HomeMy WebLinkAboutInspector's Daily Reports - 10/12/2016 t f ® INSPECTOR'S DAILY REPORT
— ` Duvall Ave NE Pavement Preservation Project
<�
Contract#CAG-16-004, Fed Aid No: STPUL-1113(003)
Page 1 of 3
��I�����III�II��I�II�I�I�I�IIIII�II����II�I���IIII��I���II���II�IIII�I�III�I�I��IIIIII�II�I���I�III����III��I W. -
54 708-Inspector's Daily Reports 10/12/2016` ednesday, October 12,
16
Inspector: Todd Freih Inspector's Shift Hrs: 7:30pm To
Weather: Time Temp Sky Time Temp Sky
7:30am 39 Clear
ID Contractor Represeritative/Title ID Contractor Representative/Title
A Icon Materials Bill Johnson/ Foreman F
-...._ - -- -----.............................................._...--- .....----- -
B AGS Marla Dawson/TCS G
-- -...---.._.._....._...._._................----........................---.._.... ------- __._._...-- - -........._........._.........._....__..._.........—.._......._.._........_... —----
C Cascade Utilities Ken Mann/Owner I
D J
---- -........._....................................._.................................._..._._......................- -- -----............................_....._...................._..................._.._............_......_..._._...._........_.....---......................_................................................_...
_.._
E K
Work Activity
ID Description Location Crew Equip
A
B
C
Traffic Control
Was Traffic Control Req'd Today? Yes Was WZTC per approved TCP?
.._..........._...................._.._.— .........._..................---- --- - --- --..._.__...__...._..__...............-------
Comments:
visual Insoil
—01Pe- ion
I)escr�iption4EstQt Unit per ROM/4�u�?
Tcicl fi°ei/c 10/12/2016
Inspector's Signature Date
2� p
1 vi By (Signature) Dat
l:rtpu!': INSPECTOR'S DAILY REPORT4i
Duvall Ave NE Pavement Preservation Project
Contract#CAG-16-004, Fed Aid No: STPUL-1113(003)
Page 2 of 3
Onsite
-
In/OIII ffi
i�Tffl me Material Descri.tion LocationlOffset��lllllllllI Conorce
ll
None
iIT Discussion
7:30am GS is on-site preparing-for the day.
- ----._.._......__..__....._.-.......... --- ----._..................................__......_................._......._......_._..........._................_.._.._...__.._-..._..._........_.._..-----....-.-.....-........----.......-�—
Icon is on-site, Cascade is on-site preparing to place sealant around the utilities and remove old castings from
8:30am the site.
9:00am Cascade is placing AR4000 beginning at Sta. 47+00L +/-.
10:00am Cascade has finished all the structures in the southbound lanes and are beginning work in the northbound_lanes.
10:30am Icon is replacing RPMs removed during utility adjustments, AGS is providing T/C.
11:30amII work has finished.
--.....__...........................................................................................................................................................
Tdd fi�ei/c 10/12/2016
Inspector's Signature Date
' p ®Gtv of INSPECTOR'S DAILY REPORT
Duvall Ave NE Pavement Preservation Project
Contract#CAG-16-004, Fed Aid No: STPUL-1113(003)
Page 3 of 3
f' Subject:
Utility Adjustment
Location:
Sta. 47+OOL +/-
Comment:
Cascade is applying sealer to the
adjustments.
Subject:
yi Utility Adjustments
q <
Location:
- 30+OOR +/-
Comment:
Cascade is removing old castings
from the site
Subject:
RPMs
- — sw�ni
25
Location:
N E 6th St.
- Comment:
16612/2616
Icon is replacing the center line at 6th
Todd 15-4a 10/12/2016
Inspector's Signature Date