractor
1:30pm on the Chelan Plat is taking trees down next to the roadway on Duvall with no spotters or traffic control.
_...._._.__..—.._.................._._. ......... _._ --. .. .................. . ---- ..._........_..
I have sent photos of the extruded curbs to Ken and Flora; the finish is uneven from excess hand work done to
compensate for the mold. Icon has placed temporary marking tape on the roadway from 8th to 10th. I have no bid
item for tape. The material approved for temp markings is paint. T/C is being adjusted to allow use of the left
2:OOpm_northbound lane from Stn to.._1.Otn_.._..._..- ----._...._....._._. ._..._........_......................................................_..........................._......._.....-.- _-- _...................................._............._........................_............._........_
3_OOpm _ Icon has finished for the day, AGS is adjusting T/C
3:30pm_Work is finished for the day.—
Tcicl6-4 8/15/2016
Inspector's Signature Date
Y , ' ' • '
,'
ZZ'A• 41:Ir-
r4 — T
NW Traffic is placing ext. curb in the
Asphalt Repair
il
I
r '�` ►ti 9 �S. i 161; "tl! �.a
22V y ba.Y "4 K rn.-i S}hSf, t.
--' •
Icon. placinga wedgeat the end of
p �Ciwnr INSPECTOR'S DAILY REPORT
,ter
Duvall Ave NE Pavement Preservation Project
Contract#CAG-16-004, Fed Aid No: STPUL-1113(003)
Page 4of4
Todd/;e/x 8/15/2016
Inspector's Signature Date