www.esnw.com DAILY FIELD REPORT
ESNW Rep. Project No. Page Report No.
JTL 0895.06 161
Time On Site Time Off Site Date Day of Week
11:00 AM 12:00 PM 3/24/20 Tuesday
Travel Time Weather
1.00Hr. RT 40s, Clear
Project Name Job Location Client/Owner
Weatherly Inn 4500 Talbot Rd. S., Renton, WA RJ Development, LLC
Contractor #1 Contact Field Supervisor Reviewed
Rino Construction Mike LAC
Contractor #2 Contact Project Manager Reviewed
Ray
Are approved plans/permits on site?Project No.Permit No.
Supplementary Report:
At the client’s request, ESNW rep was onsite to observe cut slopes and test footing backfill.
Cut Slopes
While onsite, rep observed south slopes of the cut slopes to be near vertical and covered in plastic sheeting. Rep
observed that the east slopes of the excavation were near a 0.75:1 (H:V) slope. Although over-steepened, slopes
are stable in current configuration and stable to work within. The contractor is responsible for providing all safety
measures in accordance with state and federal regulation. Rep observed that contractor had sloped the southeast
corner of the footing excavation to a 1:1 (H:V).
Footing Backfill
No footing backfill or compaction was in progress onsite.
ESNW rep will return to observe earthwork activities when requested by client
Jackson Lundgren Field Technician 206-468-0991