HomeMy WebLinkAboutCO 3CAG-19-243, CO #3-20
CITY OF RENTON
Community Services Department
CONTRACT CHANGE ORDER AGREEMENT
CONTRACT: City of Renton 6-19.2020
CAG-19-243 Sunset Neighborhood Park, Phase 2
CONTRACTOR: Terra Dynamics, Inc.
CHANGE ORDER: No. 3
SUMMARY OF PROPOSED CHANGE:
Reason/Justification:
Extension of contract time due to Impact of COVID-19 construction delays and requirements. Extend
contract time 109 calendar days from June 13, 2020 to September 30, 2020 to complete substantial
and final acceptance of park development.
DESCRIPTION:
Additional Calendar Days:
(109 calendar days) Completion Date is September 30, 2020
The payment specified and agreed to in this change order Includes every claim by the contractor for any
extra payment with respect to the work described in this change order. The work covered by this change
order must be performed under the same terms and conditions as that included in the original
agreement. All of the other terms of the original agreement remain in effect.
SIGNATURES:
Contractor: (/..,Wlr 011 Date: 6232010