Perotto Lifts
Construction Dates : The date of construction will depend on when the necessary
government approvals for the lifts are issued. Installation of the lifts and canopy will take
two days to complete. The in-water work window at the site is open from July 16th
through December 31st. The lifts and canopy will be installed during the work window
opening of 2020.
Hours and Days of Operation: The work will take place during the City of Renton’s
typical hours of construction which are 7:00 am through 10:00 pm Monday through
Friday and 9:00 am through 10:00 pm Saturday and Sunday.
Proposed Hauling/Transportation Routes: The lifts and canopy will be brought to the
site by barge.
Measures to be implemented to minimize dust, traffic and transportation impacts,
erosion, mud, noise, and other noxious characteristics: Work will take place only
during allowed hours of operation. Only a couple vehicular trips are required to install
the lifts. Erosion will not be caused by the installation. Noise levels from installation are
very low.
Special Hours Proposed for Construction: No special hours are proposed for
construction.
Preliminary Traffic Control Plan: Traffic control is not necessary for the project.