Earth Solutions NW, LLC
LETTER OF TRANSMITTAL
15365 NE 90th Street, Suite 100 Redmond, WA 98052
(425) 449-4704 FAX (425) 449-4711
To: RJ Development Date: July 17, 2020
401 Central Street SE ESNW No.: ES- 895.06
Olympia, WA 98501 Project: Weatherly Inn
Attn: Mr. Duane Meyer
Email: duane@accrete.build
No. of
Copies Date Description
1 7/6-7/10/20 Daily Field Report(s) # 191-194
Comments:
CC:
1: John Wilson ATTN: johnw@rinocon.com
2: Mark Richardson ATTN: mark@accrete.build
3: Jeff Bennett ATTN: jeffb@accrete.build
4: Jennifer Vogele ATTN: jennifer@accrete.build
5: Jonathan Chavez ATTN: jchavez@rentonwa.gov
6: Joe W ATTN: joew@accrete.build
Transmitted By: Earth Solutions NW, LLC
PM: Scott Riegel, L.G., L.E.G.
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 191
Time On Site Time Off Site Date Day of Week
4:45 PM 5:00 PM
7/6/20 Monday
Travel Time Weather
1.25 Hr. RT 70soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No. Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe slab backfill, water line backfill and earthwork activities.
Slab Backfill
While onsite, rep observed contractor use a medium sized excavator to place material for slab backfill. Rep
observed contractor place native gray silty sand with gravel material for the slab. Rep will return tomorrow, July
7, 2020, to observe and test the compaction of the slab backfill.
Water Line Backfill
Rep observed the prior to arrival that contractor had used a medium sized excavator to excavate a water line
trench (W8’xL8’xD5’) at the southwest corner of the site. Rep observed that excavation was intended for the
water line tie in. Contractor expressed plans to continue water line backfill tomorrow.
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
1/1
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 1 of 2 192
Time On Site Time Off Site Date Day of Week
2:45 PM 3:45 PM
7/7/20 Tuesday
Travel Time Weather
1.25 Hr. RT 60soF, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No. Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test slab backfill, water line backfill and earthwork
activities.
Slab Backfill
While onsite, rep observed contractor use a small sized excavator to place material for slab backfill. Rep observed
contractor place native gray silty sand with gravel material for the slab in 6” lifts and compaction with a jumping
jack. Rep took compaction tests and observed material to be adequate of at least 95% of its maximum dry density
(130.7 lbs./cu. ft.).
Water Line Backfill
Rep observed the prior to arrival that contractor had used a medium sized excavator to tie in the water line at the
southwest corner of the site. Contractor expressed plans to continue water line backfill tomorrow, July 8, 2020.
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 2 of 2 192
Time On Site Time Off Site Date Day of Week
2:45 PM 3:45 PM
7/7/20 Tuesday
Travel Time Weather
1.25 Hr. RT 60soF, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No. Permit No.
Test
Number
Test Location
(Slab Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
190 See map for approximate location SG 1 130.7 10.3 124.2 95
191 See map for approximate location SG 1 130.7 11.1 123.8 95
h
190
191
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 1 of 2 193
Time On Site Time Off Site Date Day of Week
9:15 AM;
10:30 AM
9:45 AM;
1:00 PM
7/9/20 Thursday
Travel Time Weather
1.25 Hr. RT 60soF, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No. Permit No.
Test
Number
Test Location
(Water Backfill) Elevation
Reference
Compaction
Curve
Maximum
Dry Density
(pcf)
Fill
Moisture
(%)
Test
Dry Density
(pcf)
% of
Maximum
Dry Density
192 See map for approximate location -4’ 1 130.7 12.1 124.3 95
193 See map for approximate location -2’ 1 130.7 10.3 124.6 95
194 See map for approximate location SG 1 130.7 9.6 124.0 95
195 See map for approximate location -4’ 1 130.7 11.0 123.6 95
196 See map for approximate location -2’ 1 130.7 11.5 123.8 95
197 See map for approximate location SG 1 130.7 11.3 124.2 95
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test water line backfill and earthwork activities.
Water Line Backfill
While onsite, rep observed the prior to arrival that contractor had used a medium sized excavator to tie in the water
line at the southwest and northwest corner of the site. Rep observed trench lines to be W4’xD7’. Rep observed
contractor use a medium sized excavator to place native material in loose 12”-18” lifts and compact with a hoe
pack. Rep took compaction tests and observed material to be adequate of at least 95% of its maximum dry density
(130.7 lbs./cu. ft.).
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 2 of 2 193
Time On Site Time Off Site Date Day of Week
9:15 AM;
10:30 AM
9:45 AM;
1:00 PM
7/9/20 Thursday
Travel Time Weather
1.25 Hr. RT 60soF, Overcast
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No. Permit No.
192-194
195-196
Earth Solutions NWLLC
15365 NE 90th Street, Suite 100
Redmond, WA 98052
Main (425) 449-4704 | Fax (425) 449-4711
www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
AK 0895.06 194
Time On Site Time Off Site Date Day of Week
3:00 PM 3:15 PM
7/10/20 Friday
Travel Time Weather
1.25 Hr. RT 70soF, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site? Project No. Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe and test water line backfill and earthwork activities.
Water Line Backfill
While onsite, rep observed the prior to arrival that contractor had used a medium sized excavator to tie in the water
line at the southwest corner of the site. Rep observed trench lines to be W4’xD7’. Rep observed contractor and
city inspector test the water line onsite. Contractor expressed plans to continue working on water line tie-in and
backfill on Monday, July 13, 2020. Rep will return on Monday to observe and test compaction of the water line as
needed.
ESNW rep will return to observe earthwork activities when requested by client
Andrew Kimn, Senior Technician, 206-430-9183