Loading...
HomeMy WebLinkAbout0895.06 DFR 286, 287A-289A, 290 &291.pdf Earth Solutions NWLLC 15365 NE 90th Street, Suite 100 Redmond, WA 98052 Main (425) 449-4704 | Fax (425) 449-4711 www.esnw.com DAILY FIELD REPORT ESNW Rep. Project No. Page Report No. AES 0895.06 1 of 1 286 Time On Site Time Off Site Date Day of Week 7:00 8:00 3/9/21 Tuesday Travel Time Weather 1 hr. RT 31°F, Overcast Project Name Job Location Client/Owner Weatherly Inn 4500 Talbot Rd S, Renton RJ Development, LLC General Contractor Contact Field Supervisor Reviewed Accrete Construction, LLC Joe LAC/MTK Contractor #2 Contact Project Manager Reviewed SSR Are approved plans/permits on site? Project No. Permit No. As requested by the client, ESNW representative was on-site to observe and test the stormwater discharge to the sewer. Erosion Control – Temporary Upon arrival, ESNW rep. tested the pH and conducted an Imhoff Cone test to measure settleable solids of the stormwater in the onsite vault. ESNW rep. measured a pH of 11 and 0.0 mL/L of settleable solids were observed, which is suitable for discharge into the sewer system. Onsite crews began discharging into the sewer system at a rate of 190 GPM. Daily discharge amount shown on the monthly Industrial Waste Program Self-Monitoring Report. ESNW rep. will return as requested. Alexandra Shaner Senior Field Technician (206) 355-877 Earth Solutions NWLLC 15365 NE 90th Street, Suite 100 Redmond, WA 98052 Main (425) 449-4704 | Fax (425) 449-4711 www.esnw.com DAILY FIELD REPORT ESNW Rep. Project No. Page Report No. AES 0895.06 1 of 1 287A a Time On Site Time Off Site Date Day of Week 7:00 8:00 3/10/21 Wednesday Travel Time Weather 1 hr. RT 37°F, Overcast Project Name Job Location Client/Owner Weatherly Inn 4500 Talbot Rd S, Renton RJ Development, LLC General Contractor Contact Field Supervisor Reviewed Accrete Construction, LLC Joe LAC/MTK Contractor #2 Contact Project Manager Reviewed SSR Are approved plans/permits on site?Project No.Permit No. As requested by the client, ESNW representative was on-site to observe and test the stormwater discharge to the sewer. Erosion Control – Temporary Upon arrival, ESNW rep. tested the pH and conducted an Imhoff Cone test to measure settleable solids of the stormwater in the onsite vault. ESNW rep. measured a pH of 11 and 0.0 mL/L of settleable solids were observed, which is suitable for discharge into the sewer system. Onsite crews began discharging into the sewer system at a rate of 190 GPM. Daily discharge amount shown on the monthly Industrial Waste Program Self-Monitoring Report. ESNW rep. will return as requested. Alexandra Shaner Senior Field Technician (206) 355-877 Earth Solutions NWLLC 15365 NE 90th Street, Suite 100 Redmond, WA 98052 Main (425) 449-4704 | Fax (425) 449-4711 www.esnw.com DAILY FIELD REPORT ESNW Rep. Project No. Page Report No. AES 0895.06 1 of 1 288A Time On Site Time Off Site Date Day of Week 7:15 8:15 3/11/21 Thursday Travel Time Weather 1 hr. RT 35°F, Clear Project Name Job Location Client/Owner Weatherly Inn 4500 Talbot Rd S, Renton RJ Development, LLC General Contractor Contact Field Supervisor Reviewed Accrete Construction, LLC Joe LAC/MTK Contractor #2 Contact Project Manager Reviewed SSR Are approved plans/permits on site?Project No.Permit No. As requested by the client, ESNW representative was on-site to observe and test the stormwater discharge to the sewer. Erosion Control – Temporary Upon arrival, ESNW rep. tested the pH and conducted an Imhoff Cone test to measure settleable solids of the stormwater in the onsite vault. ESNW rep. measured a pH of 11 and 0.0 mL/L of settleable solids were observed, which is suitable for discharge into the sewer system. Onsite crews began discharging into the sewer system at a rate of 190 GPM. Daily discharge amount shown on the monthly Industrial Waste Program Self-Monitoring Report. ESNW rep. will return as requested. Alexandra Shaner Senior Field Technician (206)355-877 Earth Solutions NWLLC 15365 NE 90th Street, Suite 100 Redmond, WA 98052 Main (425) 449-4704 | Fax (425) 449-4711 www.esnw.com DAILY FIELD REPORT ESNW Rep. Project No. Page Report No. AES 0895.06 1 of 1 289A Time On Site Time Off Site Date Day of Week 8:15 9:15 3/12/21 Friday Travel Time Weather 1 hr. RT 43°F, Partly Cloudy Project Name Job Location Client/Owner Weatherly Inn 4500 Talbot Rd S, Renton RJ Development, LLC General Contractor Contact Field Supervisor Reviewed Accrete Construction, LLC Joe LAC/MTK Contractor #2 Contact Project Manager Reviewed SSR Are approved plans/permits on site?Project No.Permit No. As requested by the client, ESNW representative was on-site to observe and test the stormwater discharge to the sewer. Erosion Control – Temporary Upon arrival, ESNW rep. tested the pH and conducted an Imhoff Cone test to measure settleable solids of the stormwater in the onsite vault. ESNW rep. measured a pH of 11 and 0.0 mL/L of settleable solids were observed, which is suitable for discharge into the sewer system. Onsite crews began discharging into the sewer system at a rate of 190 GPM. Daily discharge amount shown on the monthly Industrial Waste Program Self-Monitoring Report. ESNW rep. will return as requested. Alexandra Shaner Senior Field Technician (206)355-877 Earth Solutions NWLLC 15365 NE 90th Street, Suite 100 Redmond, WA 98052 Main (425) 449-4704 | Fax (425) 449-4711 www.esnw.com DAILY FIELD REPORT ESNW Rep. Project No. Page Report No. AES 0895.06 1 of 1 290 Time On Site Time Off Site Date Day of Week 8:00 9:00 3/13/21 Saturday Travel Time Weather 1 hr. RT 34°F, Partly Cloudy Project Name Job Location Client/Owner Weatherly Inn 4500 Talbot Rd S, Renton RJ Development, LLC General Contractor Contact Field Supervisor Reviewed Accrete Construction, LLC Joe LAC/MTK Contractor #2 Contact Project Manager Reviewed SSR Are approved plans/permits on site? Project No. Permit No. As requested by the client, ESNW representative was on-site to observe and test the stormwater discharge to the sewer. Erosion Control – Temporary Upon arrival, ESNW rep. tested the pH and conducted an Imhoff Cone test to measure settleable solids of the stormwater in the onsite vault. ESNW rep. measured a pH of 11 and 0.0 mL/L of settleable solids were observed, which is suitable for discharge into the sewer system. Onsite crews began discharging into the sewer system at a rate of 190 GPM. Daily discharge amount shown on the monthly Industrial Waste Program Self-Monitoring Report. ESNW rep. will return as requested. Alexandra Shaner Senior Field Technician (206) 355-877 Earth Solutions NWLLC 15365 NE 90th Street, Suite 100 Redmond, WA 98052 Main (425) 449-4704 | Fax (425) 449-4711 www.esnw.com DAILY FIELD REPORT ESNW Rep. Project No. Page Report No. AES 0895.06 1 of 1 291 Time On Site Time Off Site Date Day of Week 1:45 2:45 3/15/21 Monday Travel Time Weather 1 hr. RT 45°F, Partly Cloudy Project Name Job Location Client/Owner Weatherly Inn 4500 Talbot Rd S, Renton RJ Development, LLC General Contractor Contact Field Supervisor Reviewed Accrete Construction, LLC Joe LAC/MTK Contractor #2 Contact Project Manager Reviewed SSR Are approved plans/permits on site? Project No. Permit No. As requested by the client, ESNW representative was on-site to observe and test the stormwater discharge to the sewer. Erosion Control – Temporary Upon arrival, ESNW rep. tested the pH and conducted an Imhoff Cone test to measure settleable solids of the stormwater in the onsite vault. ESNW rep. measured a pH of 11 and 0.0 mL/L of settleable solids were observed, which is suitable for discharge into the sewer system. Daily discharge amount shown on the monthly Industrial Waste Program Self-Monitoring Report. ESNW rep. will return as requested. Alexandra Shaner Senior Field Technician (206) 355-877