HomeMy WebLinkAboutAppellant Ex 1On Wed, Dec 11, 2019 at 5:21 PM Angelea Weihs <AWeihs@rentonwa.gov> wrote:
Hello Vann,
I am out of the office until Wednesday, so for the sake of preventing further delay, please see the
attached waiver form. However, please note that a project description, including the proposed use of
the property, is a submittal requirement. This requirement will not be waived, and it is pertinent for our
review.
Have a great weekend!
Angelea Weihs
Associate Planner, City of Renton
1055 S. Grady Way
Renton, WA 98057
(425) 430-7312
From: Vann Lanz <vann@lnlbuilds.com>
Sent: Wednesday, December 11, 2019 9:58 AM
To: Angelea Weihs <AWeihs@Rentonwa.gov>; Philmon Negusse <pnegusse@gmail.com>; Chip Vincent
<CVincent@Rentonwa.gov>
Subject: Re: confirming pre meeting for new BLA
Angelea,
I am not certain their intentions however I was not aware that information is pertinent for a BLA
as the use is still bound by City of Renton code regardless.
This has been in the City of Rentons court for a while and I would appreciate it if we could wrap
this up shortly. Please call me at your convenience to discuss.
Regards,
Vann Lanz
206-499-1277
On Wed, Dec 11, 2019 at 9:28 AM Angelea Weihs <AWeihs@rentonwa.gov> wrote:
Hello Vann,
What do they want to do with the land? That is the question we are asking.
Thank you,
Angelea Weihs
Associate Planner, City of Renton
1055 S. Grady Way
Renton, WA 98057
(425) 430-7312
From: Vann Lanz <vann@lnlbuilds.com>
Sent: Tuesday, December 10, 2019 6:23 PM
To: Touma Engineers <toumaengineering@gmail.com>; Philmon Negusse <pnegusse@gmail.com>
Cc: Angelea Weihs <AWeihs@Rentonwa.gov>
Subject: Re: confirming pre meeting for new BLA
Angelea,
Following up on this email and our conversation. Is this sufficient? The topography is the
prevailing factor on this one, the only people that have access are the parcels above and this BLA
creates access that is otherwise impossible to achieve.
Regards,
Vann Lanz
LNL Builds, LLC
206-499-1277
On Dec 5, 2019, at 10:32 PM, Vann Lanz <vann@lnlbuilds.com> wrote:
Angelea,
The “upper” portion of the lot that has the odd configuration is separated from the lower half by
a 70’ cliff wall. The adjacent property owner would like to acquire the land as up there it is
relatively pancake flat.
Regards,
Vann Lanz
LNL Builds, LLC
206-499-1277
On Dec 5, 2019, at 6:56 AM, Touma Engineers <toumaengineering@gmail.com> wrote:
I have ccd Vann in this email to let him describe why the lots are configured. He is in
contact with the owners.
Dan
---------- Forwarded message ---------
From: Angelea Weihs <AWeihs@rentonwa.gov>
Date: Wed, Dec 4, 2019 at 4:29 PM
Subject: RE: confirming pre meeting for new BLA
To: Touma Engineers <toumaengineering@gmail.com>
Hello Dan,
This is a very unusual configuration that is proposed. Is there a specific goal or reason?
Thank you,
Angelea Weihs
Associate Planner, City of Renton
1055 S. Grady Way
Renton, WA 98057
(425) 430-7312
From: Touma Engineers <toumaengineering@gmail.com>
Sent: Monday, December 02, 2019 3:02 PM
To: Angelea Weihs <AWeihs@Rentonwa.gov>; Vann Lanz <vann@lnlbuilds.com>
Subject: Re: confirming pre meeting for new BLA
Angelea
Attached is are two sheets showing the existing lot and new lot layouts. let me know if this helps
Thank you for your time
Dan
On Mon, Dec 2, 2019 at 2:20 PM Angelea Weihs <AWeihs@rentonwa.gov> wrote:
Hello Dan,
Brianne confirmed that the TIR can be waived. I need to know what this LLA is called in order to
complete the waiver form. Do you have a name? Also, I am struggling to picture the new vs. old lot lines.
It looks like quite a change. Is it possible for you to highlight in different colors the new vs old lot lines so
that I can accurately picture it and provide feedback?
Thank you,
Angelea Weihs
Associate Planner, City of Renton
1055 S. Grady Way
Renton, WA 98057
(425) 430-7312
From: Touma Engineers <toumaengineering@gmail.com>
Sent: Tuesday, November 26, 2019 11:37 AM
To: Angelea Weihs <AWeihs@Rentonwa.gov>; Vann Lanz <vann@lnlbuilds.com>
Subject: Re: confirming pre meeting for new BLA
Good Morning Angelea
Where you able to look at the information i sent you on the 8th of this month to get a variance
sheet filled out in what is needed for submittial
Thank you \
Dan Touma
On Fri, Nov 8, 2019 at 11:56 AM Touma Engineers <toumaengineering@gmail.com> wrote:
Hi Angelea
Attached are a few of the maps and documents for the boundary line adjustment. This is not a
compete set of items, but I thought is would help with the waiver form for my submittal. I know
the owner has submitted for a building permit and there may be more information that I can add
to my submittal. I hope this helps and have a good vacation
Dan Touma
On Fri, Nov 8, 2019 at 7:07 AM Touma Engineers <toumaengineering@gmail.com> wrote:
Good morning Angelea
Hows your schedule today? I told the contractor I had a meeting today. Please let me know.
Thank you
Dan
On Thu, Nov 7, 2019 at 9:11 AM Angelea Weihs <AWeihs@rentonwa.gov> wrote:
No problem Dan,
I am actually going to be out of the office next week. Would you like to schedule for the following week?
Thanks,
Angelea Weihs
Associate Planner, City of Renton
1055 S. Grady Way
Renton, WA 98057
(425) 430-7312
From: Touma Engineers <toumaengineering@gmail.com>
Sent: Thursday, November 07, 2019 6:52 AM
To: Angelea Weihs <AWeihs@Rentonwa.gov>
Subject: Re: confirming pre meeting for new BLA
Angelea
with the weather being so nice the contractor on this huge paving project is trying to get it done
this week . Can we reschedule again for Monday or Tuesday. I apologize for the changing so
much
Thank you
Dan Touma
On Wed, Nov 6, 2019 at 12:15 PM Touma Engineers <toumaengineering@gmail.com> wrote:
Yes , thank you
Dan
Sent from my iPhone
On Nov 6, 2019, at 9:18 AM, Angelea Weihs <AWeihs@rentonwa.gov> wrote:
Hello Dan,
Does tomorrow at 2pm work?
Thanks,
Angelea Weihs
Associate Planner, City of Renton
1055 S. Grady Way
Renton, WA 98057
(425) 430-7312
From: Touma Engineers <toumaengineering@gmail.com>
Sent: Tuesday, November 05, 2019 5:40 PM
To: Angelea Weihs <AWeihs@Rentonwa.gov>
Subject: Re: confirming pre meeting for new BLA
Angelea
how is your Thursday look. Sorry i have to go back in the field tomorrow
Dan
On Tue, Nov 5, 2019 at 12:47 PM Angelea Weihs <AWeihs@rentonwa.gov> wrote:
Hello Dan,
Are you available at 10am tomorrow?
Thanks,
Angelea
From: Touma Engineers <toumaengineering@gmail.com>
Sent: Tuesday, November 05, 2019 7:21 AM
To: Angelea Weihs <AWeihs@Rentonwa.gov>
Subject: Re: confirming pre meeting for new BLA
Angelea
It looks like I have to reschedule out pre meeting today. i am out in the field today. I am open
tomorrow or Thursday. Please at your convenience let me know
Thank you
Dan
On Mon, Nov 4, 2019 at 2:01 PM Touma Engineers <toumaengineering@gmail.com> wrote:
2 will be fine, for some reason i had 10. but 2 is better for me
Thank you
Dan